1 / 47

Recent Fast Track Projects: Challenges, Successes & Lessons Learned

Recent Fast Track Projects: Challenges, Successes & Lessons Learned. AASHTO Sub-Committee on Design Meeting. The Ben Sawyer Bridge Design/Build Rehabilitation Project . Project History.

martha
Télécharger la présentation

Recent Fast Track Projects: Challenges, Successes & Lessons Learned

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Recent Fast Track Projects:Challenges, Successes & Lessons Learned AASHTO Sub-Committee on Design Meeting

  2. The Ben Sawyer Bridge Design/Build Rehabilitation Project

  3. Project History The historic Ben Sawyer Bridge was built in 1945 to carry locals and visitors between the east cooper barrier islands of Sullivan’s Island and Isle of Palms with Mount Pleasant and the rest of the Charleston area. For years, it was the only vehicular access for both Sullivan’s Island and the neighboring Isle of Palms. The Isle of Palms Connector was completed in 1993 and provided additional access to both Sullivan’s Island and the Isle of Palms.

  4. Project History The Ben Sawyer Bridge drew significant national attention when Hurricane Hugo came ashore in the Charleston area in 1989. The storm essentially picked up and rotated the swing span, leaving it tilted at a 45-degree angle, which created one of the lasting images of the hurricane’s devastation. The swing span was lifted back into place on October 5, 1989. One lane of the bridge was re-opened to traffic on October 8, 1989.

  5. Ben Sawyer – Post Hugo

  6. Advantages ofAccelerated Bridge Construction vs Traditional Construction Traffic Congestion • Traditional construction requires a 12-month, 11-mile detour through the Isle of Palms and Mt. Pleasant. • ABC requires a 10-day detour. • ABC avoids approximately 12 months of additional traffic congestion in both the Town of Mt. Pleasant and the Isle of Palms. • ABC reduces crash potential. • ABC reduces motor user costs. • ABC provides much greater access to both Sullivan’s Island and the Isle of Palms.

  7. Advantages ofAccelerated Bridge Construction vs. Traditional Construction Quality of Work • ABC improves the quality of work by constructing the swing span in an off-site controlled atmosphere. • The use of ABC further improves the quality by having the majority of the swing span’s electrical and mechanical components installed off-site as well. • Preliminary functional testing can be completed off-site without interference of the motoring public. Marine Traffic • ABC has much less impact to the intra-coastal waterway and its’ users.

  8. Design/Build Contract Highlights Project Duration – 540 days Liquidated Damages - $2,900/day over 540 Days DBE Goal – 5% 5-Year project warranty Warranty Bond ($5 Million) Professional Liability Insurance ($3 Million)

  9. Design/Build Contract Closure Requirements Duration – 10 days for Total Closure Closure Restrictions – Prohibited between April 1st and October 1st. Prohibited between December 15th and January 3rd. Incentive Pay - $2,500/hour up to 48 hours. Disincentive - $2,500/hour over 10 days with no cap. Swing Span fully operational

  10. Construction • Contractor – PCL Civil Constructors, Inc. • Construction Manager – PB Americas, Inc. • Designer – Hardesty & Hanover, LLP • Owner – SCDOT • FHWA – 100% oversight project

  11. Ben Sawyer Bridge

  12. Temporary Access & Supports

  13. Approach Spans

  14. Approach Spans

  15. Roller System

  16. Construction of Swing Span Off-site

  17. Transporting of Swing Span

  18. Old Swing Span being removed

  19. New Swing Span ready for placement

  20. New Swing Span being placed

  21. Emergency Contract for I-77 NB and SB Lanes over S-12-56 (Chester County) Replacement of Cracked Steel Plate GirderMain Spans

