This lecture highlights the essential components of software project planning, focusing on how to establish a pragmatic strategy for controlling, tracking, and monitoring complex technical projects. Students learn about scoping, estimation, risk management, scheduling, and control strategies. Emphasis is placed on understanding customer needs, project boundaries, and the importance of documenting project scope and estimates. Various estimation techniques and risk management strategies are also covered, enabling students to foresee potential issues and manage resources effectively to ensure project success.

jamuna
Télécharger la présentation

Effective Software Project Planning Techniques in CS451

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CS451Lecture 5: Software Project Planning[Pressman, Chap 4-7] Yugi Lee STB #555 (816) 235-5932 leeyu@umkc.edu www.sice.umkc.edu/~leeyu CS451 - Lecture 5

  2. Software Project Planning • The overall goal of project planning is to establish a pragmatic strategy for controlling, tracking, and monitoring a complex technical project. Why? • So the end result gets done on time, with quality! CS451 - Lecture 5

  3. The Steps • Scoping—understand the problem and the work that must be done • Estimation—how much effort? how much time? • Risk—what can go wrong? how can we avoid it? what can we do about it? • Schedule—how do we allocate resources along the timeline? what are the milestones? • Control strategy—how do we control quality? how do we control change? CS451 - Lecture 5

  4. Write it Down! Project Scope Estimates Risks Schedule Control strategy Software Project Plan CS451 - Lecture 5

  5. To Understand Scope ... • Understand the customers needs • understand the business context • understand the project boundaries • understand the customer’s motivation • understand the likely paths for change • understand that … Even when you understand, nothing is guaranteed! CS451 - Lecture 5

  6. Cost Estimation • project scope must be explicitly • task and/or functional decomposition is necessary • historical measures (metrics) are very helpful • at least two different techniques should be used • remember that uncertainty is inherent CS451 - Lecture 5

  7. Functional Decomposition functional decomposition Statement perform of Scope a "grammatical parse" CS451 - Lecture 5

  8. Creating a Task Matrix Obtained from process framework” framework activities application functions Effort required to accomplish each framework activity for each application function CS451 - Lecture 5

  9. Conventional Methods: LOC/FP Approach • compute LOC/FP using estimates of information domain values • use historical effort for the project CS451 - Lecture 5

  10. Normalization for Metrics Normalized data are used to evaluate the process and the product (but never individual people) size-oriented normalization —the line of code approach function-oriented normalization —the function point approach CS451 - Lecture 5

  11. Typical Size-Oriented Metrics • errors per KLOC (thousand lines of code) • defects per KLOC • $ per LOC • page of documentation per KLOC • errors / person-month • LOC per person-month • $ / page of documentation CS451 - Lecture 5

  12. CAD System Example: LOC Approach LOC/pm (line of code per month):Organizational average productivity for systems of this type UICF: User interface and control facilities, 2DGA: Two-dimensional geometric analysis 3DGA: Three-dimensional geometric analysis, DBM: Database management CGDF: Computer graphics display facilities, PCF: Peripheral control function DAM: Design analysis modules CS451 - Lecture 5

  13. Typical Function-Oriented Metrics • errors per FP (thousand lines of code) • defects per FP • $ per FP • pages of documentation per FP • FP per person-month CS451 - Lecture 5

  14. Why Opt for FP Measures? CS451 - Lecture 5

  15. Computing Function Points CS451 - Lecture 5

  16. Example: FP(function point) Approach CS451 - Lecture 5

  17. Tool-Based Estimation project characteristics calibration factors LOC/FP data CS451 - Lecture 5

  18. Empirical Estimation Models General form: exponent effort = tuning coefficient * size usually derived empirically as person-months derived of effort required usually LOC but may also be function point either a constant or a number derived based on complexity of project CS451 - Lecture 5

  19. Estimation Techniques • past (similar) project experience • conventional estimation techniques • task breakdown and effort estimates • size (e.g., FP) estimates • tools (e.g., Checkpoint) CS451 - Lecture 5

  20. Estimation Guidelines estimate using at least two techniques get estimates from independent sources avoid over-optimism, assume difficulties you've arrived at an estimate, sleep on it adjust for the people who'll be doing the job—they have the highest impact CS451 - Lecture 5

  21. The Make-Buy Decision CS451 - Lecture 5

  22. Computing Expected Cost expected cost = (path probability) x (estimated path cost) i i For example, the expected cost to build is: expected cost = 0.30($380K)+0.70($450K) build = $429 K similarly, expected cost = $382K reuse expected cost = $267K buy expected cost = $410K contr CS451 - Lecture 5

  23. Risk Management [Pressman chap 6] CS451 - Lecture 5

  24. Project Risks What can go wrong? What is the likelihood? What will the damage be? What can we do about it? CS451 - Lecture 5

  25. Reactive Risk Management • project team reacts to risks when they occur • mitigation—plan for additional resources in anticipation of fire fighting • fix on failure—resource are found and applied when the risk strikes • crisis management—failure does not respond to applied resources and project is in jeopardy CS451 - Lecture 5

