1 / 27

HRMT#6 – TPSG4 Safety review

HRMT#6 – TPSG4 Safety review. J. Borburgh. With input from: C . Baud, D. Brethoux, M. Delonca, B. Goddard. Outline. TPSG4 experiment Technical description Preparation & Installation Operation phases Post-irradiation and Disposal Hazards Risk analysis Conclusions.

jazlynn
Télécharger la présentation

HRMT#6 – TPSG4 Safety review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HRMT#6 – TPSG4Safety review J. Borburgh With input from: C. Baud, D. Brethoux, M. Delonca, B. Goddard

  2. Outline • TPSG4 experiment • Technical description • Preparation & Installation • Operation phases • Post-irradiation and Disposal • Hazards • Risk analysis • Conclusions TPSG4 test at HRMT#6

  3. Purpose of TPSG4 Protect Magnetic septa in SPS LSS4 extraction channel from damage by the beam in case of beam mis-steering or kicker fault. • Protect MSE copper coil from being deformed → ΔT <80 K • Limit water pressure rise in cooling channels of MS coil ΔP < 50 bar (→ Δtwater MSE coil< 15 K)

  4. TPSG4 beam diluter CZ5 CfC1.75 Ti 6Al 4V 3100 mm long diluter, with graphite CZ5, CfC, Titanium alloy (TA6V), and a Nickel based alloy (Inconel). Designed to protect MSE against impact of 450 GeV beam (total intensity: 4.9 1013, time structure: 25ns x 72 x 4 ) INCO718 Phase 2 Need beam test to see how this fails

  5. Scientific Motivation • To test equipment under the worst case conditions it may encounter in case of full beam impact • To validate the diluting materials used in TPSG4 • To demonstrate the MSE is properly protected by TPSG4 • To benchmark advanced numerical simulations TPSG4 test at HRMT#6

  6. Test specifications • Required test conditions: • TPSG4 and MSE under vacuum (10-8 mbar), • Cooling circuit of MSE coil under pressure (22 bar), • Beam Loss Monitoring • Cooling requirements between shots: • Cooling of TPSG4: connected to HRMT supply of ΔP=7 bar (expected flow of ~3 l/min) • Cooling of MSE: connected to HRMT supply of ΔP=7 bar (expected flow of ~47 l/min) • Real time data acquisition (vacuum, water pressure, flow rate, water circuit temperature, yoke temperature, BLM signals) TPSG4 test at HRMT#6

  7. Beam requirements • Beam energy: 450GeV • Bunch spacing: 25ns • Proton/Bunch: 1,2e+11 • Beam size: 0,5mmx0,5mm • Total time: 1 week TPSG4 test at HRMT#6

  8. Pre-assembly in building 867 (September – October) • Vacuum: gauges/primary pump on TPSG4 + MSE, beam line windows in Beryllium with C/C reinforcements (design M. Delonca EN/STI) • Hydraulic: pressure device, flow meter, temperature gauges • Survey: target alignment • Mechanical: assembly of lifting jig with counter weights • Validation: Lifting test TPSG4 test at HRMT#6

  9. Transport to BA7/TNC tunnel • Modified support feet for TPSG4/MSE • Optimization for transport: yokes locked in position, VPI blocked, bellows blocked • Transport procedure: lifting jigs, centre of gravity checked, transport trailer, … TPSG4 MSE TPSG4 test at HRMT#6

  10. Installation MSE • Support feet installation: using special braces on crane • Dedicated lifting jigs are installed onto the tanks, manual installation. TPSG4 test at HRMT#6

