1 / 5

Network exercise (P2)

Network exercise (P2). Consider the PERT/CPM network shown below. D. A. 2. 3. E. F. B. G. J. 1. 4. 6. 7. H. C. I. 5. a. Add the dummy activities that will eliminate the problem of activities having the same starting and ending nodes. Network exercise (P2).

karl
Télécharger la présentation

Network exercise (P2)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Network exercise (P2) Consider the PERT/CPM network shown below. D A 2 3 E F B G J 1 4 6 7 H C I 5 a. Add the dummy activities that will eliminate the problem of activities having the same starting and ending nodes.

  2. Network exercise (P2) b. Add dummy activities that will satisfy the following immediate predecessor requirements: Immediate Activity Predecessor H B, C I B, C G D, E

  3. Network exercise with time (P4) Construct a PERT/CPM network for a project with the following activities and times: ActivityImmediate Time Predecessor (months) A - 4 B - 6 C A 2 D A 6 E C, B 3 F C, B 3 G D, E 5 a) Find the critical path for this project network. b) This project must be complete in 1 1/2 years; do you anticipate difficulty in meeting the deadline? Explain.

  4. Consider the following network (P6)(times are in weeks) C 7 2 5 A 5 F 3 D 6 H 8 1 G 10 4 6 B 3 E 7 3 a. Identify the critical path. b. How long will it take to complete this project? c. Can activity D be delayed without delaying the entire project? How about activity C? If so, how many weeks? d. What is the schedule for activity E?

  5. Network exercise with time (P7) A project involving the installation of a computer system consists of eight activities. The immediate predecessor and activity time in weeks are shown below: ActivityImmediate Time Predecessor (weeks) A - 3 B - 6 C A 2 D B,C 5 E D 4 F E 3 G B,C 9 H F,G 3 a. Draw the PERT/CPM network for this project. b. What are the critical path activities? c. What is the expected project completion time?

More Related