Sexual Assault Kit Backlog

Sexual Assault Kit Backlog . Monthly Report from Cross-Functional Team. SAK Cross Functional Team.

kerri
Télécharger la présentation

Sexual Assault Kit Backlog

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sexual Assault Kit Backlog Monthly Report from Cross-Functional Team

  2. SAK Cross Functional Team • On 31 January 2014 a Sexual Assault Kit (SAK) Cross-functional team (CFT) was established by Mayor A C Wharton, Jr. to ensure the work and many aspects of reform are coordinated and continue to move forward. The CFT meets bi-weekly. • Organizations represented on the CFT: • Mayor’s Office • District Attorney’s Office • Memphis City Council • Victim Advocacy • CAO Office • Division of Police Services • Finance Division • Legal Division • Joyful Heart Foundation • Consultant

  3. Status of Executive Order Action Items

  4. Status of DNA Evidence Storage Room: Construction Project Timeline and Progress • A & E Contract Execution01/02/14 • Design Programming Phase submittal (15 days)01/26/14 • City Review (14 days)02/07/14 • Schematic Design submittal (15 days)02/21/14 • City Review (14 days)03/07/14 • Design Development submittal (30 days) 04/07/14 • City Review (14 days) 04/18/14 • Construction Document submittal (45 days) 05/30/14 • City Review/Code Enforcement review (30 days) 06/30/14 • Bid Date 07/11/14 • Construction Contract Execution (60 days) 09/12/14 • Construction (4 months) 01/12/15

  5. Status of funding for testing $1MM approved by City Council on 4 March. $500K from MPD Budget, $500K from Tennessee Criminal Justice Programs Office

  6. Status of Shipping and Testing Kits

  7. Testing Results • Results will be displayed here • CELLMARK reports first batch of analysis results to be returned end of March 2014