  11. Installation of TPSG4 TPSG4 test at HRMT#6

  12. Test set-upoverview Beam Catia rendering of final installation TPSG4 test at HRMT#6

  13. Hydraulic installation TPSG4 test at HRMT#6

  14. Installation sequence (planned for week 46) • Transport to BA7/TNC tunnel: 1/2 day • Modified support feet for TPSG4/MSE • Optimization for transport: yokes locked in position, VPI blocked, bellows blocked • Transport procedure: lifting jigs, centre of gravity checked, transport trailer, … • Installation of the experiment: 1 day • Mechanical support installation: special braces will be used on crane • Tank installation: special braces used on crane, dedicated lifting jig with counter weights for tanks • First manual installation of the MSE tank, followed by the TPSG4 • Finalize assembly: 3 days • Survey • Vacuum: leak test performed on the assembly • Hydraulic assembly: static pressure system on MSE (22 bar), dynamic circuit (7 bar) on TPSG4 • Installation of data acquisition systems (BLM, etc…..) • Installation validation: 1/2 day TPSG4 test at HRMT#6

  15. Test phases • Test run: week 47 (19 – 23 November) • Expected experiment duration: 1 full week • At least two people from the experimental team present in the CR during all phases of the experiment set-up and test run (TE/ABT, BE/BI) • In principle no access request is planned during tests • After the experiment: equipment remains in test area to allow the activation to decrease to an acceptable level (last experiment before LS1) TPSG4 test at HRMT#6

  16. Post-irradiation phase • After irradiation, the following analysis are foreseen: • Direct observation and in-situ measurements of MSE coil and TPSG4 diluter after dismantling (thanks to quick-disconnection flange). • Transport to 867 workshop once radiation levels have become acceptable (April 2013). • Damage inspection and dismantling followed by refurbishment of irradiated equipment. TPSG4 test at HRMT#6

  17. Hazard Inventory • Pressure: • Max. static pressure ~80 bar MSE coil • Max. dynamic pressure ~22 bar TPSG4 coil • Tank TPSG4 volume ~ 1.01 m3, tank MSE volume ~1,25 m3 • Vacuum: 10-8 mbar • Temperature: • ΔT on the TPSG4 coil ~700K • ΔT on the MSE coil ~8 K • Electricity: • 220 Von hydraulic electro-valves, up to 6kV on ion pumps • Ionizing radiation: • Particle type: protons • Pulse intensity: up to 288 bunches, 1.2E11 p/b • Beam energy: 450 GeV TPSG4 test at HRMT#6

  18. Radiological risk • Theoretical residual dose rate after 4 months: < 20 µSv/h à 40cm (C. Theis) • Dismantling of experiment at HRMT: April 2013 • Same procedure for transport from TNC/BA7 to 955 or 867 • Workshop 867 for refurbishment of the TPSG4 and MSE Max. 500 uSv/h inside diluter block (~80 cm from front face) 4 months TPSG4 test at HRMT#6

  19. Risk analysis • A hazard analysis is established separately for installation, test and dismantling of the set-up, and is accessible in the EDMS document page of the safety file. TPSG4 test at HRMT#6

  20. Conclusions • Mechanical design of test completed • Additional lifting braces being manufactured • Special support feet being manufactured • Lifting jig being manufactured • Transport chassis’ re-designed after review with transport team and ordered • Beam windows ordered • TPSG4 and MSE tanks presently being prepared in 867 • Risk inventory edited • Installation period extremely short TPSG4 test at HRMT#6

  21. Present situation in building 867 TPSG4 test at HRMT#6

  22. Back-up slides TPSG4 – preliminary post-irradiation dose rate estimates C. Theis / DGS-RP

  23. FLUKA simulation Inco 718 (3 x 1.9 x 30 cm) Titanium (3 x 1.9 x 30 cm) Simplified geometry: Graphite blocks (3 x 1.9 x 240 cm) Iron yoke Beam Protons @ 440 GeV 2E14 spread over 1 hour

  24. Residual dose rate 8 hours 1 hour

  25. Residual dose rate 1 day 1 week

  26. Residual dose rate Max. 500 uSv/h inside diluter block (~80 cm from front face) 1 month 4 months

  27. Back to radiological risk slide TPSG4 test at HRMT#6

More Related