An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ALICE 5 o’clock meeting http://indico.cern.ch/conferenceDisplay.py?confId=115692 Wk 49

  2. Access requestCavern and surface • You should submit an ADI and a task procedure Attach task procedure Work breakdown structure – risk associated at each step Two persons minimum ADI https://edh.cern.ch/Document/ADI Task procedure Template EDMS 1103355 ALICE planning meeting

  3. ALICE Christmas break schedule TRD Close L3 doors Open L3 doors EMCal Close Experiment Open Experiment ALICE planning meeting

  4. UX25 access • Rules for access restrictions: • Removal/installation of shielding (restriction includes RB24 triplets) • PX24 blocks: no access CR5 and UX25 • PX24 beams (35t): no access CR1-5, Expo, and UX-25 • All other blocks: no access to UX-25 • LHC evacuation test (7/12 after 18:00 and 24/12 tbc) – no access UX25 • Gas functional test (10/12 - 2 hrs) – no access UX25 and CR1-5 • AUG test (20/1) (Arrêt Urgence General – General Emergency Stop) – no access UX25 • DSO test (12-13/1) (Department Safety Officer) – no access UX25 • No access SX2 during manipulation of blocks in SX2 (except ACR and WRs) ALICE planning meeting

  5. L3 (and MNF) access EMCal No Ventilation 24 31 No Ventilation +AUG EMCal EMCal Evac. • Wks 50 and 4: access (TPC) to be coordinated with TC (transport) • Wks 1-2: no access during EMCal SMs insertion inside L3 (see day-by-day) • When moving from low-beta to yellow platform: no access to MNF • When inserting the module: no access L3 and MNF • Watcher needed in wk 49 and from wk 4 onwards • Wk 6 or 7 (tbd): Kr calibration – TPC T stability (all interventions to be agreed by TC/RC) ALICE planning meeting

  6. Day-by-day schedule UX25 and MNF - Wk 49

  7. Week 49 - 6/12 MondayProgram • 18:00: end HI program • Ramp down both magnets • 18:00 – 21:00: access system test. No access UX25 • 21:00: RPE survey (Jiri + 2nd person) • Collect samples • Then go to general mode • From 21:30: TRD Wiener PS (?) ALICE planning meeting

  8. It H Activities in UX25 - Week 49 - 6/12 Monday No access UX-25 - possibility of access from 21:00 TRD team at CERN: 6 to 10/12 ITECO TRD Wiener PS TRD Wiener PS HAULOTTE TRD: after 21:30 ALICE planning meeting

  9. Week 49 - 7/12 TuesdayProgram • 8:00 - 18:00: UX25 cavern in Restricted mode • No access UX25 (except Transport, VAC, TC and RP) • SLIMOS needed (Werner) • 8:30 - 9:30: RP liquid sampling (Adeline, Pierre) – SPD and TPC priority • 18:00 - 21:00: evacuation test – No access UX25 • From 21:00 - Cavern in General mode • 14:00 - 15:00: Portuguese Press visit. 10 persons ALICE planning meeting

  10. Week 49 - 7/12 TuesdayActivities • ALTEAD: PX24 shielding blocks • 8:00 to 18:00: no access CR5 • 14:00 to 15:00: put SM16 into the rotator • VAC: Neon injection preparation • Transport needed (EDH 4472100) • Remove “green fence” (P2 technician) • 9:00: stop flammable gases i-C4H10 and CH4 (Ar/H2 on 10/12) • 8:30: Lock L3 power converter + conpensator • Reinstall crane electronics • Test transmission of alarm lift to FB • 8:30: inspection PHOS cooling plant (Arturo, Dominique, Philippe, Sasha) • 15:15: VIC SPD • DCS: 10:00 – 12:00, interruptions of the GPN link to/from P2 ALICE planning meeting

  11. It H Activities in UX25 - Week 49 - 7/12 Tuesday 8:00 to 18:00: no access UX25 (except Transport, VAC, TC and RP) 18:00 – 21:00: evacuation test (No access UX25) PX24 shielding: blocks VAC RP samples 8:00 to 18:00: no access CR5 ALICE planning meeting

  12. Activities in MNF - Week 49 - 7/12 Tuesday 8:00 to 18:00: no access MNF 18:00 – 21:00: evacuation test (No access UX25) ALICE planning meeting

