1 / 3

Enhanced Statewide URM Mitigation Progress Report 2004

This report highlights the significant progress made in mitigating unreinforced masonry (URM) buildings across the state, with 69% mitigation achieved by 2004. A comparison to the 66% mitigation rate in early 2003 is included for reference. The Bay Area has shown commendable progress, reaching 81% to 85% in URM building mitigation efforts by early 2003, with a focus on the 10-county region comprising 6,718 URM buildings. Stay informed with this comprehensive update on URM mitigation strategies and advancements.

leila-quinn
Télécharger la présentation

Enhanced Statewide URM Mitigation Progress Report 2004

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Statewide Progress on URM Mitigation69% as of 2004 25,413 URM Buildings

  2. Statewide Progress on URM Mitigation 66% as of early 2003 25,515 URM Buildings 81% 85%

  3. Bay Area Progress on Mitigating URM Buildings44% as of early 2003 6,718 URM Buildings in 10 County Region