1 / 14

DCS Solutions: Don Jackson Chen Kiat Yong Sarah Doyle

DCS Solutions: Don Jackson Chen Kiat Yong Sarah Doyle. Constructed Wetland Design at Sipaulovi Village. DCS Solutions Who are we?. Don Jackson – Team Leader Main client contact Design & research Chen Kiat Yong Main design research Permitting & regulations Sarah Doyle Main drafter

lerato
Télécharger la présentation

DCS Solutions: Don Jackson Chen Kiat Yong Sarah Doyle

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DCS Solutions:Don JacksonChen Kiat Yong Sarah Doyle Constructed Wetland Design at Sipaulovi Village

  2. DCS SolutionsWho are we? • Don Jackson – Team Leader • Main client contact • Design & research • Chen Kiat Yong • Main design research • Permitting & regulations • Sarah Doyle • Main drafter • Design & research • Deliverable editing

  3. Objective • To design a centralized wastewater treatment system to meet current and future demand for the Village of Sipaulovi.

  4. External Consultants • George Mase • Main Tribal Contact • Community Services Administrator • John Mead • Wastewater Technical Specialist • Institute for Tribal Environmental Professionals • Suzanne Jamison • Liaison for DCS and Hopi Tribe • Paul Gremillion, P.E. • N.A.U Professor, Civil & Environmental Department • Christine Laguna, P.E. • Grading & Drainage Specialist • CAD advisor • Jason Nieto • Certified Plant Operator • Sipaulovi Lagoons • Erika Schoen, E.I.T. • Environmental Engineer • Indian Health Service • Carl Seweyestewa • Land Information Systems Surveyor, Hopi Tribal Government • Mike Stover, P.E. • Technical Advisor • I.H.S. Environmental Engineering Consultant

  5. Introduction • Problems with current system • Future growth – population may double • Projected calculations in Microsoft Excel • Odors from existing facility • No central sewer system

  6. Proposed site Sipaulovi Village

  7. Aerial photo

  8. What does the client want? • Centralized WWTS for current and future users • Prefers Constructed Wetland Design • Wants to reuse effluent for non-edible crops (gourds, livestock fodder, etc…) • Trees • Would like to attract birds and other wildlife

  9. Design phases: • 30% design proposal (completed) • Includes research of design alternatives • 60% design proposal (pending) • Will be completed by April 6 • After 60% design proposal is completed, client representative (George Mase) will be consulted to select final design • 90% design proposal (to be completed) • Includes engineer’s construction cost estimates • 100% design proposal • To be completed by April 20th • Capstone presentation April 27th

  10. Design Elements: • Transport (not in scope of project) • Flow equalization/settling tank • Bar screen • Flow meter (requires electricity) • Pump (requires electricity) • Pressure sewer & Gravity sewer • Primary Treatment System • Oswald system OR lagoon • Lined or unlined • Secondary Treatment System • Constructed wetland (Oswald only) • Non-discharging OR effluent reuse

  11. Questions?Comments?Suggestions?

More Related