1 / 11

PERHITUNGAN VOLUME PEKERJAAN

PERHITUNGAN VOLUME PEKERJAAN. S0802 -Rencana Anggaran Biaya Pertemuan 6-7 Ir. Dwi Dinariana,MT. Pek. Persiapan, Galian dan Urugan Pek. Pondasi dan Beton Bertulang Pek. Pasangan Dinding dan Plesteran Pek. Lantai dan Dinding Pek. Plafon Pek. Kusen Pintu dan Jendela. Pek. Atap

lenora
Télécharger la présentation

PERHITUNGAN VOLUME PEKERJAAN

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PERHITUNGAN VOLUME PEKERJAAN S0802-Rencana Anggaran Biaya Pertemuan 6-7 Ir. Dwi Dinariana,MT

  2. Pek. Persiapan, Galian dan Urugan Pek. Pondasi dan Beton Bertulang Pek. Pasangan Dinding dan Plesteran Pek. Lantai dan Dinding Pek. Plafon Pek. Kusen Pintu dan Jendela Pek. Atap Pek. Perlengkapan Pintu dan Jendela Pek. Sanitair Pek. Instalasi Air Pek. Instalasi Listrik Pek. Pengecatan Pek. Pembersihan Lahan ITEM PEKERJAAN “PEMBANGUNAN RUMAH TINGGAL”

  3. 1. Pek. Persiapan, Galian dan Urugan • Pek. Persiapan • Pembersihan/Persiapan Lahan • Pengukuran dan Pasang Bouwplank • Pek. Galian dan Urugan • Galian Tanah Pondasi • Urugan Pasir Bawah Pondasi • Urugan Pasir Bawah lantai • Urugan Tanah Kembali • Urugan Tanah Dibawah Lantai

  4. Lahan yang akan dibangun rumah dibersihkan terlebih dahulu dari pohon-pohon dan akarnya, semak-semak, rum put dan semua hal yang dapat mengganggu pekerjaan V = p x l Keterangan : V = volume pembersihan lahan (m2) p = panjang lahan (m) l = lebar lahan (m) l Luas lahan yang akan dibangun p Pembersihan/Persiapan Lahan

  5. Bouwplank merupakan papan kayu sebagai pembatas lahan pekerjaan. Bouwplank dipasang mengikuti bentuk lahan yang akan dibangun dengan jarak ±1 m dari galian pondasi V = (p+2)x2 + (l+2)x2 Keterangan : V = volume bouwplank (m) p = panjang lahan (m) l = lebar lahan (m) l Luas lahan yang akan dibangun p Pengukuran dan Pasang Bouwplank

  6. V = [(a+b)/2xh] x p Keterangan : V = volume galian pondasi (m3) p = panjang pondasi (m) b = lebar bawah galian pondasi (m) a = lebar atas galian pondasi (m) h = tinggi galian pondasi (m) a (m) h (m) b (m) Galian Tanah Pondasi

  7. V = h x b x p Keterangan : V = volume pasir urug bawah pondasi (m3) p = panjang pondasi (m) b = lebar urugan (m) h = tebal urugan (m) a (m) Pasir h (m) h (m) b (m) UruganPek. Urugan Pasir Bawah Pondasi

  8. Urugan pasir di bawah lantai berfungsi u/ menstabilkan tanah, juga sebagai landasan lantai kerja diatasnya V = h x l x p V = h x L L = l x p Keterangan : V = volume urugan pasir (m3) p = panjang ruangan (m) l = lebar urugan (m) L = luas lantai keramik (m2) h = tebal urugan pasir UruganPek. Urugan Pasir Bawah Lantai

  9. Urugan tanah untuk peninggian lantai diperlukan agar peil lantai memiliki perbedaan tinggi Ketinggian tergantung tinggi lantai yang diinginkan V = h x l x p V = h x L L = l x p Keterangan : V = volume urugan tanah (m3) p = panjang ruangan (m) l = lebar urugan (m) L = luas lantai keramik (m2) h = tebal urugan tanah UruganPek. Urugan Tanah Bawah Lantai

  10. UruganPek. Urugan Tanah Kembali • Urugan tanah kembali di sisi kanan maupun kiri pondasi berfungsi untuk mengisi sisa galian pondasi yang telah dipasang pondasi batu kali • V = Vgal tanah – (Vpondasi+Vurugan pasir) • Keterangan : • V = volume urugan tanah kembali (m3)

  11. 2. Pek. Pondasi dan Beton Bertulang • Pek. Pondasi • Pondasi Batu Kali • Pek. Beton • Beton Lantai Kerja • Pek Beton Bertulang • Sloof beton • Kolom Beton • Ringbalk Beton dst

More Related