Savannah River Site Spent Fuel Program Status. NSNFP Technical Exchange Meeting Bethesda, MD April 14, 2005. L-Basin. Receipts Since Last Meeting. Foreign: 5 casks from Japan Domestic: 7 casks HFIR/MURR/MIT. Work in Process. L-Area Storage Racks (temp. hold)

keahi
Télécharger la présentation

NSNFP Technical Exchange Meeting Bethesda, MD April 14, 2005

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Savannah River Site Spent Fuel Program Status NSNFP Technical Exchange Meeting Bethesda, MD April 14, 2005

  2. L-Basin

  3. Receipts Since Last Meeting Foreign: 5 casks from Japan Domestic: 7 casks HFIR/MURR/MIT

  4. Work in Process • L-Area Storage Racks (temp. hold) • RBOF Cask Pad Cleanup • Treatment and Storage Facility

  5. L-Basin Inventory – Without TSF LASR = L-Area Storage Rack project (FY00-06) MTRE = Material Test Reactor Equivalent 30000 Capacity with LASR ~ 19000 MTRE 25000 Equivalent MTREs 20000 15000 10000 5000 02 04 06 08 10 12 14 16 18 20 22 24 26 Fiscal Year

  6. L-Basin HFIR Projection – Without TSF LASR = L-Area Storage Rack project (FY00-06) HFIR = High Flux Isotope Reactor (Oak Ridge) 350 Capacity After LASR 208 cores 300 250 200 HFIR Cores 150 100 50 02 04 06 08 10 12 14 16 18 20 22 24 26 Fiscal Year

  7. Work in Process • L-Area Storage Racks (temp. hold) • RBOF Cask Pad Cleanup • Treatment and Storage Facility

  8. RBOF Cask Pad

  9. Work in Process • L-Area Storage Racks (temp. hold) • RBOF Cask Pad Cleanup • Treatment and Storage Capability

  10. Status: SNF Treatment and Storage Facility • CD-O package in approval process

  11. Spent Nuclear Fuel Program Schedule (By FY) 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Foreign SNF Receipt Program Domestic SNF Receipt Program Basin Operations TSF Project TSC Operations Deactivate Shipments to Repository Final closure/Disposition

  12. Issues • Lack of formal, written program direction • No TSF funding Identified • Global Threat Reduction Initiative impacts • Potential receipt of INEEL FRR shipments • H-Canyon processing – near term decision