1 / 16

HSIP

HSIP. 1310-01-02/72 STH 50 Intersection with CTH D Reconstruction, Preservation LET: 02/10/2015 PSE: 08/01/2014 PM: Brian Pluemer. Project Location. CTH D. STH 50. Project Overview.

marnie
Télécharger la présentation

HSIP

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HSIP 1310-01-02/72 STH 50 Intersection with CTH D Reconstruction, Preservation LET: 02/10/2015 PSE: 08/01/2014 PM: Brian Pluemer

  2. Project Location CTH D STH 50

  3. Project Overview Intersection has had a high number of right angle crashes. There is a vertical curve 600ft to the east of the intersection with CTH D which may be a factor in drivers on CTH D misjudging speed of vehicles on STH 50. The median allows for refuge of one vehicle but drivers attempt to traverse the entire roadway. Connecting Highway: No Long Truck Route: Yes NHS Highway: Yes Oversize/Overweight Route: (OSOW): Yes; Primary

  4. Pavement Recommendation • Match existing pavement structure on STH 50 or CTH D depending on work location. • Minimize reconstruction as much as possible in intersection area.

  5. Traffic Volumes • Current Traffic Volumes • STH 50 (2008) AADT 18500

  6. Proposed Improvement • J-turn type intersection • Restricts movements to left turns only for traffic on STH 50 turning onto CTH D • Restricts traffic on CTH D to only making right turns onto STH 50 • Then allows for U-turns at appropriate median openings for traffic from CTH D that either wanted to go left or through.

  7. J-Turn Layout

  8. Project Photos On CTH D – Looking South

  9. STH 50 - Looking West

  10. STH 50 - Looking East

  11. Oncoming Traffic!!

  12. General Project Areas • Multimodal: No updates anticipated with proposed project scope. • Drainage: No updates anticipated with proposed project scope. Some ditch refinements will be needed in J-turn areas. • Signals: N/A.

  13. General Project Areas • Structures/Bridges: N/A • Railroad: N/A • Environmental: Programmatic Environmental Report (pER) with proposed scope. • Survey: Coordinate with Survey Unit as needed.

  14. GeneralProject Areas • Traffic: Any operational concerns that we should note for the designers • Safety: Looking for any additional ad hoc concerns in this area. • Signing: Updated as impacted by project. • Access Management: No changes anticipated with proposed scope.

  15. General Project Areas • Utilities: Trans 220 • Lighting: No impacts anticipated with current scope. • Right of Way: Small fee or TLE may be needed for J-turn areas

  16. Questions...

More Related