  13. It H Activities in UX25 - Week 49 - 8/12 Wednesday 8:00 to 18:00: no access UX25 (except Transport and VAC) 18:00 to 8:00: access in general mode Move TRD Wiener PS TPC: replacement of damaged FECs (after 21:00) PX24 shielding: beams (35t) Stabilizers VAC Muon TRK: CROCUS firmware upgrade TPC FEC and TRD LV Cut SPD pipes (after 18:00) After 18:00 TPC cooling Empty tank (after 18:00) Muon TRG TRD Wiener PS 8:00 to 18:00: no access CR1-5 and Expo TRD: back-Plane modifications LV Wiener (~80 PSU) and Modified LV patch panels and new cables (after 18:00) Maintenance Local decision electronics (after 18:00) Upgrade FE threshold distributors, higher segmentation (after 18:00) ALICE planning meeting

  14. Activities in MNF - Week 49 - 8/12 Wednesday 8:00 to 18:00: no access UX25 18:00 to 8:00: access in general mode ALICE planning meeting

  15. It H Activities in UX25 - Week 49 - 9/12 Thursday 8:00 to 18:00: no access UX25 (except Transport and VAC) 18:00 to 8:00: access in general mode EMCal team at CERN: fit rollers on all SMs RAMSES: removal of Data Acquisition modules CR5 Interruption on auto-transfert network (from 07:00 till 07:05). No access underground TRD Wiener PS MNF shielding VAC Muon TRK: CROCUS firmware upgrade TPC FEC and TRD LV Stabilizers TRD Wiener PS No access CR1-5 during lifting up of 5 big beams ALICE planning meeting

  16. Activities in MNF - Week 49 - 9/12 Thursday 8:00 to 18:00: no access UX25 18:00 to 8:00: access in general mode ALICE planning meeting

  17. It LV156 H Activities in UX25 - Week 49 - 10/12 Friday 8:00 to 18:00: no access UX25 (except Transport) 18:00 to 8:00: access in general mode EMCal team at CERN: fit rollers on all SMs Gas functional test (2h no access UX25 and CR1-5) Maintenance PX24 MAD (transparent) TRD Wiener PS MNF shielding Muon TRK: CROCUS firmware upgrade TPC FEC and TRD LV TRD Wiener PS Move if needed No access CR1-5 during lifting up of 5 big beams ALICE planning meeting

  18. Activities in MNF - Week 49 - 10/12 Friday 8:00 to 18:00: no access UX25 18:00 to 8:00: access in general mode ALICE planning meeting

  19. It LV156 H Activities in UX25 - Week 49 - 11/12 Saturday 8:00 to 18:00: no access UX25 (except Transport) 18:00 to 8:00: access in general mode TRD Wiener PS TRD LV MNF shielding TRD Wiener PS ALICE planning meeting

  20. Activities in MNF - Week 49 - 11/12 Saturday 8:00 to 18:00: no access UX25 18:00 to 8:00: access in general mode ALICE planning meeting

  21. It H Activities in UX25 - Week 49 - 12/12 Sunday Access in general mode ALICE planning meeting

  22. Activities in MNF - Week 49 - 12/12 Sunday Access in general mode ALICE planning meeting

  23. Services interruption

  24. Maintenance gas systems New gas monitoring 13 Functional tests • 13-15/12: • Stop N2, CO2, Neon, Ar and C2H2F4 (24 hours max N2, CO2 and Neon) • TRD backup (N2 bottle in CR5) – HMPID backup (Ar bottle in SG2) ALICE planning meeting

  25. Gas system status over Christmas • TPC & TRD: ON • TOF: ON – stop from 12 to 21/1 (cooling stop, KNF pump stopped) • HMPID: ON (Ar backup) • PHOS: N2 flushing • PMD: ON (except wks 1-2 – gas stop) • Muon TRK: backup CO2 • Muon TRG: backup Ar • No flammable gases from 7 Dec until 21 Jan PM (after maintenance L3 ventilation) ALICE planning meeting Albin

  26. Maintenance cooling unitsCooling Plants and Primary Network TOF/PHOS EMC Maintenance and consolidation TPC 10 17 SSD/SDD 12 TPC Cooling towers TRD HMPID 21 SPD Maintenance on production network. No primary water from 12/1 (PM) to 21/1 CR1-2-3, the Wiener PS and detector cooling plants affected (plants can RUN, but no cooling power). Part of DCS will keep running Maintenance on cooling plants. Replacement of pneumatic actuators for TOF/TRD/TPC plants + TOF/PHOS flowmeter. CP will be stopped during maintenance ALICE planning meeting

