2015 FTBA ANNUAL CONVENTION August 6-9, 2015 NAPLES GRANDE BEACH RESORT WORK PROGRAM OVERVIEW

F LORIDA D EPARTMENT O F T RANSPORTATION. 2015 FTBA ANNUAL CONVENTION August 6-9, 2015 NAPLES GRANDE BEACH RESORT WORK PROGRAM OVERVIEW 2016-2020 Jim Boxold Secretary, Florida Department of Transportation. F LORIDA D EPARTMENT O F T RANSPORTATION 100 Y EARS O F S ERVICE.

louannj
Télécharger la présentation

2015 FTBA ANNUAL CONVENTION August 6-9, 2015 NAPLES GRANDE BEACH RESORT WORK PROGRAM OVERVIEW

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FLORIDA DEPARTMENT OF TRANSPORTATION 2015 FTBA ANNUAL CONVENTION August 6-9, 2015NAPLES GRANDE BEACH RESORT WORK PROGRAM OVERVIEW 2016-2020 Jim Boxold Secretary, Florida Department of Transportation

  2. FLORIDA DEPARTMENT OF TRANSPORTATION 100YEARS OF SERVICE • 1915 - the State Road Department (SRD) was authorized by the Florida Legislature. • 1920 - the SRD created five divisions which later became districts. • 1969 - The State Road Board and State Road Department were merged into the Department of Transportation.

  3. WHAT WAS OUR PROGRAM LIKE IN 1915? 1915 VEHICLE COST –AVERAGE WAS $500

  4. EARLY ROAD BUILDING RESOURCES 1925-26 REPORT: STATE WORK FORCE The Men Convict Labor 1,000 Convicts working at $1.06 per day. CONVICTS LAYING BRICK PAVEMENT 1915 ROAD-BUILDING USING CONVICT LABOR The Mules The Department added to the organization a Veterinarian to care for the 514 mules.

  5. WE’VE COME A LONG WAY IN 100 YEARS 1917 DIXIE HWY BEFORE 1917 DIXIE HWY AFTER FROM EARLY IMPROVED 2-LANES TO MODERN MULTI-LEVEL FREEWAYS DISTRICT SIX  This 13 mile $481M project - tolled express lanes along the SR 826/Palmetto Expressway

  6. TOTAL FUNDINGFY 2016 - 2020

  7. TOTAL BUDGETFY 2016-2020

  8. TOTAL CONSTRUCTIONFY 2016 - 2020 Total 5-Year Adopted Work Program $19,226M

  9. Total 5-Year Adopted Work Program $2,019M

  10. FY 2016 PROJECT LETTINGS - BY MANAGING DISTRICT (JULY 31, 2015 LOCKDOWN PLAN)

  11. FY 2016 PROJECT LETTINGS - BY PROJECT TYPE (JULY 31, 2015 LOCKDOWN PLAN)

  12. FY 2016 PROJECT LETTINGS PROJECT LETTINGS > $50M PLANNED DESIGN BUILD

  13. STATEWIDE PROJECT LETTINGS IN $B FY 2016-2018

  14. PROJECT LETTINGS > $100M FY 2016-2018 P3

  15. PROJECT LETTINGS - HISTORY/ESTIMATED $3.4 $3.1 $2.2 Note: These lettings include the Highway and Bridge Programs only, including Resurfacing, Bridges, Roadway, Safety, and Traffic Operations. 0nly Contract Classes 1 (Central Office Let), 7 (District Office Let), and 9 (Design-Build) are included. Reserves are included for 2016-2018 . The $2.3B D5 I-4 DBFOM contract is shown in 2015; 2006-2015 ARE ACTUALS; 2016-2018 BASED ON DATA AS OF 7/31/15 Note: These lettings include the Highway and Bridge Programs only, including Resurfacing, Bridges, Roadway, Safety, and Traffic Operations. 0nly Contract Classes 1 (Central Office Let), 7 (District Office Let), and 9 (Design-Build) are included. Reserves are included for 2016-2018 . The $2.3B D5 I-4 DBFOM contract is shown in 2015; 2006-2015 ARE ACTUALS; 2016-2018 BASED ON DATA AS OF 7/31/15

  16. DESIGN BUILD HOW MUCH ARE WE DOING?

  17. DESIGN BUILD FOR FY 2016 (JULY 31, 2015 LOCKDOWN PLAN)

  18. STATEWIDE LETTINGS - LOW BID HISTORY (COMPARISON OF LOW BIDS TO THE LOCKDOWN PLAN ESTIMATES) SAVINGS IN $M SAVINGS IN %

  19. CONSTRUCTION COST AND TIME MANAGEMENT TARGET IS < 20% TIME INCREASE TARGET IS < 10% COST INCREASE CONSTRUCTION PERFORMANCE: When projects reach a status of being conditionally, materially, and finally accepted (status 6, 7 or 8), the time and cost changes are determined. They are reported in two methods: 1) simply as what percentage time or cost increases have occurred over the life of the contract, or 2) what percentage contracts have had less than 20% time increases or what percentage contracts have had less than 10% cost increase.

  20. CONSTRUCTION COST AND TIME MANAGEMENT TARGET IS > 90% OF ALL CONTRACTS WITH < 10% COST INCREASE TARGET IS > 80% OF ALL CONTRACTS WITH < 20% TIME INCREASE CONSTRUCTION PERFORMANCE: When projects reach a status of being conditionally, materially, and finally accepted (status 6, 7 or 8), the time and cost changes are determined. They are reported in two methods: 1) simply as what percentage time or cost increases have occurred over the life of the contract, or 2) what percentage contracts have had less than 20% time increases or what percentage contracts have had less than 10% cost increase.

  21. SUMMARY OF PUBLIC-PRIVATE PARTNERSHIP PROJECTS(P3) AS OF APRIL 2015

  22. PARTNERS IN TRANSPORTATION HAVE A GREAT CONVENTION AND BE SAFE OUT THERE!