  22. Project Timeline • April 29, 2010 cracks in the webs of steel plate girders were found by the District 4 Bridge Inspection Team at I-77 NB and SB over S-12-56 in Chester County • Bridge Maintenance Office verified the severity of this condition, which did not exist as of the previous normal inspections 2 years ago • It is believed that the primary causes for the cracked girders on I-77 are the following: • thin web plates (<1/2”), these were 3/8” • diaphragm and stiffener web plates were only welded to the web and top flange thus causing an inordinate amount of torsion to be carried more directly by the web No weld Diaphragms offset due to skew Weld

  23. Project Timeline • Other factors contributing to the cracking were: • bridge skew • torsional fatigue and possible overall fatigue • possible overheating of the steel substrate due to multiple weld passes on the web to flange connection during fabrication • material mechanical properties (to be verified by testing) • construction loadings during I-77 construction could have reduced the fatigue life • Emergency Declaration was approved by SCDOT Secretary of Transportation Limehouse on May 3, 2010 • met two qualified bridge contractors on site May 4, who were given information that required the contractors to bid on temporarily shoring and replacing both steel plate girder main spans • District 4 closed the ramps and overpass/S-12-56 on May 5, 2010 and began work to improve the on and off ramps which were used for the detour • Bids were received on May 10, 2010 and an accelerated contract cost and schedule was negotiated on May 11, 2010 with the project low bidder, United Contractors

  24. Project Timeline • Temporary shoring was installed beginning May 12, 2010 to allow traffic to continue using the bridges until closed for work Temporary Shoring

  25. Project Timeline Bridges were closed on June 7, 2010 and demolition of the main spans began. New girders were set beginning June 11, 2010

  26. Project Timeline Deck pours started midweek of June 14, 2010

  27. Project Timeline • Both spans were completed by June 28, 2010 • Bridge Maintenance performed a project final inspection on June 28, 2010 Bridges were opened 2 days later on June 30, 2010

  28. Project Activity

  29. Project Activity

  30. Project Activity

  31. Project Activity

  32. Project Activity

  33. Project Activity

  34. Project Activity

  35. Project Activity

  36. Project Timeline • Ramps were reopened for normal use on July 23, 2010

  37. I-385 Rehab Project

  38. Project Scope& Schedule • Interstate Rehabilitation of I-385, approximately 15 miles, with 10” of high strength concrete • Raising of 6 overpass bridges • Bridge replacement of fly-over bridgethat connects I-26westbound to I-385 northbound • Shoulder widening with roller compacted concrete • I-385 northbound detoured; construction duration condensed from 3 years to 7 ½ months

  39. Traffic Control Plan • Northbound Detour • Relatively low ADT (17,600 to 21,900) within project corridor • Existing pavement width (32’) insufficient to stage or run head to head traffic • Parallel interstate in close proximity for detour traffic (15 mi./15 min.) • Good network of regional primary routes for local traffic • Detour Benefits • Safety increased by separating motorists from construction operations • Construction operations streamlined with closure; allowed pavement of full width PCC up to one mile per day (weather permitting) • Estimated $34.6 million in savings compared to traditional construction staging over multiple years

  40. Keys to Success • Affected businesses, elected officials, and state trucking association contacted months prior to closure • Brochures and maps were distributed at local Rest Areas and project website was established with detour information • Contractor was required to hold Public Information Meeting prior to closure • Pre-construction and mid-construction partnering meetings • Contract had $25,000 daily incentives not to exceed $750,000 and $50,000 daily liquidated damages with no cap beginning August 16, 2010

  41. Construction Related Keys to Success • Bridge jackings were let in separate contract and completed prior to I-385 northbound closure • Project let five months in advance of closure date for prep work and material fabrication (fly-over bridge superstructure) • All excavation was converted to Site Excavation • Concrete paving machine guided by laser total station with an automatic dowel inserter • Leica Scan Station 2 survey scanner used to verify cross-slope correction

  42. I-385 Southbound Mainline Paving Operations

  43. Concrete Paving Machine

  44. Total Station Prism for Paving Machine Guidance

  45. Concrete Finishing

  46. Roller Compacted Shoulder Paving

  47. Fly-Over Bridge Replacement

More Related