1 / 7

Critical items, Key issues, Risks and Save Operation Aspects

Critical items, Key issues, Risks and Save Operation Aspects. R.Schieder/ R.Bieber. Critical Items PAD sheets are sent off. Laser diode: QA program almost finished CCD: Radiation test finished (3 krad okay) QA program at Lewicki successfully finished ASICS:

kin
Télécharger la présentation

Critical items, Key issues, Risks and Save Operation Aspects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Critical items, Key issues, Risks and Save Operation Aspects R.Schieder/ R.Bieber WBS CDR 2-3rd april 2003

  2. Critical ItemsPAD sheets are sent off • Laser diode: • QA program almost finished • CCD: • Radiation test finished (3 krad okay) • QA program at Lewicki successfully finished • ASICS: • Radiation test and life-time test successful • ATMEL tests: okay • MITEQ: • Prototype delivered and successfully tested • Amplifier not yet selected - delivery 2-3 months • MPAE: • Output filter for secondary voltages WBS CDR 2-3rd april 2003

  3. Key issues (1) ! WBS REQUIREMENTS ! • Thermal interface of WBO • 1K/hour (acc. ESA analysis: okay) • 2K over the baseplate (analysis by ESA shows a 6K difference) • wrapped in MLI • Temperature range: +5 - +150C WBS CDR 2-3rd april 2003

  4. Key issues (2) • Out of band signals ? • IF input signal without any filtering • Mechanical interface of WBE • (no full baseplate contact - 1mm spacing to SVM) • design already established with MITEQ • no design change possible anymore (mail from and to HA on 25.03.03) • Thermal analysis verifies current design WBS CDR 2-3rd april 2003

  5. Key issues (3) • Shock vibration: • Critical for WBO-modules • Levels: TBD • ESD: • Increased level in IID-A ? • Radiated Emission: • Transponder band spec. (0dBmV/m) not compliant • CPPA: (no information!) • Delivery of Filter, power supplies, ADC ??? WBS CDR 2-3rd april 2003

  6. schedule manpower Either QM delivery delays or model philosophy has to change Risks success oriented at lowest limit Delivery of parts / subcontractors (CPPA/MITEQ) delays at least QM program WBS CDR 2-3rd april 2003

  7. Undefined IF-input signal Longer non-operating periods (>1 week) Temperature of WBO > 300C Save Operation Aspects ZERO: ON Laser: OFF ZERO: ON Laser: OFF ZERO: ON WBS CDR 2-3rd april 2003

More Related