  26. Proactive Risk Management • formal risk analysis is performed • organization corrects the root causes of risk • TQM concepts and statistical SQA • examining risk sources that lie beyond the bounds of the software • developing the skill to manage change CS451 - Lecture 5

  27. Risk Management Paradigm control track RISK identify plan analyze CS451 - Lecture 5

  28. Building a Risk Table Risk Probability Impact RMMM Risk Mitigation Monitoring & Management CS451 - Lecture 5

  29. Risk Mitigation, Monitoring, Management • mitigation—how can we avoid the risk? • monitoring—what factors can we track that will enable us to determine if the risk is becoming more or less likely? • management—what contingency plans do we have if the risk becomes a reality? CS451 - Lecture 5

  30. Risk Due to Product Size Attributes that affect risk: • estimated size of the product in LOC or FP? • estimated size of product in number of programs, files, transactions? • percentage deviation in size of product from average for previous products? • size of database created or used by the product? • number of users of the product? • number of projected changes to the requirements for the product? before delivery? after delivery? • amount of reused software? CS451 - Lecture 5

  31. Risk Due to Business Impact Attributes that affect risk: • affect of this product on company revenue? • visibility of this product by senior management? • reasonableness of delivery deadline? • number of customers who will use this product • interoperability constraints • sophistication of end users? • amount and quality of product documentation that must be produced and delivered to the customer? • governmental constraints • costs associated with late delivery? • costs associated with a defective product? CS451 - Lecture 5

  32. Risks Due to the Customer Questions that must be answered: • Have you worked with the customer in the past? • Does the customer have a solid idea of requirements? • Has the customer agreed to spend time with you? • Is the customer willing to participate in reviews? • Is the customer technically sophisticated? • Is the customer willing to let your people do their job—that is, will the customer resist looking over your shoulder during technically detailed work? • Does the customer understand the software engineering process? CS451 - Lecture 5

  33. Risks Due to Process Maturity Questions that must be answered: • Have you established a common process framework? • Is it followed by project teams? • Do you have management support for software engineering? • Do you have a proactive approach to SQA? • Do you conduct formal technical reviews? • Are CASE tools used for analysis, design and testing? • Are the tools integrated with one another? • Have document formats been established? CS451 - Lecture 5

  34. Technology Risks Questions that must be answered: • Is the technology new to your organization? • Are new algorithms, I/O technology required? • Is new or unproven hardware involved? • Does the application interface with new software? • Is a specialized user interface required? • Is the application radically different? • Are you using new software engineering methods? • Are you using unconventional software development methods, such as formal methods, AI-based approaches, artificial neural networks? • Are there significant performance constraints? • Is there doubt the functionality requested is "do-able?" CS451 - Lecture 5

  35. Staff/People Risks Questions that must be answered: • Are the best people available? • Does staff have the right skills? • Are enough people available? • Are staff committed for entire duration? • Will some people work part time? • Do staff have the right expectations? • Have staff received necessary training? • Will turnover among staff be low? CS451 - Lecture 5

  36. Recording Risk Information Project: Embedded software for XYZ system Risk type: schedule risk Priority (1 low ... 5 critical): 4 Risk factor: Project completion will depend on tests which require hardware component under development. Hardware component delivery may be delayed Probability: 60 % Impact: Project completion will be delayed for each day that hardware is unavailable for use in software testing Monitoring approach: Scheduled milestone reviews with hardware group Contingency plan: Modification of testing strategy to accommodate delay using software simulation Estimated resources: 6 additional person months beginning 7-1-96 CS451 - Lecture 5

  37. Project Scheduling and Tracking Pressman Chap 7 CS451 - Lecture 5

  38. Why Are Projects Late? • an unrealistic deadline established by someone outside the software development group • changing customer requirements that are not reflected in schedule changes; • an honest underestimate of the amount of effort and/or the number of resources that will be required to do the job; • predictable and/or unpredictable risks that were not considered when the project commenced; • technical difficulties that could not have been foreseen in advance; • human difficulties that could not have been foreseen in advance; • miscommunication among project staff that results in delays; • a failure by project management to recognize that the project is falling behind schedule and a lack of action to correct the problem CS451 - Lecture 5

  39. Scheduling Principles • compartmentalization—define distinct tasks • interdependency—indicate task interrelationshipsffort validation—be sure resources are available • defined responsibilities—people must be assigned • defined outcomes—each task must have an output • defined milestones—review for quality CS451 - Lecture 5

  40. Defining Task Sets • determine type of project • assess the degree of rigor required • identify adaptation criteria • compute task set selector (TSS) value • interpret TSS to determine degree of rigor • select appropriate software engineering tasks CS451 - Lecture 5

  41. Example CS451 - Lecture 5

  42. Define a Task Network CS451 - Lecture 5

  43. Effort Allocation • “front end” activities • customer communication • analysis • design • review and modification • construction activities • coding or code generation • testing and installation • unit, integration • white-box, black box • regression 40-50% 15-20% 30-40% CS451 - Lecture 5

  44. Tools: Timeline Chart CS451 - Lecture 5