PHENIX Run-12 Status Report: Achieving Milestones and Prep for Au+Au Engineering Run

PHENIX successfully reached the total sampled luminosity goal for Cu+Au run after overcoming downtime due to lightning. It is now ready for the 5.GeV Au+Au engineering run, with VTX and FVTX moved to secure positions and radiation monitoring in place. The schedule is extended till June 28, with watching shifts planned. The team celebrated surpassing the integrated luminosity goal, thanks to everyone involved in this successful run. As the run concludes, achievements and records set by PHENIX are remarkable. The team is prepared for the next phase of operations, anticipating continued success in data collection.

martha
Télécharger la présentation

PHENIX Run-12 Status Report: Achieving Milestones and Prep for Au+Au Engineering Run

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Last PHENIX Run-12 Status Report (6/26) Xiaochun He • PHENIX reached the goal of the total sampled luminosity of Cu+Au run in the early morning on Sunday after ~36 hours of beam downtime due a power dip caused by lightening. • PHENIX is ready for the 5 GeVAu+Au engineering run. Both VTX and FVTX have been moved to their retracted position during a ~3.5-hour access yesterday. Six film badges were installed near beam pipe in order to monitoring the radiation level. • Our current shift schedule is extended to the end of June 28. The last two days will be watching shifts. PHENIX PM, X. HE

  2. Total Sampled Integrated Luminosity from Cu+Au 2.3% above the goal of 2.4 nb-1 within |z| < 10 cm. Reached the goal around 6am on Sunday (6/24) RHIC Time Meeting, X. HE

  3. 36-hour Beam Downtime Made the Moment Sweeter Daily Sample 36-hour downtime RHIC Time Meeting, X. HE

  4. Short IR Access on 6/25 Moved the PHENIX VTX/FVTX detector to their retracted position in order to avoid potential radiation damage to the silicon pixel layer. Installed six film badges for monitoring the radiation level during the 5 GeVAu+Au test run. Beam pipe On the south side of copper nose cone RHIC Time Meeting, X. HE

  5. Final Note • RHIC Run-12 is extremely successful. Our sincere thanks go to everyone involved in CA-D. • PHENIX has had a record-breaking run. It seems that PHENIX can measure anything that RHIC could provide. • I had a good time of sharing the stories from PHENIX weekly basis. In the meantime, I am very glad that it is about to be over.  RHIC Time Meeting, X. HE