1 / 12

HBD Update: DC Meeting June 2006

HBD Update: DC Meeting June 2006. Thomas K Hemmick for the HBD Crew…. Overview of HBD Progress:. HBD Prototype Tests: Excellent Experience; many lessons learned: Install; Cabling; HV; LV; Noise; Gas QA; Gain; Elect; DAQ; LVL-2; Offline; One Mystery in Data:

kyra-franco
Télécharger la présentation

HBD Update: DC Meeting June 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HBD Update: DC Meeting June 2006 Thomas K Hemmickfor the HBD Crew…

  2. Overview of HBD Progress: • HBD Prototype Tests: • Excellent Experience; many lessons learned: • Install; Cabling; HV; LV; Noise; Gas QA; Gain; Elect; DAQ; LVL-2;Offline; • One Mystery in Data: • MIP apparently seen (Forward Bias). • Electrons give larger signals (great). • All Signals too low…Factor of 6 Mystery. • Learning the surprises now is the PURPOSE of the test… • HBD Construction: • HBD #1 nearly complete…Ship next week. • Glove Box installed & Running at Stony Brook.

  3. Quick Comments: • Installation: smooth…but detector should have “handles” instead of gas pipes for lifting. • Cabling: Final cabling plans excellent. (D. Lynch) • HV: Continuously at full voltage…never tripped. • LV: Fool-proof…low noise means good grounds. • Noise: pedestal sigma < 0.5 photo-electrons. • Gas QA: Plumbing perfect; detector is ONLY source of contamination…prototype leaks/outgasses some: • 20-25 ppm water, 15-20 ppm oxygen; ONLY 3-4 p.e. loss. • Gain:55Fe source shows published gain. • Electronics: Works through Full DAQ. Maybe fastest turn on of new system in PHENIX history?? • A few channels died (while cabling?). Must investigate. • DAQ: Reliable. System occasionally needed feeds. • LVL-2: SUPERB!! The LVL-2 stream = high purity electrons. • Offline: HBD data smoothly included in CNT files…

  4. PadId4 PadId1 50mV 100mV 250mV PadId5 PadId8 1500mV 1000mV 500mV Calibration: • Calibration uses test pulser input of pre-amps read through full electronics chain. • Each channel gets gain curve. • Online determination shows 0.1 fC/ch. • Exactly the same as design value.

  5. 430mVGain=1x104 Pulser Gain of Detector (Hutch Test): • 55Fe source (6 keV X-rays, 109-e’s). Clear peak. • Absolute gain can be determined by comparing the signal from pulser (known charge) to 55Fe. • Gain = 1 x 104…exactly consistent with publication. • Same pulser that propagated through full chain.

  6. Hadrons and Electrons in Forward Bias • Forward bias allows hadrons to make reference signal. • MIP apparently seen…electrons give bigger signal. • Factor-of-6 Mystery: Calibration says MIP peak should be channel 600 instead of channel 90.

  7. Row-Column Correlation • “Rows” in phi, “Columns” in Zed. • Offline determines predicted location of track. • Clear correlation of track projection with struck pad.

  8. Forward-1X Gain Reverse-1X Gain Forward-2X Gain Reverse-2X Gain Electron Hit Finding Forward • Electrons are produced in the collision and in the HBD back plane. • Should be ~2X as many from behind HBS as in front. • In forward and reverse mode electron efficiency roughly right and independent of gain. Reverse

  9. HBD In Beam Tests • Extremely valuable experience. • Detector seems operational and responds differently to hadrons & electrons. • Need to complete all data analysis for N0. • Factor-of-6 Mystery might be most important discovery (why we did this now). • Request for getting HBD “out”: • Return detector to floor (dead turtle position). • Restore to hutch tests. • Main Electronics  Chi.

  10. Main HBD • 10 days to finish 1st vessel after PCB. • 2nd PCB shipping to WIS now. • First Vessel Ships Middle of Next Week. • Second Vessel Ships End of June.

  11. Glove Box is here and installed. • 0.6 ppm water!! • Equipping unit for production now. • Dry run next week…production after… • <1 month per HBD (factor of 2 contingency)

  12. Summary • Need to finish analysis of all data. • Need to understand Factor-of-6. • On track for vessel delivery 1st August (tight but can be done). • Pre-amp board needs to be farmed out. • FEM Electronics need 3 months after final design (3 weeks from now following post-mortem of dead channels) • End of September… • Not a delay of vessel installation… • “May you live in interesting times”.--RFK Chinese Curse(??)

More Related