Lansing Central School District Budget Update March 10, 2014

Lansing Central School District Budget Update March 10, 2014. Mary June King, Business Administrator. TONIGHT’s TOPICS. BUDGET UPDATE: Bus Purchase 2014-2015 Septic Funding Funding Projections. BUS PURCHASE. Replacement Schedule: 2 Full-sized Buses 1 (super-sized?) van

jemima
Télécharger la présentation

Lansing Central School District Budget Update March 10, 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lansing Central School DistrictBudget UpdateMarch 10, 2014 Mary June King, Business Administrator

  2. TONIGHT’s TOPICS • BUDGET UPDATE: • Bus Purchase 2014-2015 • Septic Funding • Funding Projections

  3. BUS PURCHASE • Replacement Schedule: • 2 Full-sized Buses • 1 (super-sized?) van • No related debt falling off • Local impact in GF would mean budget increase ($25K - $30K/yr) • Local Impact in Debt Service Fund means $0 budget impact; FYE22 DSF balance reduced from $409,972 to $271,032 • Need BOE decision by end of March 24 meeting

  4. SEPTIC PROJECT FUNDING - CONSIDERATIONS • $1M Debt Service “falling off” in 2016-2017 • This will effectively decrease LCSD property tax limit (cap) by around $400,000 • State building aid will also reduce by ~ $650,000 • The septic project should be Bonded in 2016-2017

  5. SEPTIC PROJECT FUNDING - CONSIDERATIONS • Monies “available” • $391,000 in Capital reserve • $276,000 unassigned, in excess of 4% • SUM: $ 667,000 • BOND FOR $4.1M OR $3.5M • Full bonding will offset reductions above:

  6. SEPTIC PROJECT FUNDING - RECOMMENDATIONS • ADMINISTRATION AND FINANCIAL ADVISORS: • Recommend funding entire cost with Bond • Hold $667,000 for another project • Try to work up second project for Fall 2014 or Winter 2015 vote to offset future revenue reductions.

  7. BUDGET FUNDING UPDATE