1 / 35

FP6 Contractual issues

FP6 Contractual issues. PRESENTATION OUTLINE. Participation Contract structure Collective Approach signature and entry into force collective Responsibility consortium Agreement Provisions of general conditions, special reference to: financial provisions controls and sanctions.

marlee
Télécharger la présentation

FP6 Contractual issues

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FP6 Contractual issues

  2. PRESENTATION OUTLINE • Participation • Contract structure • Collective Approach • signature and entry into force • collective Responsibility • consortium Agreement • Provisions of general conditions, special reference to: • financial provisions • controls and sanctions

  3. General Principles • Reflect requirement of the Legal Framerwork • Simplification • No different categories of contractors • Reduction of the number of contracts • Collective approach • Greater flexibility • the Work Programme may adjust Rules • flexibility in the composition and changes to consortium • Greater autonomy for participants

  4. Participation • New Every legal entity that contributes to the project • General Rule: Participant = contractor Every legal entity contributing to a project must have a contractual link with the Community • Exceptional cases: subject to very restrictive rules • Third parties identified in Annex I • Subcontractors

  5. Participation • Third parties identified in Annex I • In most of the cases they do not participate, they simply make their resources available to a contractor, this is not a case of participation but only a question of eligibility of the cost of these resources • In exceptional cases: “participation” of members of entities (such as EEIG, SMEs Associations) : • their members can do some of the work on the project even though they are third parties • contractor and third parties must have a previous agreement, normally the constitution • the third parties, the agreement and the tasks must be identified in Annex I

  6. Participation Subcontracting (1) • Contractors shall ensure that the work to be performed can be carried out by them. • Exception: where it is necessary to subcontract certain elements of the work, this should be clearly identified in Annex I. • Management activities should not be subcontracted • Minor services may be subcontracted: • which do not represent core elements of the project • which cannot be directly assumed by contractors • where necessary for the performance of the project

  7. Participation Subcontracting (2) • Consequences : • Costs must be awarded to the bid offering best value for money (best price-quality ratio) (no more competitive tender) • Responsibility of the contractor who enters in subcontract • The IPR belong to the contractor

  8. Contract Structure • Core contract (standard with specifics of project and special clauses) new version 23 Octobre 2003 • Annex I (technical tasks - the “project”) • Annex II General Conditions (applicable to every instrument) • Annex III Instrument specific provisions (specific to instrument - 5)

  9. Contract Structure • Annex IV - Form A Consent of contractors identified in the core-contract (article 1.2) to accede to the contract. To be signed by the contractor concerned and by the coordinator. • Annex V - Form B Accession of new legal entities to the contract. To be signed by the new contractor concerned and by the coordinator • Annex VI - Form C Financial statement per activity. Specific to each Instrument and/or type of action. To be filled periodically by each contractor

  10. Signature and entry into force(1) • Contractual link of all contractors with the Commission (Form A signed by authorised legal representative of the contractor identified in contract, if change form A accompanied by new CPF identifying the new legal representative or letter indicating that other person is also legal representative) • New Contract enters into force upon signature of coordinator and the Commission. Coordinator must ensure other contractors sign within delays (30/45/60 days)

  11. Signature and entry into force (2) • Distribution of pre-financing to coordinator : within 45 days of : date of entry into force of contract/date of signature of minimum number of participants/date of signature of last contractor • Distribution of pre-financing to contractors : not before minimum number of contractors have acceded to the contract • Project begins in the date established in the contract (this can be before the contract enters into force but usually later)

  12. LIABILITY (1) • New : Collective responsibility of contractors • Mechanism by which a contractor may be held liable, technically and/or financially, fully or partially, for the action of another contractor • Consequence of FP6 principle of « autonomy of the consortium » : if the money is granted to the consortium, which decides on its allocation, then consortium as a whole is held liable.

  13. LIABILITY (2) • Implementation: applied as a last resort • Breach of contract • Depending on the nature of the breach, the consortium will be invited to find the appropriate solution(technical responsibility) • If no solution is found, the defaulting contractor is excluded and the consortium is requested to continue the project(technical responsibility with financial consequences) • If the consortium refuses to perform: • 1 - the contract is terminated • 2 - the consortium is requested to reimburse money owed by the defaulting contractor(collective financial responsibility)

  14. LIABILITY (3) • Implementation: limitations • Limited in proportion to the participant’s share of costs in the project, up to the total payment they are entitled to receive • IOs, public bodies or entities guaranteed by MS/AS solely responsible for their own debts • Exceptions for specific actions for SME’s, fellowships, duly justified cases of specific support actions • Without prejudice to civil and criminal actions to be launched against the defaulting contractor

  15. Consortium agreement General principles • Regulates internal organisation and management of consortium (Mandatory for IP and NoE) • New Compulsory unless otherwise mentioned in the call for proposal • Between contractors - NOT signed nor approved by the Commission • Non binding guidelines provided by the Commission

  16. Consortium agreementManagement of the consortium • Distribution of funds paid to the consortium (via the coordinator) • No automatic pre-allocation of the funds among contractors : allocation of funds among contractors to be decided by the consortium (via the consortium agreement ) • Evolution of the project • Organisation of work to be carried out (sub-projects) • Reports presented and submitted by the consortium (via the coordinator) • Decision-making process • Evolution of the consortium’ composition (modification)

  17. Amendments • Art.10 of Core Contract & Art.8 of Annex II • Request in writing • New at the request of the coordinator, deemed to act on behalf of the consortium • NewTacit amendments with implicit agreement of the Commission within 6 weeks onlyfor modification and evolution of the consortium and for technical reports • New in IP/NoE, enlargement of the consortium to new contractors and new activities may be foreseen. This enlargement follows a competitive call launched by the consortium with evaluation of proposals by external experts

