Mapping the supply chain

Mapping the supply chain. Mapping the supply chain. Step 1: Make a picture of The Fresh Connection supply chain: Suppliers Inventories Productions steps Customers And connect the different entities in a correct way. The Value Chain – The Supply Chain Flow. Inbound.

lajos
Télécharger la présentation

Mapping the supply chain

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mapping the supply chain

  2. Mapping the supply chain • Step 1: • Make a picture of The Fresh Connection supply chain: • Suppliers • Inventories • Productions steps • Customers • Andconnect the different entities in a correct way

  3. The Value Chain – The Supply Chain Flow Inbound Outbound Orange OR 1L Mixing OR-C 1L Mango Orange Food and Groceries in The Fresh Connection OR-M 1L Mango Vit C OR pet Vit C Bottling OR-C pet Pack 1L Pack 1L LAND Market In The Fresh Connection OR-M pet PET PET Overflow Overflow Dominick’s in The Fresh Connection

  4. Mapping the supply chain • Step 2: • Fill the picture with important leadtimes:

  5. The Value Chain – Lead Times across the SC Inbound Outbound Orange OR 1L LT: 30d SS: 3 wk Cycle: 10 ds SS: 2 wk Mixing OR-C 1L Mango Orange SS: 3 wk Cycle: 10 ds Food and Groceries in The Fresh Connection LT: 10d SS: 2 wk OR-M 1L Mango SS: 3 wk Cycle: 10 ds Vit C SS: 2 wk OR pet Vit C Bottling LT: 40d SS: 3 wk Cycle: 10 ds SS: 2 wk Frozen period: 3 wk OR-C pet Pack 1L Pack 1L SS: 3 wk LAND Market In The Fresh Connection +5d intake Cycle: 10 ds LT: 15d SS: 2 wk OR-M pet PET SS: 3 wk Cycle: 10 ds PET +5d intake LT: 10d Overflow Overflow Dominick’s in The Fresh Connection

  6. Mapping the supplychain • Step 3: • Fill the picture withother important elements: • Lotsizes • Servicelevels • Obsoletes • Capacities, usageand overflows • This is your business on 1 A4

  7. The Value Chain – Your business on 1 A4 Outbound Inbound Capacity : 1500 pal Capacity : 900 loc Cost: 200€/loc/yr Cost: 200€/loc/yr Orange Utilization: 65% Utilization: 94% Val/rnd: 400 K€ Crew : 4 Terms: 4 wk P: 1.004 Crew: 5 OR 1L Dem: 66 KU Rej: 1% SL: 98% Overflow: 12% SL: 93.4% LT: 30d SS: 3 wk Tank Cycle: 10 ds Dem/wk: 34 KLit Obsol: 8.5% Ordsize: 165 KLit SS: 2 wk Mixing Lot: 4 wk OR-C 1L Dem: 11 KU Mango SL: 82.9% Val/rnd: 82 K€ CHG = Cleaning: 14% Orange SS: 3 wk Terms: 4 wk P: 1.058 Avg Lot: 11 KLit QC: No Cycle: 10 ds Rej: 2% SL: 94% LT: 10d Obsol: 5.7% SS: 2 wk IBC Lot: 4 wk OR-M 1L Dem: 42 KU Dem/wk: 3 KLit SL: 93.4% Mango Ord size: 15 KLit SS: 3 wk QC: No Cycle: 10 ds Vit C Val/rnd: 2 K€ SS: 2 wk Obsol: 8.6% P: 0.966 Terms: 8 wk Lot: 4 wk OR pet Vit C Dem: 116 KU Rej: 2% SL: 80% Bottling LT: 40d SL: 95.9% drum SS: 3 wk QC: No Dem/wk: 0.2 KLit Cycle: 10 ds Obsol: 8.7% Ord size: 1 KLit SS: 2 wk Lot: 4 wk Frozen period: 3 wk OR-C pet Dem: 18 KU Pack 1L Pack 1L Val/rnd: 110 K€ SL: 83.3% Terms: 4 wk P: 0.992 SS: 3 wk QC: No +5d intake SL: 93% Rej: 5% Cycle: 10 ds LT: 15d Obsol: 5.8% Pallet SS: 2 wk Dem/wk: 130 KUnit Lot: 4 wk OR-M pet Dem: 51 KU Ord size: 608 KUnit SL: 93.6% PET SS: 3 wk QC: No Cycle: 10 ds PET Val/rnd: 291 K€ +5d intake Obsol: 8.3% Terms: 4 wk Price: 0.962 Rej: 6% SL: 84% LT: 10d Breakdown Training Pallet Preventive Maintenance Overflow Overflow Dem/wk: 202 KUnit SMED Ord size: 927 KUnit Increase Speed Cost: 3 €/loc/day Cost: 3 €/loc/day

  8. Mapping the supply chain • Step 4: • Highlight the biggest issues andproblems: • Getting a grip on the situation

  9. The Value Chain – Getting Grip on the Situation Outbound Inbound Capacity : 1500 pal Capacity : 900 loc Cost: 200€/loc/yr Cost: 200€/loc/yr Orange Utilization: 65% Utilization: 94% Val/rnd: 400 K€ Crew : 4 Terms: 4 wk P: 1.004 Crew: 5 OR 1L Dem: 66 KU Rej: 1% SL: 98% Overflow: 12% SL: 93.4% LT: 30d SS: 3 wk Tank Cycle: 10 ds Dem/wk: 34 KLit Obsol: 8.5% Ordsize: 165 KLit SS: 2 wk Mixing Lot: 4 wk OR-C 1L Dem: 11 KU Mango SL: 82.9% Val/rnd: 82 K€ CHG = Cleaning: 14% Orange SS: 3 wk Terms: 4 wk P: 1.058 Avg Lot: 11 KLit QC: No Cycle: 10 ds Rej: 2% SL: 94% LT: 10d Obsol: 5.7% SS: 2 wk IBC Lot: 4 wk OR-M 1L Dem: 42 KU Dem/wk: 3 KLit SL: 93.4% Mango Ord size: 15 KLit SS: 3 wk QC: No Cycle: 10 ds Vit C Val/rnd: 2 K€ SS: 2 wk Obsol: 8.6% P: 0.966 Terms: 8 wk Lot: 4 wk OR pet Vit C Dem: 116 KU Rej: 2% SL: 80% Bottling LT: 40d SL: 95.9% drum SS: 3 wk QC: No Dem/wk: 0.2 KLit Cycle: 10 ds Obsol: 8.7% Ord size: 1 KLit SS: 2 wk Lot: 4 wk Frozen period: 3 wk OR-C pet Dem: 18 KU Pack 1L Pack 1L Val/rnd: 110 K€ SL: 83.3% Terms: 4 wk P: 0.992 SS: 3 wk QC: No +5d intake SL: 93% Rej: 5% Cycle: 10 ds LT: 15d Obsol: 5.8% Pallet SS: 2 wk Dem/wk: 130 KUnit Lot: 4 wk OR-M pet Dem: 51 KU Ord size: 608 KUnit SL: 93.6% PET SS: 3 wk QC: No Cycle: 10 ds PET Val/rnd: 291 K€ +5d intake Obsol: 8.3% Terms: 4 wk Price: 0.962 Rej: 6% SL: 84% LT: 10d Breakdown Training Pallet Preventive Maintenance Overflow Overflow Dem/wk: 202 KUnit SMED Ord size: 927 KUnit Increase Speed Cost: 3 €/loc/day Cost: 3 €/loc/day