Bangladesh-India Friendship Power Company (Pvt.) Limited (A Joint Venture of NTPC Ltd and BPDB ) Registered Office : Bidyut Bhaban (14th Floor), 1 Abdul Gani Road, Dhaka-1000, Bangladesh 2X660 MW MAITREE SUPER THERMAL POWER PROJECT PROGRESS REPORT FOR THE MONTH OF MARCH 2014.
E N D
Bangladesh-India Friendship Power Company (Pvt.) Limited(A Joint Venture of NTPC Ltd and BPDB)Registered Office : Bidyut Bhaban (14th Floor), 1 Abdul Gani Road, Dhaka-1000, Bangladesh2X660 MW MAITREE SUPER THERMAL POWER PROJECT PROGRESS REPORT FOR THE MONTH OF MARCH 2014 1 Photograph of Site to be given PROGRESS REPORT-MAR'2014
2X660 MW MAITREE SUPER THERMAL POWER PROJECT INDEX PROGRESS REPORT-FEB'2014
2X660 MW MAITREE SUPER THERMAL POWER PROJECT Management Summary • Appointment of Owner’s Engineer : Technical Bid opened on 13th March ’14. Financial Bid opened on 24th March ‘14. • Appointment of Coal Consultant : RFP finalized & issued to short-listed consultants. Pre-proposal meeting of 10th April ‘14. • Environment Management: Inception Report submitted by CEGIS • Boundary wall, Slope protection & Additional area filling: Negotiation held with M/S BDPL. Contract Finalized. • Pre-fabricated Site Office : Technical specification Finalized. • Substation Package: NIT given for newspaper publication. Bid opening on 30th April ‘14 Highlights – Progress: Corporate Activities PROGRESS REPORT-FEB'2014
2X660 MW MAITREE SUPER THERMAL POWER PROJECT Highlights - Progress : Site Activities • Pontoon Jetty foundation protection wall made. Pontoon stair erected. • 33/11 KV Line 200 KVA Transformer erected. Cable laying is under progress. • Site filling work completed. Micro-leveling & compaction in progress. • Earthen dyke preparation in progress, for slope protection. 1060 m/ 5400 m completed. • Main Plant Fencing work started. PROGRESS REPORT-FEB'2014
2X660 MW MAITREE SUPER THERMAL POWER PROJECT Cumulative Expenditure (FY-2013-14) PROGRESS REPORT-FEB'2014
2X660 MW MAITREE SUPER THERMAL POWER PROJECT Critical Assistance Required from External Govt. Bodies PROGRESS REPORT-FEB'2014
2X660 MW MAITREE SUPER THERMAL POWER PROJECT Critical Approvals / Agreements PROGRESS REPORT-FEB'2014
2X660 MW MAITREE SUPER THERMAL POWER PROJECT Major Initiatives taken during March ’14 • Owner’s Engineer Technical & Financial Bid opened • RFP issued for Coal Consultancy. • Boundary wall, Slope protection & Additional Land filling contract awarded. • 33/ 11 KV Sub-station, 11 KV Ringmain & Lighting Mast Supply/ Erection Contract document finalized. • Pre-fabricated Site Office Technical Specification finalized • Pontoon Jetty along with Gangway, Foundation protection & pontoon stair commissioned • Tax consultant engagement is at final stage PROGRESS REPORT-FEB'2014
2X660 MW MAITREE SUPER THERMAL POWER PROJECT Schedule of activities Planned in next six months PROGRESS REPORT-FEB'2014
2X660 MW MAITREE SUPER THERMAL POWER PROJECT 2 no. Site Photographs to be added PROGRESS REPORT-FEB'2014
BANGLADESH- INDIA FRIENDSHIP POWER COMPANY (PVT.) LTD. • One Photograph to be added PARTNER IN PROGRESS PARTNER IN PROGRESS PARTNER IN PROGRESS PROGRESS REPORT-FEB'2014