Proposed Rule on Small Generator Interconnection RM02-12-000

Proposed Rule on Small Generator Interconnection RM02-12-000. July 23, 2003. Goals of Small Generator Proposed Rule. Facilitate the interconnection of small generators with a rule designed for their special features and needs Lower wholesale prices for customers,

kkerry
Télécharger la présentation

Proposed Rule on Small Generator Interconnection RM02-12-000

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proposed Rule onSmall Generator InterconnectionRM02-12-000 July 23, 2003

  2. Goals of Small Generator Proposed Rule • Facilitate the interconnection of small generators with a rule designed for their special features and needs • Lower wholesale prices for customers, • Reduce small generator interconnection time and costs, • Prevent undue discrimination in interconnections,

  3. Goals of Small Generator Proposed Rule (cont’d) • Preserve reliability of the electric system, • Increase energy infrastructure, and • Encourage the development of alternative energy sources such as wind, solar and distributed generation.

  4. Small Gen. Rulemaking Process • NOPR (consisting of both large generator and small generator matters) issued in April 2002 • Small Gen proponents requested separate treatment • Commission issued a separate Small Gen ANOPR for generators up to 20 MW in August 2002, initiating a stakeholder negotiation process • Coalition documents filed November 2002 • 45 comments received December 2002

  5. Small Gen Rulemaking Process(cont’d) • Coalition filed two Agreements and two Procedures – one set for ≤ 2 MW and another set for 2-20 MW • NARUC proposed a single set of procedures and agreement • The draft NOPR draws significantly from ideas brought forth by NARUC • The draft NOPR has a single set of procedures and an agreement applicable to all generators no larger than 20 MW

  6. Small Gen. Intercon. Agreement • Sets forth legal rights and obligations of each party, • Addresses cost responsibility for interconnection facilities and upgrades, • Lays out milestones for completing the interconnection, and • Sets forth the process for dispute resolution.

  7. Small Gen. Intercon. Procedures • Accelerated procedures for: • Generators connecting at high voltage and • Generators >10 MW connecting at low voltage • Expedited procedures for generators 2-10 MW connecting at low voltage • Super-Expedited procedures for generators ≤ 2 MW connecting at low voltage

  8. Pricing and Applicability • Pricing Policies – same as Large Generator Final Rule • Applicability – same as Large Generator Final Rule • Interconnection to a public utility’s transmission system • Interconnection to a public utility’s distribution system, if such facilities are currently being used to make a jurisdictional wholesale sale (all upgrade costs assigned to the generator) • The proposed rule may be used as a model by state regulatory commissions for interconnection subject to state regulation. • State standardization will help develop renewable resources and alternative fuel technologies.

  9. Public Comments • Comments are due 45 days after publication in the Federal Register. • Please file your comments electronically using the Commission’s website.