Project Estimating Overview

Project Estimating Overview. Module: 03.1 – PS&E Revised: June 2, 2014. Purpose:. Illustrate the scope of estimating. Define the types of estimates. Describe the contents of a typical estimate. Begin the description of “how to do” an estimate. Learning Objectives:.

maegan
Télécharger la présentation

Project Estimating Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Estimating Overview Module: 03.1 – PS&ERevised: June 2, 2014 CVEN-349 Maxwell

  2. Purpose: • Illustrate the scope of estimating. • Define the types of estimates. • Describe the contents of a typical estimate. • Begin the description of “how to do” an estimate. CVEN-349 Maxwell

  3. Learning Objectives: • Students should be able to list the steps in the estimating process. • Students should be able to define the cost elements of a simple construction estimate. • Students should be able compute the value of these cost elements, given appropriate data. CVEN-349 Maxwell

  4. Overview • Types of Estimates • Estimating Process • Cost Components • Estimating Resources • Work Packages • Parametric Estimates CVEN-349 Maxwell

  5. Types of Estimates • Feasibility Estimate(s) • Preliminary or Pre-construction Estimate(s) • Unit Cost Estimate – • Parametric Estimate – • Factor Estimate – • Definitive or detailed estimates: CVEN 473 • Working drawings and estimates: CVEN 405 CVEN-349 Maxwell

  6. AACE Classifications • Order of Magnitude Estimates • Budget Estimates • Definitive Estimates CVEN-349 Maxwell

  7. Definitive Estimating Process • Develop a Work Element Structure • CSI Categories • Site Work • Concrete • Etc. • Schedule the Work Elements • Bar Chart • CPM Diagram • These should be related processes! CVEN-349 Maxwell

  8. Continued • Organize Historical Data • Rationalize and Scale to Job at Hand • Apply Learning Curves • Identify Crew Configurations • Compute Direct Labor, Material, and Equipment Costs • Estimate Indirect and G&A Costs CVEN-349 Maxwell

  9. Continued • Apply Inflation and Factors • Compute Costs • Fine Tune • Publish in Useful Form CVEN-349 Maxwell

  10. In Class Pair Exercise 03.01 • Let’s estimate the “order of magnitude” cost of a parking garage at TAMU. • How many cars or spaces? • Get cost per space from R.S. Means. • Arrive at a range, etc. • Compute estimate. CVEN-349 Maxwell

  11. Definitive Estimate Direct Cost Components • Direct Material Costs (30%-50%) • Direct Labor Costs (40%-60%) • Wage Rates • Productivity • Direct Equipment Costs (20%-30%) Direct Costs: Those costs that are applied directly to the product in question – This is an important concept. CVEN-349 Maxwell

  12. Cont’d – Indirect Costs & Profit • Indirect Job Supervision – Clerical Staff • Other Project Indirects – Office Trailer • Company Indirects – General and Administrative (G&A) Indirect Costs: All costs that are NOT direct. • Profit – Net of Revenue less all Costs, including interest costs on Working Capital. CVEN-349 Maxwell

  13. Resources • R. S. Means, etc. (See Handouts) • Historical Project Data • Productivity Work Standards • Scaling Factors: Location, Inflation, Customer, etc. A lot of the questions I get asked by “call-ins” can be answered from information in one or more of the Means Manuals. CVEN-349 Maxwell

  14. Assessment: • Take a minute to write 1 sentence on the “muddiest” topic for the day. CVEN-349 Maxwell