This document outlines key R&D milestones and decisions as part of the TDP for inclusion in the TDR text. It highlights changes related to R&D roll-ups, including the impact on various sections and decisions made through change control processes. Critical reviews of previous snapshots will inform future R&D planning, ensuring that all sections are interconnected and outcomes are traceable. The importance of having a comprehensive, clear timeline for design decisions is emphasized, reinforcing the value of R&D in the ILC Design framework.

Télécharger la présentation

Summary of TDP R&D Items and Baseline Changes for TDR Text Inclusion

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. R&D for TDR Summary of TDP R&D items and baseline changes to RDR – to be included and highlighted in TDR text AD & I 15 August 2012 Marc Ross First critical review of the ‘July TDR snapshot’ – given by EC last week TDR R&D Roll-up

  2. TDP Milestones and Decisions • We listed milestones in the ‘R&D Plan’ • and recorded decisions through ‘Change Control’ (TLCC and BTR) • Each TDR1 R&D section should include conclusions and refer to the relevant TDR2 section • in some cases primary authors did not participate in change control and their sections report R&D without summarizing impact. • Examples for review (to be included in TDR): TDR R&D Roll-up

  3. SCRF R&D Plan Milestones R&D Plan V5, 08.2010 TDR R&D Roll-up

  4. System Test Goals R&D Plan V5, 08.2010 TDR R&D Roll-up

  5. Electron Source R&D Plan V5, 08.2010 TDR R&D Roll-up

  6. Positron Source R&D Plan V5, 08.2010 TDR R&D Roll-up

  7. DR RTML MDI R&D Plan V5, 08.2010 TDR R&D Roll-up

  8. CFS R&D Plan V5, 08.2010 TDR R&D Roll-up

  9. Risk assessment R&D Plan V5, 08.2010 TDR R&D Roll-up

  10. ML Baseline Review (KEK 01.2012 TDR R&D Roll-up

  11. ML BTR TDR R&D Roll-up

  12. ML BTR

  13. TDR: Traceability • The TDR must have ‘shelf life’ • The value of R&D and value of ILC Design has always been clear • Timeline is not clear • Design decisions must be ‘traceable’ • R&D sections in TD Report must include a summary and conclusions • and be appropriately referenced within TDR itself and within EDMS • Remaining work to be outlined TDR R&D Roll-up