1 / 13

“RAABSTEG” FELDBACH (AUT) Institute for Timber Engineering and Wood Technology, TU Graz / Austria Case study no. 3

“RAABSTEG” FELDBACH (AUT) Institute for Timber Engineering and Wood Technology, TU Graz / Austria Case study no. 3. Leonardo da Vinci project no. CZ/06/B/F/PP-168007 WP6 – Case Studies PC 3 – A set of case studies. General Information.

mahdis
Télécharger la présentation

“RAABSTEG” FELDBACH (AUT) Institute for Timber Engineering and Wood Technology, TU Graz / Austria Case study no. 3

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. “RAABSTEG” FELDBACH (AUT)Institute for Timber Engineering and Wood Technology, TU Graz / AustriaCase study no. 3 Leonardo da Vinci project no. CZ/06/B/F/PP-168007 WP6 – Case Studies PC 3 – A set of case studies

  2. General Information • Type of building:(Covered) Pedestrian and bicycle bridge • Structural System:Cable supported single-span girder withsuspended bridge deck • Owner:City of Feldbach / Austria • Location:Feldbach / Austria • Erection date:08 / 1998 • Architectural, structural and construction design:LIGNUM CONSULT, Graz / Austria • Manufacturer of the timber structure:Stingl GesmbH, Trofaiach / Austria

  3. Longitudinal Section andStructural System Longitudinal Section(with dimensions) Structural System(with dimensions)

  4. Cross section

  5. Detail CLT - plate 130 mm (19_l_NF+34_q+24_l+34_q+19_l_NF) Detail Detail: Deck Construction Load carrying: - in longitudinal direction as T-beam - in longitudinal direction for horizontal forces - in cross direction for load distribution purposes Main girder 2 x 200 / 450 mm out of GL36c- (BS 18 c)- twin girder machine graded C35m- (MS 13)-lamellas machine graded C40m- (MS 17)-lamellas

  6. Detail: Connection Suspension Bar on Main Girder

  7. Detail: Support Detail – Connection on Tie Bar

  8. Detail: Railing System

  9. Assembling / Transport Assembling in the production hall of the manufacturer Transport by means of a truckwith a trailer

  10. Erection Erection concept Erection by means of three auto-cranes

  11. Impressions View from the cycle track View in londitudinal direction

  12. Impressions View from Raab River

  13. Thank you for your attention! http://fast10.vsb.cz/temtis/en/

More Related