This document outlines critical items and key issues regarding the laser diode and CCD operations as of April 3, 2003. It discusses the quality assurance programs nearing completion for the laser diodes and CCDs, successful radiation and lifetime tests, and delays in amplifier selection. Key issues include thermal interfaces, mechanical compatibility, and compliance with shock and vibration requirements. Additionally, risks related to delivery delays from subcontractors and the undefined input signal are addressed, alongside measures for safe operation to ensure project success.
E N D
Critical items, Key issues, Risks and Save Operation Aspects R.Schieder/ R.Bieber WBS CDR 2-3rd april 2003
Critical ItemsPAD sheets are sent off • Laser diode: • QA program almost finished • CCD: • Radiation test finished (3 krad okay) • QA program at Lewicki successfully finished • ASICS: • Radiation test and life-time test successful • ATMEL tests: okay • MITEQ: • Prototype delivered and successfully tested • Amplifier not yet selected - delivery 2-3 months • MPAE: • Output filter for secondary voltages WBS CDR 2-3rd april 2003
Key issues (1) ! WBS REQUIREMENTS ! • Thermal interface of WBO • 1K/hour (acc. ESA analysis: okay) • 2K over the baseplate (analysis by ESA shows a 6K difference) • wrapped in MLI • Temperature range: +5 - +150C WBS CDR 2-3rd april 2003
Key issues (2) • Out of band signals ? • IF input signal without any filtering • Mechanical interface of WBE • (no full baseplate contact - 1mm spacing to SVM) • design already established with MITEQ • no design change possible anymore (mail from and to HA on 25.03.03) • Thermal analysis verifies current design WBS CDR 2-3rd april 2003
Key issues (3) • Shock vibration: • Critical for WBO-modules • Levels: TBD • ESD: • Increased level in IID-A ? • Radiated Emission: • Transponder band spec. (0dBmV/m) not compliant • CPPA: (no information!) • Delivery of Filter, power supplies, ADC ??? WBS CDR 2-3rd april 2003
schedule manpower Either QM delivery delays or model philosophy has to change Risks success oriented at lowest limit Delivery of parts / subcontractors (CPPA/MITEQ) delays at least QM program WBS CDR 2-3rd april 2003
Undefined IF-input signal Longer non-operating periods (>1 week) Temperature of WBO > 300C Save Operation Aspects ZERO: ON Laser: OFF ZERO: ON Laser: OFF ZERO: ON WBS CDR 2-3rd april 2003