Pilbara Undergrounding Program Steering Committee 17 September 09

kieve
Télécharger la présentation

Pilbara Undergrounding Program Steering Committee 17 September 09

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. DMS# 3198987 Pilbara Undergrounding Program Steering Committee 17 September 09

    2. DMS# 3198987 Project Overview Aimed at cyclone affected North West towns Karratha, Roebourne, Onslow & South Hedland A Royalties for Regions Program Significant expenditure over 4 year period Various agencies involved in Program Horizon Power is implementing agency

    3. DMS# 3198987 Purpose Safe & reliable electricity supply to north west towns Improved system reliability during cyclones & adverse weather Improved network performance through smart metering Network automation and improved communications (smart grid) Reduced network maintenance costs Safer and more attractive streetscapes Opportunities for local employment and businesses

    4. DMS# 3198987 Project Scope Underground distribution network House service connections New streetlighting Connect and energise new assets Advanced Metering Infrastructure smart meters network communication links Remove all old assets Site rehabilitation

    5. DMS# 3198987 Schedule for Program Team being established Stakeholder consultation Detailed planning, design and sourcing of materials over next few months Engagement of contractors Implementation schedule for towns to be developed Implementation likely to start early/mid 2010

    6. DMS# 3198987 HPs Project Team

    7. DMS# 3198987 Technological Innovations Distribution network voltage upgrade for Karratha Smart Metering innovations Smart Grid innovations National Broadband Network (NBN) initiatives Common trenching opportunities with other utilities Energy efficient, low maintenance, LED streetlighting

    8. DMS# 3198987 Proposed Project Area Karratha

    9. DMS# 3198987 Proposed Project Area South Hedland

    10. DMS# 3198987 Proposed Project Area Onslow

    11. DMS# 3198987 Proposed Project Area Roebourne

    12. DMS# 3198987 Next Steps Project Scope and Delivery Strategy approved by Steering Committee Funding arrangements for Project finalised. Horizon Power: Finalises establishment of Project team Initiates EOI process to engage contract support Commences procurement of materials Commences design and detailed planning Ongoing and increasing stakeholder engagement Next Steering Committee meeting