1 / 11

Overview

GLAST Program Beam Test Workshop CU Integration Francesco Bellardi francesco.bellardi@pi.infn.it Nicola Saggini nicola.saggini@pi.infn.it. Overview. Highlights of the INFN Integration Procedure: Requirements Towers Integration CALs Integration INFN CAL Integration MGSE: Main feature

lacy
Télécharger la présentation

Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GLAST ProgramBeam Test WorkshopCU IntegrationFrancesco Bellardi francesco.bellardi@pi.infn.itNicola Saggininicola.saggini@pi.infn.it

  2. Overview • Highlights of the INFN Integration Procedure: • Requirements • Towers Integration • CALs Integration • INFN CAL Integration MGSE: • Main feature • Comparison with SLAC philosophy • Status of Hardware • Schedule

  3. Highlights of INFN Integration Procedure • Requirements: • Critical components • Part of the components of the CU are FLIGHT HARDWARE • CAL: Cesium iodide crystals of calorimeter have an allowable relative humidity range of 35 to 50%. (Bagging and N2 flow at all times) • Environmental • All operations will be performed in Class 100,000 Clean Room • Electrostatic Discharge Control Per NASA-STD-8739.7 • Quality Assurance • Assembly and Inspection Data Sheet • QC inspection at the completion of each assembly sequence • Quality assurance will maintain surveillance of the operations required by this procedure

  4. Highlights of INFN Integration Procedure • TKR Towers Integration: • Performed according to LAT-PS-03058 - Tracker Integration Procedure • Towers are integrated from above the 1x4 Grid in two adjacent bays towards one of the sides (Bays 2-3) • TKR Tower to Grid interface Hardware (Studs and Cones) very well known by the INFN Integration Team (18 TKR Towers!!!) 2 3

  5. Highlights of INFN Integration Procedure • CAL Integration: • Different approach from that of LAT-PS-03027 - Calorimeter Integration & Processing Procedure: • CAL’s are integrated from underneath the 1x4 Grid instead of lowered into respective Bays. Reasons: • INFN Clean Room lacks necessary ceiling clearance • No overhead travelling crane • New MGSE and Procedure developed for this purpose Challenges: • Replicate same restraints and degrees of freedom during the entire operation • Use consistent safety precautions for the hardware and personnel • Adapt SLAC philosophy to INFN needs or absence of needs (e.g. CAL inversion) • Optimize use of available space (INFN Clean Room is not devoted entirely to GLAST!) • Maximize value of training performed at SLAC

  6. INFN CAL Integration MGSE • Main Features: Rotating Support Plates (θ angle) Thrust Ball Bearing, Sphered Housing Washer (φ & ψ angles - small) Vertical Drive Unit (Z direction) Z θ φ ψ Torque Limiter X Y Y direction Table X direction Table

  7. INFN CAL Integration MGSE • Comparison with SLAC philosophy: Different approach, same philosophy!!

  8. INFN CAL Integration MGSE • Putting it all together:

  9. INFN CAL Integration MGSE • Hardware Status: • Vertical Drive Unit: Here @ INFN ready for use • Torque Limiter: Here @ INFN ready for use • Thrust Ball Bearing: Here @ INFN ready for use • Profile Rail Guides and Carts: Here @ INFN ready for use • New Rotation Stand Wheels: Here @ INFN ready for use • X-Y Tables: In fabrication delivery in the first week of April • Vertical Drive Support Strct.: In fabrication delivery in the first week of April

  10. Schedule • Ready for MGSE Assembly by April 06 • Ready for Integration by May 02 • Milestones: • Delivery of 1x4 Grid by 03/27 • Delivery of remaining CAL and TKR units by 04/28 (does NOT include incoming tests etc. !!) • Delivery of Alignement Tools/MGSE retained by SLAC I&T by 05/02

  11. Conclusion If anything goes wrong…. Anywhere fun …we are outta here!! darn!!

More Related