School #33 on Camino A Lago aims for a successful construction and opening process. Funded by the 2002 and 2005 bonds, the Board initially approved the project in 2006. While the school has target opening dates in 2014 and 2015, there are significant considerations, including construction costs, enrollment stabilization, and design options. The committee supports a review of previous designs and developing collaborative site plans. Additional time for school readiness and addressing challenges is crucial for ensuring a smooth transition for students.
E N D
Elementary School #33 • Board approval in 2006 • Funding • 2002 Bond • 2005 Bond • Location • Camino A Lago • Meadows
Opening Date – 2014 versus 2015 • 2014 Opening Considerations • Construction costs • Committee support • Enrollment stabilization • Challenges • Alternate location • Budgeting considerations • New Request For Proposal (RFP) requirements for Construction Manager (CM) at Risk • Compressed timeline
Opening Date – 2014 versus 2015 • 2015 Opening Considerations • More time for review and development of school design • More time to ready fixtures and furnishings upon completion • Challenges • More than one move for some students
Design Options • Proceed with 2008 design • Review prototypes from approved architects • Design committee to work with architect to develop site plans and make recommendations to Board