  18. Financing Grant for integration Grant to the budget Flat-rate Networks of excellence  Integrated Projects  Specific targeted research projects  Specific research projects for SMEs  Integrated initiatives relating to infrastructure  Actions to promote human resources & mobility   Coordination actions  Specific support actions  

  19. Financial Provisions Grant for integration (NoE) • Newmechanism • Calculation basis: number of researchers to be integrated not as a %age of the budget for the JPA • Payment basis: completion of the JPA + costs certificates mentioning that the costs incurred are greater than the grant itself

  20. Financial Provisions Grant to the budget • Calculation basis: %age of the preliminary budget of the execution plan • Payment basis: covers a share of the expenditure incurred, necessary for the execution of the indirect action • %age depends on: • type of activity • participant involved (cost models)

  21. Financing: cost reporting models • FC: actual direct and indirect costs • NewFCF (variant of FC): actual direct costs + flat rate for indirect costs (20% of total actual direct costs, except costs of subcontracts - all instruments) • AC: actual additional direct costs + flat rate for indirect costs (20% of total actual additional direct costs, except costs of subcontracts)

  22. Financing: cost reporting models • General Rule:a legal entity applies the same cost model in ALL contracts established under FP6 except may move from AC to FCF/FC or from FCF to FC (“one way ticket”)

  23. Financing Type of activity Research and technological development (including innovation related activity) Demonstration Training Other specific support activities NewConsortium Management : costs reimbursed up to 100% within the limit of 7% of Community contribution(AC contractors apply FCF)

  24. Financial Provisions Identification of costs • New No cost categories but list of ineligible costs • To be eligible costs must be : • actual, economic and necessary for the project • incurred during the duration of the project (exception : costs of final reports) • recorded in the accounts of the contractor (or third parties) and must exclude indirect taxes, duties, interests, costs reimbursed in respect of another Community project • follow contractors own accounting rules • Not give rise to profit • Audit certificates by external auditor (For public bodies - competent public auditor)

  25. Financing Receipts • Three kinds of receipts must be taken into consideration in order to avoid any possibility of profit: • Financial transfers or their equivalent to the contractor from third parties ; • Contributions in kind from third parties; • Income generated by the project. • In the first two cases (financial transfers or contributions in kind), these endowments are considered as receipts of the project if the third party has provided them specifically to be used in the project. • If, on the other hand, these endowments are at the discretion of thecontractor they are not to be considered as receipts.

  26. Financing Receipts • In thefirst two cases, where contributions from third parties are used for the project by the contractor, the latter is required toinformthe third party of this use and in accordance with the national legislation or practice in force. • In the case of income generated by the project itself: • General rule: any income generated by the project itself, including the sale of assets bought for the project, are considered as income to the project (receipts) • Derogation: income generated by the use of the knowledge resulting from the project is not considered as a receipt

  27. Financing Reporting periods (12 months for IP and NoE) • The consortium will submit the following reports to the Commission( within 45 days after the end of each reporting period) : a periodic activity report • a periodic management report (justification of resources/Form C/summary financial report) • a report on the distribution between contractors • supplementary reports required by Annex to this contract • an audit certificate when (certification of costs incurred in corresponding period)

  28. Financing Audit certificates Article II.26 • each contractor shall provide an audit certificate prepared and certified by an external auditor • for public bodies - competent public officer • for each period for which an audit certificate is required: Article 7 • an audit certificate must be provided by each contractor requesting a Community financial contribution exceeding 750.000€. • every 12 months for IP/NoE: Annex III (based on the reporting period)

  29. Financing Payment Modalities • Initial pre-financing (Pre-financing for each period and 6 month of next period) • Periodic payment (base on consumption of pre-financing) • Periodic pre-financing (based on the applicable periodicity) • The Community financial contribution is paid to the coordinator on behalf of the contractors: the consortium decides on the allocation of each tranche of its between the contractors(consortium agreement)

  30. Payments and reporting schedule for a STREP, CA or SSA(example of a 3 year contract) Final activity report Final payment Reported costs + audit certificate (mandatory) Intermediate pre-financing and/or payment NB: impact on the total pre-financing Periodic activity report (mid-term review : optional) Reported costs + (audit certificate if required) Detailed work plan Initial advance 0 6 12 14 18 20 24 26 30 36 38 Months

  31. Payments and reporting schedule for an IP(example of a 4 year contract) Activity report Reported costs Activity report Detailed work plan Reported costs Adjusted advance Activity report Detailed work plan Reported costs Adjusted advance Activity report Detailed work plan Reported costs Adjusted advance Detailed work plan Initial advance 0 6 12 18 24 30 36 42 48 Months

  32. Controls and Audits • Objective to reinforce ex-post controls • To simplify and streamline ex-ante controls • As a counterbalance to increased autonomy for participants

  33. Controls and Audits • Reports • Periodic activity and financial reports • Supplementary reports if foreseen (in Annex I or III) • Audit certificates • Monitoringby Commission with external experts • Scientific, technological, and financial audits • Ethical audits

  34. Sanctions • Financial irregularity: exclusion criterion • Recovery decisions (art. 256 EC Treaty) • Other sanctions in contracts (overclaims)

  35. For more information • Legal framework within FP6 • Model contract : http://europa.eu.int/comm/research/fp6/working-groups/model-contract/index_en.html • Approved core contract and annex II • Approved annex III • Consortium checklist, financial guidelines, Form A- accession to the contract • Helpdesk • http://www.ipr-helpdesk.org • RTD-A03-Question-juridiques@cec.eu.int • General information on FP6 • http://europa.eu.int/comm/research/fp6/index_en.html

More Related