1 / 12

ERCOT 2011 Five-Year Transmission Plan Update

ERCOT 2011 Five-Year Transmission Plan Update. 2011 5YTP Reliability Analysis Update. N-1 Reliability Thermal and Voltage Analysis Reliability and voltage analysis completed for all years (2012, 2014 and 2016)

josephwhite
Télécharger la présentation

ERCOT 2011 Five-Year Transmission Plan Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERCOT 2011 Five-Year Transmission Plan Update RPG Meeting

  2. 2011 5YTP Reliability Analysis Update • N-1 Reliability Thermal and Voltage Analysis • Reliability and voltage analysis completed for all years (2012, 2014 and 2016) • 40 - Reliability driven projects identified to relieve various thermal constraints (for n-1 issues) • 10 – Reliability driven projects are same projects identified in both 2010 & 2011 5YTP • No projects required to relieve voltage constraints for 100 kV & above for all years (for n-1 issues) • List of all Reliability projects and the 2012, 2014 & 2016 Reliability cases were posted on Nov. 15, 2011 RPG Meeting

  3. Reliability Projects in 2010 & 2011 5YTP’s RPG Meeting

  4. 2011 5YTP Reliability Projects – East & Coast RPG Meeting

  5. 2011 5YTP Reliability Projects – West & Far West RPG Meeting

  6. 2011 5YTP Reliability Projects – North & North Central RPG Meeting

  7. 2011 5YTP Reliability Projects – South & South Central RPG Meeting

  8. 2011 5YTP G-1 & N-1 Reliability Analysis • West & Far West • Initial screening results from TARA • San Angelo Concho to Lake Nasworthy overload (2012) • Colorado River Municipal Water #2 to Goodfellow 138 kV line (2016) • Morgan Creek 138/69 kV autotransformer (2016) • All these overloads were resolved with generation re-dispatch and system adjustments (PST, Transformer taps) using Powerworld • No reliability projects needed for G-1 & N-1 • East and Coast • Initial screening results from TARA • Bryan Atkins 7 showed one overload (2016) • This overload was verified in Powerworld and might require an upgrade RPG Meeting

  9. G-1 & N-1 Reliability Analysis • North & North Central • Initial screening results from TARA • Atmel Hitachi Tap 1– Hackberry 138 kV line overload (2012) • Monticello Units, Kiamichi Energy Facility Units 1 and Lamar Power Partners Units outages caused this overloads (2012) • The overload was resolved using existing SPS or generation re-dispatch, reactive device adjustment, or transformer tap adjustment using Powerworld • Additionally, a scenario was run with all Dallas-Fort Worth area generation units that do not have selective catalytic reduction off-line. • No reliability projects needed for G-1 & N-1 RPG Meeting

  10. 2011 5YTP Studies in progress • G-1 & N-1 Reliability Analysis for South & South Central • will be completed next week • Low wind Scenarios (G-1 & N-1) for the six wind areas • work in progress • Transformer outage + N-1 Reliability Analysis • work in progress • 2014 Economic Analysis • In the process of completing the 2014 UPLAN case RPG Meeting

  11. 2010 5YTP Update • Report Update • Draft report update • Section II – Assumption and Process (currently working) • Section III - Reliability Driven Projects (currently working -will be sent to TO’s for comments end of January) • Section IV – Economic Analysis (Feb.) • Final report to be issued in March. RPG Meeting

  12. Questions? March 12, 2010 RPG Meeting

More Related