An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. From PFI to LED Peter Simpson - HCC Senior Asset Manager and Team Leader

  2. Hertfordshire - The Strategic Story: 2010 - 2017 Street Lighting: • 110,000 lighting columns, 115,000 luminaires • Majority of columns in excess of 30 years old • High Density, Low pressure sodium lighting 2010/11: • £174m PFI credits secured, Government’s Public Spending Review, PFI withdrawn • Austerity agenda, Reducing Revenue Budgets, Increasing Energy Costs: Challenge • Review of Street Lighting Service: Opportunity: Develop a Sustainable Street Lighting Strategy based on Affordable, Safe & Operational principles. A two-stage approach

  3. Hertfordshire - The Strategic Story: 2010 - 2017 2011/12: • Street Lighting Strategies endorsed: Part Night Lighting (PNL), Safe & Operational (Point for Point, Like for Like Replacement) • PNL: 80,300 units delivered on time, within £3.5m budget, saving £1.3m p.a. (£1m in energy), no adverse impact on road safety or crime and reduced ‘sky glow’ • Highway Services Term Contract (HST) started 1st October 2012 (includes Refurbishment) 2013/14: • Development and approval of HCC Capital Invest to Save Initiatives • CMS & LED Technology becoming more robust, reliable and affordable • Asset Management Approach: Data driven, condition led (rather than age). Testing circa 85,000 units, replaced 13,000 columns (rather than 70,000 under PFI model). Making the best use of existing infrastructure where Structurally & Electrically sound 2014/15: • CMS & LED including Variable Lighting Strategy, Ad-hoc replacements, New Works and New Developments endorsed • CMS & LED Phase 1 : A - Roads, 12,600 units, delivered on time, within £6.5m budget, saving £0.66m p.a.

  4. Hertfordshire’s Approach to CMS & LED: 2014 - 2020 2015/16: • CMS & LED Phase 2 : B, C & U - Roads and Footways in Full Night Lighting (FNL), 21,400 units, delivered over 2 financial years on time, within £7.5m budget, saving £0.77m p.a. • Phase 1 and Phase 2 Pilot Projects endorsed - PNL, Dimming and Trimming 2016/17: • CMS & LED Phase 3 (Integrated within Phase 2) : Remote Footpaths and Outlying Settlements in PNL, 8,700 units, delivered on time, within £3.5m budget, saving £0.18m p.a. 2017/18: • CMS & LED Phase 4 : Remainder (B, C & U - Roads and Footways) in PNL, 70,000 units, cost £18.5m over three financial years, started April 2017, estimated saving £1.86m p.a., plus conversion of Belisha Beacons, cost £84k over 2017/18, estimated saving £31k p.a. • To date circa 50,000 units have been converted to CMS & LED (including circa 3,000 ad-hoc replacements, following column knockdowns), reducing carbon emissions (CO2) by circa 5,800 t p.a. • Value for Money: Total investment: £39.5m (22% of PFI model), total savings (energy, maintenance and carbon tax) circa £4.8m p.a., CO2 circa 12,600 t p.a.

  5. CMS & LED Project Planning, Implementation and Technical Aspects • Governance: Highways Cabinet Panel, Highways Electrical Board and Project Team • Sustainable Procurement: HST Contract: Ringway, CMS: Telensa, LED: Urbis. Procurement model tests the market. • CMS: 48 Base stations (Phase 1) - low power radio network across Hertfordshire, One Tele cell Node per LED unit, Remote management, control and detection of faults • LED: ‘Soft’ White Light. Operation: Dimmed by 25%, 11pm - 6am • Structural & Electrical Integrity: Testing, surveys, Brackets and Post Top, Audit Process: 10% ‘on-site’ checking • Design: ‘Safe & Operational’ philosophy: Point for Point, Like for Like Replacement, Light Distribution & Uniformity on the ground - ‘no worse than existing’ • Innovation & Sustainability: Installing new technology on structurally sound existing infrastructure. Reduced wastage and maintenance visits whilst maximising recycling

  6. CMS & LED Project Planning, Implementation and Technical Aspects • Warranties - comprehensive on products, catastrophic failure, legal involvement • Recovery of Energy Savings and Load Profile - liaison with meter administrator and energy provider • Telensa/Confirm Integration - development of interface, automatic fault generation and improving the customer journey • Continuous engagement with supply chain and Industry. All phases have run contiguously and forward plan & programme have been shared. • Holistic management of the project and routine maintenance has enabled the refurbishment / recycling of sodium lanterns (and management of their obsolescence) pending conversion in later phases • Pilot Projects - Part Night Lighting and Dimming & Trimming On site Interactive Trials undertaken. Monitoring for 12 months • Political engagement & endorsement is essential

  7. Hertfordshire - Lessons Learned • Environmental benefits: Duty - Wildlife & Countryside Act 1981: Bats - Protected Species. Proactive engagement with Hertfordshire & Middlesex Bat Group • Contributed to study, trials & monitoring on how LED affects the local Bat population by Bristol University. Paper published: Outcome: LED does not affect Bat activity at street lights. • Assessments: Equality Impact, Environmental Impact, Public Health, Sustainability • Benchmarking: Visit other Local Authorities • Sell benefits: Energy & Maintenance savings, Cost Avoided, Reduction in Energy demand, Carbon Reduction, Improve Visibility, Reduction in Light Pollution • Regular Lessons Learned with Supply Chain (including HST Maintenance) - ‘One Team’, Joined Up

  8. Hertfordshire - Lessons Learned • Positive Impact on Asset Inventory and Grass Cutting (night time) • Forward visibility of Programme - Logistics and Production e.g. Factory Fitted Nodes on LED’s • Light Distribution: Segregated Footways / Cycleways and Internal Shields on LED’s • Remote Footpaths - Podium Steps • GIS Mapping and Data Capture, Work Scheduling, E-Coding, Test Certificates • Sharing Knowledge of the Network - Accessibility, Availability, Group Switching • Robust Consultation and Proactive Communications: Stakeholders (including emergency services), District and Parish Councils, Public and Local HCC Members. • Shared Hertfordshire’s approach and lessons learned: Regional (ADEPT), National (HEA) and International (Portugal and Singapore)

  9. CIHT Sustainability Award 2017 Winner From PFI to LED

  10. Hertfordshire: The Future - Positive Evolution • Wider Implementation Potential: Pushing the boundaries - further dimming & trimming. New Code of Practice - Risk based approach, Dynamic Dimming, Smart Sensors • CMS & LED Phase 5 : 114High Masts, 19,981 Signs (includingIlluminated Bollards) and 4,142 Subway lights, estimated cost circa £1m over 3 financial years, starting April 2018, subject to funding • DfT (HMEP) & DECC - Toolkits: Effective use of Asset Condition data. Extensive testing regime has provided the foundation for a robust six-year testing strategy. Updating & Maintaining inventory is KEY • CMS, ITCC & ‘Smart Cities / Counties / Living’: Future Opportunities, Evolution of Transport and Future Highways - Internet of Things, Connectivity, Connected Automated Vehicles, Mobility as a Service

  11. A414 St Albans A505 North Herts The Future is Bright The Future is White (and not Orange!)