1 / 20

Presented by: Mike Bailey PE Director of Engineering

Presented by: Mike Bailey PE Director of Engineering. Lessons Learned: Why data is not Always enough. Case Study #1. First Case Study. Oregon based co-op food processor with two plants U tility provided 15-minute electric data Multiple products with mix of equipment and processes

lumina
Télécharger la présentation

Presented by: Mike Bailey PE Director of Engineering

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presented by: Mike Bailey PEDirector of Engineering Lessons Learned: Why data is not Always enough

  2. Case Study #1 First Case Study • Oregon based co-op food processor with two plants • Utility provided 15-minute electric data • Multiple products with mix of equipment and processes • Digital process controls with in plant control technicians • Full year operation (little seasonality) • Full year, stable workforce • Capital available for projects

  3. Case Study #1 Plant AEnergy Use • Energy Sources • Electricity • Steam (from utility co-gen plant) • Natural Gas • Production and Energy Use • Electricity and Steam • Seasonal Energy Use • Natural Gas

  4. Case Study #1 Plant BEnergy Use • Energy Sources • Electricity • Diesel • Production and Energy Use • Operational Changes • Switched from diesel to electric boiler in mid-2009 • Electricity Energy Intensity • ~3 times greater than Plant Aper Vat • Production Cost • ~4 times the production cost of Plant Aper Vat

  5. Case Study #1 Rebates and Incentives (at time of study) • BPA Energy Smart Industrial (ESI) Program • Incentive Programs and Pilot Programs • Custom Projects • $0.25/kWh up to 70% of project cost • Energy Project Manager (EPM) • Potential incentive for Plant Ais $100,000 • Potential incentive for Plant Bis $270,000 • Track & Tune (T&T) • High Performance Energy Manager (HPEM) • Northwest Lighting Trade Ally Network (TAN) • Green Motors Initiative • Business Energy Tax Credit (BETC) • Option 1: Credit taken directly by co-op • Up to 35% of project costs (before utility incentives) over a five year period • Option 2: “Pass-through” to a third party • Up to 25.5% of project costs (30.5% for smaller projects)

  6. Case Study #1 Example Energy Measures • EEM 1: Lighting • Estimated simple payback: Immediate • EEM 2: Refrigeration • Estimated simple payback: 2.2 years • EEM 3: Compressed Air System • Estimated simple payback: Immediate

  7. Case Study #1 Example Energy Measures • EEM 4: Heated Regenerative Dryers • Estimated simple payback: Immediate • EEM 5: Waste Water Treatment Blower Replacement • Estimated simple payback: 2.8 years • EEM 6: Heat Recovery • Estimated simple payback: 2.4 years • EEM 7: Motor Efficiency • Estimated simple payback: Immediate • EEM 8: Boilers • Estimated simple payback: 0.6 years

  8. Case Study #1 Results • Very little progress on facility equipment or process optimization – staff focused on capital expansion projects • Lack of upper management attention to utility costs • No owner for utility energy data or utility cost management • Did not use real time utility data - did not allocate energy use between process and products • Implemented some measures such as lighting but did not proceed with energy manager position (funded by BPA)

  9. Case Study #2 Second Case Study • NW based co-op food processor with multiple plants • Utility provided 15-minute electric data • Multiple products with mix of equipment and processes • Manual and electric controls – no centralized process control • No in-plant controls staff • Seasonal products • Seasonal work-force with moderate turn-over • Little capital available for projects

  10. Case Study #2 Many Different Crops

  11. Case Study #2 Seasonal Utility Use

  12. Case Study #2 Poor Understanding of Energy Drivers • Refrigeration Issue Example • Staging condensing tower fans and pumps (200 hp total) based on compressor discharge pressure (3,000 hp total) • Boiler Issue Example • 400 BHP 1980’s Boiler used three months per year • 600 BHP late 1990’s Boiler used four months per year • 3 year old audit study recommending controls upgrades and stack heat recovery – unfunded due to 5 year pay-back

  13. Case Study #2 Identified Utility Cost Drivers

  14. Case Study #2 Estimated Utility Cost by Product “Carrots Don’t Care”

  15. Case Study #2 Now for the data… • Plant Energy Manager Team established • Utility real time data owner assigned • Worked with utility to understand tool, work out communication issues • Serve as resource for internal staff to understand data • Each process owner responsible for managing energy drivers • Process owners worked with utility data owner to “break apart utility use” • Team created control charts real time data flagged issues and trends • Regular summary reporting to plant management

  16. Case Study #2 Boiler Recommendations • Only use one Boiler • Eliminate “Hot standby” spare • Manage production volume during carrots to avoid needed to operate two boilers • Add Stack Economizer – Boiler Feed-Water pre-heater to one boiler • Payback less than 1 year – if boiler used full season • Add boiler combustion controls • Manage blanchers to reduce boiler demand RESULT: Capital approved to fund ONE boiler upgrade

  17. Case Study #2 Refrigeration Recommendations • Do NOT stage condenser tower fans & pumps – run as much as possible to reduce condenser pressure • 200HP total for condenser towers • >3000HP total compressor capacity • Stage Compressor controls • Always have smallest compressor as Trim • Large compressors should be fully loaded if on • Install VFD on ONE compressor and dedicate that to Trim • Track Compressor Log to incremental electrical meter data

  18. Lessons Learned Why was #2 Successful but #1 was not? • Upper management Serious about managing utility costs • “Seek First to Understand” what drive energy use • Data is not helpful if it is not converted to information • Begins and ends with people! • Once system and drivers are known, data used to manage • Data without systems knowledge is useless • Decisions makers must be will to ACT on the data – PARTICULARLY when it contradicts old assumptions

  19. Data Is Necessary But Not Sufficient…

  20. Thank you! Mike Bailey PE mbailey@ecova.com

More Related