CMS Area Working Group Meeting

CMS Area Working Group Meeting. Installation schedule for coming months. CEMESTE / 104 : March 14 th 2007 Agenda: Key milestones UXC55 Installation sequence of the cable chains Cabling work between patch panels and racks on towers Impact on start of gas commissioning

kimberleyt
Télécharger la présentation

CMS Area Working Group Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CMS Area Working Group Meeting martin.gastal@cern.ch

  2. Installation schedule for coming months CEMESTE/104: March 14th 2007 Agenda: Key milestones UXC55 Installation sequence of the cable chains Cabling work between patch panels and racks on towers Impact on start of gas commissioning CMS Cabling coordination meeting +Z area installation YB0 installation schedule Impact on start of central beam pipe installation -Z area installation USC55 Electronics installation in Control area LV system installation on top of By-pass Magnet/Cryogenics area installation martin.gastal@cern.ch

  3. Key milestones • Nov2006 Dec2006 Feb2007 March2007 • Ready for crates with cooling in UXC55 X2 level • 12/12/2006 27/02/2007 06/03/2007 17/04/2007 • HF+1 installed in its garage • 14/11/2006 08/12/2006 • HF-1 installed in its garage • 21/11/2006 08/01/2007 08/01/2007 • Lower End Cap YE+3 • 23/11/2006 30/11/2006 • Lower YB+2 • 20/12/2006 19/01/2007 19/01/2007 • Lower YB0 • 05/02/2007 23/02/2007 28/02/2007 • Start pre-cabling of TK • 15/03/2007 27/03/2007 16/03/2007 22/03/2007 • Lower cold box • 12/01/2007 27/02/2007 12/02/2007 14/02/2007 martin.gastal@cern.ch

  4. Cable chains installation schedule martin.gastal@cern.ch

  5. Connect Cables From Patch p To racks On towers CEGELC contract: on critical path to gas system commissioning Other team requested to catch up with schedule Labels missing… could stall work martin.gastal@cern.ch

  6. Connect Cables From Patch p To racks On towers LV cabling to be done by Hadrelec On +Z additional WP were forgotten… Should not happen on –Z => Each WP supervisor should sign off the work upon completion, not TS-LEA martin.gastal@cern.ch

  7. Connect Cables From Patch p To racks On towers Installation of fibre optics should take place once patch panels are fully installed with heavy cables martin.gastal@cern.ch

  8. Connect Cables From Patch p To racks On towers Very challenging task!! Planning/coordination effort on-going martin.gastal@cern.ch

  9. YE+1 Draft schedule TS-LEA: Criotec contract martin.gastal@cern.ch

  10. YE+1 Draft schedule Install turbine cables: Fall back solution under study (See Mats’ talk) martin.gastal@cern.ch

  11. YE+1: very challenging environment martin.gastal@cern.ch

  12. martin.gastal@cern.ch

  13. martin.gastal@cern.ch

  14. UXC55: Racks installation martin.gastal@cern.ch

  15. UXC55: Racks installation – Near side • PH-CMI: Perform pressure tests • Start 26/03 for 2days • If flexible pipes are delivered martin.gastal@cern.ch

  16. UXC55: Racks installation – Near side • TS-EL: Install cables for turbines • Start 19/03 for 2 weeks • Hadrelec • Routing to be provided by Jean-Pierre Billon Grand • Order to be sent out by R Lassausaie ~ 1 week delay to expect… martin.gastal@cern.ch

  17. UXC55: Racks installation – Near side • TS-EL: Install cables for LV power distribution • Start 02/04 for 4 weeks • Hadrelec • Routing to be provided by S Bally (nothing available at TS-EL) martin.gastal@cern.ch

  18. YB0 project eighth iteration Optimised schedule version 5: Milestone summary: Keys date to keep in mind martin.gastal@cern.ch

  19. YB0 & HBs positioning martin.gastal@cern.ch

  20. YB0 & HBs positioning + YB0 services Starts as soon as Cradle HB+ dismantled Starts as soon as HB- aligned martin.gastal@cern.ch

  21. Install access platforms and scaffold +Z martin.gastal@cern.ch Design by CMS Integration group, April 2005.

  22. Optimised schedule version 5 Start after Easter Starts as soon as studs are welded, before Easter martin.gastal@cern.ch

  23. Optimised schedule version 5 No interruption in TK cabling between sides martin.gastal@cern.ch

  24. Optimised schedule version 5 martin.gastal@cern.ch

  25. Optimised schedule version 5 martin.gastal@cern.ch

  26. -Z Area installation Forward Beam pipe installation Low-Beta repairs Assembly of RS56 martin.gastal@cern.ch Design by CMS Integration group, April 2005.

  27. Draft schedule Driver of FIN56 installation See Sylvain’s talk martin.gastal@cern.ch

  28. USC55 : Control Area – CMS Electronics S2 (-1) martin.gastal@cern.ch

  29.   Diesel Canalis: start 05/03  UPS supported      IT-CS to insert a new starpoint rack at location S2-E-20 Canalis for row A: complete by 26/03 Duct under S2A for sniffer?      martin.gastal@cern.ch

  30. USC55 : CMS Electronics –Temporary Ctrl room Partition walls erected General services done Temporary access ctrl installed IT services being installed martin.gastal@cern.ch

  31. USC55 : Control Area – CMS Electronics S1 (-2) martin.gastal@cern.ch

  32.    UPS supported Diesel Canalis Turbines racks: 2nd to be installed this week New request from TK: accepted More requests are being considered martin.gastal@cern.ch

  33. Low-Voltage system USC55 – top of bypass martin.gastal@cern.ch

  34. USC55 – Top of Bypass: LV electronics installation • TS-EL: Install 2 LV cabinets (HF & YE+1) • Start 08/03 for 8 weeks • Hadrelec • Layout provided by S Lusin Crucial for commissioning martin.gastal@cern.ch

  35. Installation of Magnet areaA project in itself! Sequence has been under intensive review Baseline available Actors from 3 departments (AT-PH-TS) martin.gastal@cern.ch

  36. Transfer line Cold Box DCCT CP1 & CP2 Discharge lines supports (design to be reviewed) 16 racks martin.gastal@cern.ch Cryo cabinets

  37. PM54 – lowering sequence • PH-CMI: Fix discharge lines to shaft wall • Start 26/03 for 2 days • Use of a crane martin.gastal@cern.ch

  38. USC55- Magnet area • TS-EL: Install backlog of LV cables in racks • Start 08/03 for 2 weeks • Hadrelec martin.gastal@cern.ch

  39. USC55- Magnet area • TS-EL: Install 200 ctrl cables for Magnet system • Start 26/03 for 4 week • INEO • Work can only start once backlog of turbine cables is cleared… martin.gastal@cern.ch

  40. USC55- Magnet area • AT-ECR: Install last section of Transfer line • Start 12/03 for 2 weeks • DeMaCo • On-going, crane turned off in USC55 martin.gastal@cern.ch

  41. USC55- Magnet area • AT-ECR: Install last section of Transfer line • Start 12/03 for 2 weeks • DeMaCo • On-going, crane turned off in USC55 martin.gastal@cern.ch