  27. Maintenance ventilation units UX25, Muon TRK-TRG UX25, Muon TRK-TRG 17 12 SG2 L3 ALICE planning meeting

  28. Safety and electrical systems PX24 fire detect. 20 Evacuation SNIFFER mainten. UX25 fire detect. + red phones UPS UPS DSS Auto-transfert Evacuation Evacuation Early morning/late evening (tbc) UPS AUG DSO ALICE planning meeting

  29. Safety and electrical systemsImpact on ALICE • EN/EL: interruption on auto-transfert network (9/12 from 07:00 till 07:05): • All 'normal power‘ will be cut for 5 minutes: wall outlets, non-UPS in the ACR, SXL2, non-UPS power for the cooling plants, gas systems • It will not affect the 'machine network‘ (all racks will remain powered (part of the 'EXD', machine, network) • This network also provides the power to the UPSes, so they will run on battery for the time of this cut • See https://edms.cern.ch/file/1106913/1/ENNC_2010_196.pdf • EN/EL: AUG Test (20/1) (Arrêt Urgence General – General Emergency Stop) • Major electrical perturbation. Also ACR affected • DSS modification (13/1) • Will stop the full DSS, trigger all interlocks, including stopping power to all racks • LHC evacuation tests (7/12 after 18:00 and 24/12 tbc) • no access UX25 ALICE planning meeting

  30. DAQ upgrade plans • 21st Dec PM till the 04th Jan included • The DAQ will be OFF during the CERN closure. • The ACR PCs will be left ON to give access to the DCS for the detectors teams who need it. • 5th to the 11th of January included • DAQ restarted on the first working day for 1 week. The DAQ will be switched ON with the present version of all software. Allow a quick commissioning after the installation of new detector modules or the intervention on existing detectors. • 12th to the 23rd Jan included • The DAQ will be OFF during the cooling interruption at P2. • DAQ renovated (see TB December) • 24th January • The DAQ will be ON again. It will run under SLC5 64 bits unless there would be an unexpected key problem. • The electronic logbook will remain available during the whole period. When the DAQ will be OFF, it will be running in the DAQ lab in Meyrin. There will be a few hours of interruption to switch from P2 to Meyrin and back. ALICE planning meeting Pierre/Uli

  31. DCS plans Baseline: DCS will be operational all times where technically possible With ‘best effort’ support With access restrictions during CERN End-of-Year closure (22/12 – 4/1) Many activities and upgrades are planned Will be coordinated with individual detectors to minimise impact For central systems, as much as possible in shadow of other perturbations (e.g. cooling stop) Perturbations (e.g. for reboots etc.) cannot be excluded Detectors are invited to communicate ‘critical periods’, with services needed Will try to cater for detector needs as much as possible Known perturbations: Tue 7/12 10:00 – 12:00, interruptions of the GPN link to/from P2 Upgrade of router, test impact on ALICE Wk50 (13-17/12) – major updates to all PC (many perturbations to be expected) 12/1 – 21/1 (cooling stop), only minimal central services. All detector DCS switched off, except for special requests and if cooling power allows More detailed planning at weekly and daily meetings 26/11/10 ALICE planning meeting ALICE planning meeting 31 André / Peter

  32. Magnet control upgrade • Wk 49: nous devons intervenir dans la MCR pour: • changement des alimentations 24V et 48 V des systèmes MSS et MCR (préventif) • changement des modules convertisseurs PT100 des hots points du Solénoïde (correctif suite à deux incidents ayant entrainés l'arrêt du Solénoïde) et en UX25, comme Philippe Bouvier l'a déjà signalé: • recâblage des AU du dipôle et du Solénoïde • signalisation du champ magnétique du dipôle et du Solénoïde • Nous étudions toujours une solution pour le monitoring des températures du Solénoïde. • L'arrêt de fin d'année va permettre de faire une meilleure approche de ce qui est existant en UX25. • En ce qui concerne l'alimentation électrique de la MCR, nous dépendons actuellement d'une seule source de courant sous UPS avec secours diesel. • Afin d'établir une redondance pour l'alimentation de la MCR je souhaiterais installer une seconde source d'alimentation sous UPS. • Je sais qu'une étude est faite à ALICE pour augmenter la puissance des UPS existants en 2012. • Je souhaiterais que cette demande soit incluse pour le calcul de puissance des nouveaux UPS (besoin pour la MCR: 16A en monophasé) ALICE planning meeting Pascal

  33. VIP visits – wk 49 • Portuguese Press visit to CERN (7/12 14:00 to 15:00). 10 persons ALICE planning meeting

  34. AOB • SLIMOS shifts still missing in wks 49-50 and 4-5 ALICE planning meeting