1 / 29

Network Design with Constraints

Network Design with Constraints. Chapter 10 Part 1. Overview. Build a network connecting 75 stores to a HQ Each store generates 500bps of traffic & receives about 1500bps of traffic. An MST or CMST will be the correct solution

loman
Télécharger la présentation

Network Design with Constraints

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Network Design with Constraints Chapter 10 Part 1 Prepared by Giray Birkan gbirkan@mail.smu.edu

  2. Overview • Build a network connecting 75 stores to a HQ • Each store generates 500bps of traffic & receives about 1500bps of traffic. • An MST or CMST will be the correct solution • But you are told that each store needs 64Kbps access & 3 hops maximum. • Or the lowest cost network where the average end-to-end delay is 300 ms or less. Prepared by Giray Birkan gbirkan@mail.smu.edu

  3. Designs Constraints • Cheapest design may not be acceptable for reasons of reliability, performance, … or organizational or political reasons • May have to modify algorithms or write problem-specific code to produce an acceptable design. • Manual Design? Prepared by Giray Birkan gbirkan@mail.smu.edu

  4. Hop constraints Worst case Average Node-pair Equipment constraints Degree Throughput Link constraints Required or forbidden Performance constraints Worst case Average Node-pair Reliability constraints Entire network Backbone Node-pair Miscellaneous High & Low Security Nodes Types of Constraints Prepared by Giray Birkan gbirkan@mail.smu.edu

  5. Over-Constrained Problem • It is possible to specify so many or so severe constraints that there is no feasible network design • War Story 10.1: each node must be of degree three, for example if n = 7. There is no solution • Suppose each site has equipment that can only terminate a LAN and two leased lines - Can only build a ring. Prepared by Giray Birkan gbirkan@mail.smu.edu

  6. Over-Constrained Problem • In any network, the total amount of capacity used by all of the traffic is bounded from below by • Capacity of a leased line is C and capacity of the ring is (n-1)C. • As network grows, link capacity will be overloaded at some point Prepared by Giray Birkan gbirkan@mail.smu.edu

  7. Hop-Limited Designs • Problem Statement 10.1: Given a set of traffic Trafi,j, find the lowest cost design such that if Trafi,j > 0then the path chosen by the routing algorithm through the network has less than h hops. • If h is very large, first solve the unconstrained problem maybe a cost-optimized network is sufficient. Prepared by Giray Birkan gbirkan@mail.smu.edu

  8. B A C D E AMPL and Hop-Limited Design • Arc-Path Model • Set P : set of paths • Only paths with 3 hops are in the data model • A-B A-D-B A-D-E-B • A separate program can be written to find these paths Prepared by Giray Birkan gbirkan@mail.smu.edu

  9. AMPL and Hop-Limited Design • Node-Arc Model • Only links and nodes no paths are given • The hop limit is 3 and each demand must be satisfied by a single path. • Giray’s Solution: Subject to HopLimit {c in N, n in {N diff {c}}: sum{e in E} (-yi[c,e,n] - xi[c,e,n]) >= 3 * rhs[c,n]; Prepared by Giray Birkan gbirkan@mail.smu.edu

  10. A B C D Badly Posed Examples • MUX network : The path that a requirement takes depends on the loading sequence. Assume each link can load 2 circuits Network appears to be a 2-hop design Loading pattern 1 : { AB, AB, CB} Loading pattern 2 : { AB, CB, AB} Prepared by Giray Birkan gbirkan@mail.smu.edu

  11. Badly Posed Examples • Boundary of the Network • 6 Hop Design: NY - Philadelphia - Detroit - Chicago - Denver - LA - San Diego • 6 Hops or 12 hops? BBNY – Building – 14 Floor – Workstation • Generally, we don’t cost optimize building networks Prepared by Giray Birkan gbirkan@mail.smu.edu

  12. Approach I : Culling • Generate a lot of designs with varying parameters • If Mentor is used try different values for alpha, slack, nclst, seed • Throw away all that do not meet hop constraints • Select best remaining design • Brute force method may be quite acceptable if it avoids writing problem-specific code • May not work if constraints are too severe • Frequency of feasible designs may be too low to be practicable Prepared by Giray Birkan gbirkan@mail.smu.edu

