1 / 11

MINIATURE ENGINEERING SYSTEMS GROUP :

MINIATURE ENGINEERING SYSTEMS GROUP :. COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE & TRANSFER FACILITIES AT NASA KSC Presented by – K.V.Krishna Murty. References : A report on ‘NASA KSC Base Center Hydrogen Operations’ by Dr.Addison Bain, 2001-2002.

lynna
Télécharger la présentation

MINIATURE ENGINEERING SYSTEMS GROUP :

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE & TRANSFER FACILITIES AT NASA KSC Presented by – K.V.Krishna Murty

  2. References: • A report on ‘NASA KSC Base Center Hydrogen Operations’ by Dr.Addison Bain, 2001-2002. • Communication of Mr.Thomas Tomsik (NASA GRC). • Communication of Mr.Bill Notardonato (NASA KSC).

  3. LH2 Storage and Transfer facilities: • LH2 Storage Tank: • Outer Diameter of the outer shell = 70 ft, • Inner Diameter of the inner shell = 62.5 ft, • Material – Stainless Steel. •  LH2 Transfer Line: •  Fill Rate to ET = 8,400 gpm to 10,000 gpm, •  Outer Jacket m/l – Stainless Steel, •  Inner Jacket m/l – Welded Invar,

  4. Economic Analysis of Pre-Chilling of metals: • Assumptions and Values: • Latent Heat of Vaporization of LH2 (L): 56 W-hr/lb • Cost of Electricity = 0.05 $/kW-hr • LH2 cost = 2 $/lb • Specific Heat of 304 SS at cryogenic temperature = 144 J/lb-K • Density of 304 SS = 0.285 lb/in3 = 7,900 kg/m3 • Specific Heat of Welded Invar at cryogenic temperature = 149 J/lb-K • Density of Welded Invar = 0.291 lb/in3 = 8,055 kg/m3 • Thickness of storage tank = ½ in (assumed for calculations), • VJ Transfer Line Length = 1500 ft • Cooling Power of 1 RTBC = 1 kW @ 19K

  5. Cost of Pre-Chilling: 304 SS: Cost of pre-chilling per lb of SS: 310K80K 80K19K LH2 Boil-off $0.328 $0.087 RTBC $0.004 $0.018 Cost of pre-chilling 304 SS over the complete range (310K  19K): cost/lb of SS Savings Boil-off $0.414 0 % 310K to 80K by RTBC, rest by boil-off $0.091 78 % 310K to 19K by RTBC $0.022 95 %

  6. Pre-Chilling of 304 SS (with 1 RTB): Pre-chilling with top stage  to 80 K Time Mass (min) (lb) 7½ 208 15 417 22½ 625 30 833 Pre-chilling with 2 stages  Time Mass (min) (lb) 45 208 90 417 135 625 180 833 Pre-chilling with bottom stage  to 19K Time Mass (min) (lb) 37½ 208 75 417 112½ 625 150 833

  7. Cost of Pre-Chilling: Welded Invar: Cost of pre-chilling per lb of Welded Invar: 310K80K 80K19K LH2 Boil-off $0.339 $0.090 RTBC $0.004 $0.019 Cost of pre-chilling Welded Invar over the complete range (310K  19K): cost/lb of WI Savings Boil-off $0.429 0 % 310K to 80K by RTBC, rest by boil-off $0.094 78 % 310K to 19K by RTBC $0.023 95 %

  8. Cost savings in maintaining the system at LH2 temperature by RTBC: Considering 1 kW of heat leakage, If LH2 is let to boil-off: Rate of LH2 boil-off = 430 lb/day Cost of LH2 boil-off = 860 $/day If RTBC is used to prevent LH2 boil-off: Number of RTBC required = 1 Total cost of input power for 1 RTBC = 180 $/day The savings from complete boil-off to RTBC use for Pre-Chill = (860-180)/860 ≈ 79 %

  9. Input power required to maintain the Storage Tank (Pad B) at LH2 temperature:LH2 Boil - Off = m = 600 gallons/day = 355 lb/day, Cost of LH2 Boil-Off = $ 260,000/yr, Input power required = P where,P= m*L = (355*56)/24 = 830 W.So, a nominal cooling power of about 1 kW at 19K would be appropriate.

  10. Pre-Chilling of Storage Tank: Time required to pre-chill the storage tank to 19 K with 1 RTB = 770 hr,Cost of LH2 Boil-Off for Pre-Chill = $ 105,000 Pre-Chilling of Transfer Line:LH2 Boil-Off Cost = $ 17,000,Number of RTBCs required to pre-chill the transfer line to 19K in 9 hrs, I.e., with both stages = 15 (1 for every 100 feet of the transfer line),Number of RTBCs required to pre-chill the transfer line to 80K in 9 hrs, I.e., if only the top stage is used = 3 (1 for every 500 feet of the transfer line).

  11. Conclusion: • The calculation shows that it is economically effective to use cryo-coolers for cooling the Liquid Hydrogen Vacuum Jacket storage & transfer facilities at NASA KSC. • Please NOTE: This analysis considers only the running costs associated with the cryocoolers. It does not take into account the installation and maintenance costs associated with the cryocoolers.

More Related