An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Requirements and Procedures Notice Submissions

  2. Part 1 Projects Covered

  3. Equipment Replacement • Medical and Non-Medical • Used for similar purposes as equipment being replaced • “Substantially equivalent” technology • FDA-approved, if applicable.

  4. Nonclinical Infrastructure • Including but not limited to HVAC, fire alarm and call bell systems, exterior building envelope, parking garages and elevators. • Others that do not relate to: • Clinical space or service • Renovation or reconfiguration of patient rooms • Renovation or reconfiguration of resident rooms.

  5. Non-Clinical Construction • Administrative Offices • Utility Structures • Maintenance Shop • Central Kitchen • Cafeteria • Gift Shop • Dedicated Worship Space • Hospital Lobbies

  6. Clinical Impact • Limited Review (710.1(c)(5)) still required for projects that impact clinical space, such as • Operating rooms • Treatment and procedure rooms • ICU’s • Special care units (e. g., cardiac) • Isolation rooms • Laboratories

  7. Clinical Impact • Limited Review (710.1(c)(5)) still required for projects to: • Renovate or reconfigure patient rooms • Renovate or reconfigure resident rooms. • Notice required for painting, replacement of floor coverings, etc., which are repair and maintenance

  8. Part 2 Notice Submission Process

  9. “Written” Notice • Electronic Submission via NYSE-CON

  10. Notice Submission to NYSE-CON • Format Similar to Limited Review Application, but streamlined: • Project Description • Architecture/Engineering Certification, where applicable.

  11. Patient Safety Plan • Required for projects that implicate patient safety • Submission of plan document required

  12. Timing and Acknowledgements • No timeframe for submission in advance of project • No formal approval will be issued by the Department for Notices • An acknowledgement will be generated by NYSE-CON when a notice is uploaded.

  13. Compliance • Pre-opening and /or Post-opening inspections will be conducted selectively. • All projects must be fully compliant with applicable codes and regulations. • Full citation and correction of any violations.

  14. Certification Documents • Initial Submission: • Architect/Engineer Certification • Patient Safety Plan • Physicist Certification

  15. Certification Documents • Project Closeout • Architect/Engineer Certification • Installer’s Certification • Balancing Report