1 / 11

1 Photograph of Site to be given

Bangladesh-India Friendship Power Company (Pvt.) Limited (A Joint Venture of NTPC Ltd and BPDB ) Registered Office : Bidyut Bhaban (14th Floor), 1 Abdul Gani Road, Dhaka-1000, Bangladesh 2X660 MW MAITREE SUPER THERMAL POWER PROJECT PROGRESS REPORT FOR THE MONTH OF MARCH 2014.

keegan
Télécharger la présentation

1 Photograph of Site to be given

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bangladesh-India Friendship Power Company (Pvt.) Limited(A Joint Venture of NTPC Ltd and BPDB)Registered Office : Bidyut Bhaban (14th Floor), 1 Abdul Gani Road, Dhaka-1000, Bangladesh2X660 MW MAITREE SUPER THERMAL POWER PROJECT PROGRESS REPORT FOR THE MONTH OF MARCH 2014 1 Photograph of Site to be given PROGRESS REPORT-MAR'2014

  2. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT INDEX PROGRESS REPORT-FEB'2014

  3. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Management Summary • Appointment of Owner’s Engineer : Technical Bid opened on 13th March ’14. Financial Bid opened on 24th March ‘14. • Appointment of Coal Consultant : RFP finalized & issued to short-listed consultants. Pre-proposal meeting of 10th April ‘14. • Environment Management: Inception Report submitted by CEGIS • Boundary wall, Slope protection & Additional area filling: Negotiation held with M/S BDPL. Contract Finalized. • Pre-fabricated Site Office : Technical specification Finalized. • Substation Package: NIT given for newspaper publication. Bid opening on 30th April ‘14 Highlights – Progress: Corporate Activities PROGRESS REPORT-FEB'2014

  4. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Highlights - Progress : Site Activities • Pontoon Jetty foundation protection wall made. Pontoon stair erected. • 33/11 KV Line 200 KVA Transformer erected. Cable laying is under progress. • Site filling work completed. Micro-leveling & compaction in progress. • Earthen dyke preparation in progress, for slope protection. 1060 m/ 5400 m completed. • Main Plant Fencing work started. PROGRESS REPORT-FEB'2014

  5. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Cumulative Expenditure (FY-2013-14) PROGRESS REPORT-FEB'2014

  6. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Critical Assistance Required from External Govt. Bodies PROGRESS REPORT-FEB'2014

  7. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Critical Approvals / Agreements PROGRESS REPORT-FEB'2014

  8. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Major Initiatives taken during March ’14 • Owner’s Engineer Technical & Financial Bid opened • RFP issued for Coal Consultancy. • Boundary wall, Slope protection & Additional Land filling contract awarded. • 33/ 11 KV Sub-station, 11 KV Ringmain & Lighting Mast Supply/ Erection Contract document finalized. • Pre-fabricated Site Office Technical Specification finalized • Pontoon Jetty along with Gangway, Foundation protection & pontoon stair commissioned • Tax consultant engagement is at final stage PROGRESS REPORT-FEB'2014

  9. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Schedule of activities Planned in next six months PROGRESS REPORT-FEB'2014

  10. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT 2 no. Site Photographs to be added PROGRESS REPORT-FEB'2014

  11. BANGLADESH- INDIA FRIENDSHIP POWER COMPANY (PVT.) LTD. • One Photograph to be added PARTNER IN PROGRESS PARTNER IN PROGRESS PARTNER IN PROGRESS PROGRESS REPORT-FEB'2014

More Related