  13. Culling Continued • Cost Optimized design with 11 hops Prepared by Giray Birkan gbirkan@mail.smu.edu

  14. Culling Continued • The best 9-hop design culled from a run • Out of 325 trial, only 28 of them had 9 hops Prepared by Giray Birkan gbirkan@mail.smu.edu

  15. Culling Continued • More than 150 different networks only one of them had 7 hops Prepared by Giray Birkan gbirkan@mail.smu.edu

  16. Culling Continued • If Culling fails to find 6-hop designs • Reduce the diameter of the backbone • Reduce the depth of the access trees A tree centered on N45 Prepared by Giray Birkan gbirkan@mail.smu.edu

  17. Approach II : Augmentation • 5 pairs of nodes 8 hops apart, 7 hop design required Prepared by Giray Birkan gbirkan@mail.smu.edu

  18. An Algorithm To Compute Hops In The Access Topology • For each backbone node b compute la(b) : max depth of the local access tree at b. • Loop until done. Compute diameter of the network: • If d > h, return fail • For each backbone site b, compute • e(b) gives the number of extra hops we can expand la(b) and still meet the h hop constraint • If any e(b) greater than 0, select a node b and increase la(b) by 1. Otherwise break loop • Return the values la(b) Prepared by Giray Birkan gbirkan@mail.smu.edu

  19. Algorithm Continued h = 6 Prepared by Giray Birkan gbirkan@mail.smu.edu

  20. Algorithm Continued The design with a 3 hop cluster at N45 Prepared by Giray Birkan gbirkan@mail.smu.edu

  21. Average Hop Constraints • Average number of hops is a far easier constraint to meet than a constraint on the maximum number of hops • Three approaches for MENTOR • Increase alpha • Builds more star-like networks • Increase slack • Introduces more links • If slack = 1, we will build a network where there is a link between any 2 sites that have traffic • Use lower-speed links • Introduces more links – because of utilization Prepared by Giray Birkan gbirkan@mail.smu.edu

  22. Average Hop Constraints • First mean tends to equalize performance among large & small sites • Second makes most people happy at the cost of a minority of users with lower grade of service Prepared by Giray Birkan gbirkan@mail.smu.edu

  23. Meeting hops Constraints The cost of improving hops2 Hops & cost for various Values of slack The interesting choices for slack Prepared by Giray Birkan gbirkan@mail.smu.edu

  24. Meeting hops Constraints Prepared by Giray Birkan gbirkan@mail.smu.edu

  25. Homework 12 • Using node-arc model from homework 8 solve the following mesh design problem. • Use one model file • First, Minimize the number of average hops • Then, Minimize the total cost • Trunk types: • 96K bps - $50 per trunk • 128K bps - $60 per trunk • 256K bps - $105 per trunk • Each demand must be satisfied by a single path. • The utilization should be no more than 50%. Prepared by Giray Birkan gbirkan@mail.smu.edu

  26. Homework 12 A F D B E C G Prepared by Giray Birkan gbirkan@mail.smu.edu

  27. Homework 12 Prepared by Giray Birkan gbirkan@mail.smu.edu

  28. AMPL & Multiple Objective Functions • You can define several problems in one model file • You can solve a problem then fix some variables and solve another problem #---first problem----- problem DefineBIG: # objective segmentlength, # variables X, Y, A, B, BIG, # constraints flowbalance, flowbalance2 ,linkbetweenXandA, linkbetweenYandB, linkbetweenAandB, linkbetweenBIGandX, lastAMP, firstAMP; solve DefineBIG; #---second problem----- problem ReduceAMPS: # objective amps, # variables X, Y, A, B, BIG, # constraints flowbalance, flowbalance2, linkbetweenXandA, linkbetweenYandB, linkbetweenAandB, linkbetweenBIGandX, lastAMP, firstAMP, BIGfix; solve ReduceAMPS; Prepared by Giray Birkan gbirkan@mail.smu.edu

  29. GRIN • http://www.geocities.com/pechv_ru/main.html Prepared by Giray Birkan gbirkan@mail.smu.edu

More Related