1 / 8

Friday 31 st August & night

Friday 31 st August & night. 00:03 Stable beams #3016. Initial luminosity ~6.7x10^33 cm -2 s -1 . 08:59 Electrical network glitch - Beam dump - ~125 pb-1 in 9 hours . Lost 3 sectors (1-4) with fast abort of the mains and trip of the dipoles of ALICE and LHCb

makani
Télécharger la présentation

Friday 31 st August & night

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Friday 31st August & night • 00:03 Stable beams #3016. Initial luminosity ~6.7x10^33 cm-2s-1. • 08:59 Electrical network glitch - Beam dump - ~125 pb-1 in 9 hours. • Lost 3 sectors (1-4) with fast abort of the mains and trip of the dipoles of ALICE and LHCb • 11:36 At the end of the pre-cycle another electrical problem appeared in point 8 • Problems with the beams from the BOOSTER and a vacuum spike in the SPS extraction kicker (LSS4) • 14:33 Injection physics beams • Large emittances from the injector chain, up to 2.6um for B2V. • 15:33 Lost beam at the very end of the ramp (3.9 TeV) • Trip of IT.R1: the module RTQX2.R1 went in VS_fault, with an overcurrent reading. OK on the next pre-cycle. • 18:55 Stable beam fill #3018, initial lumi 6.6e33 cm-2s-1 • 08:03 Operator dump, integrated lumi’s 173 pb-1 • 08:40 Trip of RQX.R1, same as yesterday afternoon – waiting for news LHC 9:00 meeting

  2. Large beams from the injectors Very likely the cause of the losses end of ramp and the squeeze of the fills Thursday night as well. LHC 9:00 meeting

  3. Fill # 3018 Slightly better emittances from the injectors B2 lifetime suffering during squeeze Initial lumi’s around 6.7 / 6.5 e33 cm-2s-1: suffering from reduced brightness. LHC 9:00 meeting

  4. Check abort gap population by cleaning Effect on measured BLM losses at the collimators is very reproducible B1 Matteo & Lasse B2 LHC 9:00 meeting

  5. Effect on beam current & lumi Matteo & Lasse LHC 9:00 meeting

  6. BSRT B1, out position, stays cold. LHC 9:00 meeting

  7. Injection kicker temperatures Not running long enough to get the injection kickers hot, yet LHC 9:00 meeting

  8. Ahead • Physics • SPS EDF intervention • Monday morning around 9 h for about two hours • Close to CCR again – same test took computers in CCR down • Will only allow safe beams in the LHC • Candidate tests • Rogelio skew sextupole polarity • Rogelio triplet octupole correct circuit tests & polarity • On the waiting list • Totem in at end of fill • RF batch-by-batch blow-up LHC 9:00 meeting

More Related