Omega

Omega. Utgangspunkt for PowerPoint presentasjoner. Quantity Management (QMS). Introduction. Currently the Quantity Mgmt module contains two sub modules Contract Evaluation Measurement Verification Sutable for time and material contracts

judith-holt
Télécharger la présentation

Omega

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Omega Utgangspunkt for PowerPoint presentasjoner

  2. Quantity Management(QMS)

  3. Introduction • Currently the Quantity Mgmt module contains two sub modules • Contract Evaluation • Measurement Verification • Sutable for time and material contracts • Price elements for man-hour norm and material unit rate (Compensation Codes) • Quantity * Norms and Rates = Man-Hours, Labor Cost, Material Cost and Total Cost

  4. Time and Material Contract Example

  5. Evaluation FEED MTO • Compare bidders • Analyze norms and rates • Scenarios / Normalizing • Identify «tactical priced norms and rates» Compensation Codes Scenarios Bidders Norms and Rates Compare Reports

  6. Contract Evaluation (Demo) • Compensation Codes & CBS • Scenarios • Bidders • Compare Bids • Norms and Rates Analyzer

  7. Measurement • Tool for Company’s verification of Contractor’s measurement and management of quantity update estimates that provides a continuous interpretation of Scope of Work into man-hours and cost through to final account. Deviations, cost changes and inconsistencies can be identified and managed at the earliest possible stage. The tool is divided in two main areas: • Quantity Update – Estimates in line with Weight Reporting • Quantity Measurement – A/IFC and As-built measurement

  8. Quantity Update Project Duration Estimate IFC Quantities 100% Scope As-Built Quantities

  9. Quantity Update Demo • Estimate (Forecast) • Scenarios • Can be activated / deactivated in estimate • Archive • Estimate and MTO development Scenarios

  10. Measurement Approaches • 100% As-Built Verification (Heavy workload) • Spot Check of As-Built • Continuous verification -> Feedback to Contractor

  11. Measurement data flow example Always use contractor’s measurement 100%, incl. errors and missing data. Contractor 100% transmissions, Incl. Errors, disagreements e.a Feedback • Agreed measurement adjustments Company • Own measurement on the few items we definitive disagree on Disagreements

  12. Measurement Simplified Model Contractor Contractor’s MTO 1 MTO 4 Quantity Update 2 Estimate 5 Compensation Codes 3 a b Client

  13. Measurement (Demo) • MTO • Information Library • Reporting

  14. What is there to check ? Reimbursable items (Not be measured) Tag or articles installed by vendors on equipment packages Compensation code Material Take Off (MTO) on document’s QtyMgmt Article weight Void item’s on documents and index Article length MTO Art Doc Clarifications Duplications in articles, documents or MTO (X) Item's that should be included in other articles with a general compensation code Tag or articles that should be measured in other phases (Hook-up) ATS-MC work paid both in measure and invoice