Update on Lafayette Terminal Program Progress as of March 13, 2019
The Lafayette Terminal Program is advancing with multiple updates. Coordination with FP&C has confirmed the bid process and eligible items for terminal contributions. A $7 million capital outlay application for terminal construction is submitted, with an EDA grant application awaiting feedback. Significant demolition and enabling work, including fencing and material fill, are completed. Rental car agreements are moving forward, and ongoing projects include foundational work and parking lot enhancements, with timelines established for upcoming milestones.
Update on Lafayette Terminal Program Progress as of March 13, 2019
E N D
Presentation Transcript
Lafayette New Terminal Program Update March 13, 2019
LA FP&C • Coordinating with FP&C to confirm bid process and eligible items for terminal contribution • 2019 Capital Outlay Application submitted • Applying for $7 million towards terminal construction to be available next Fall EDA Grant Application • Revised EDA grant application submitted and received decision that the application meets further consideration TSA OTA Application • Submitted Grant Application, waiting on feedback Terminal Program Update
Airlines • Working with Airlines to discuss leasable space and an agreement to buildout space in New Terminal QTA \ Ready Return • Continued to meet with Rental Car Companies, moving forward on QTA Lease Rates • Rental cars agreement to move to Short Term Lot - completed Concessions Terminal Program Update
Enabling Demo • Demolition - Complete • AOA fencing and gates – Complete • Fill Material and Asphalt – Complete • Seeding/Sod – Complete • Substantially Complete • Reviewing completion paperwork and waiting on 45-day lien-free period • Final Acceptance - upcoming Terminal Program Update
Rental Car Quick Turn Around Facility Timeline: • Oct. 2018: Commission Approved Updated CFC • Nov. 2018: Construction Bids Due • Dec. 2018: Approved Bids • Jan. 2019: FP&C Construction Concurrence • Feb. 2019: Award Contract • Preconstruction meeting completed 2/20/19 • Apr. 2019: NTP • Feb. 2020: Construction Complete Terminal Program Update
GMP 1: Approved 9/25/18, Notice to Proceed 11/12/18 Terminal Program Update GMP 2: Approved 1/15/19, Notice to Proceed 1/15/19 GMP 3: Terminal Building Shell, MEP and Finishes 100% Design to complete in Feb. 2019 – Presentation in April Bidding in Mar. 2019 Approval by LAC May 2019
New Terminal Construction Update Project 1 – RTR Cable Relocation • Cable wire pulled, spliced, and FAA cutover complete • Manholes 1 through 4 set and backfilled, asphalt placement upcoming GMP1 – Project 1
New Terminal Construction Update Project 2 – RTR Facility • Duct banks for the RTR cable from the building to tower – complete • Building walls and roof trusses– complete GMP 1 – Project 2 RTR Facility
New Terminal Construction Update Project 2 – RTR Facility • RTR tower foundations – ongoing • Facility ice and water shield – ongoing GMP 1 – Project 2 RTR Facility
New Terminal Construction Update Project 3 – Terminal Foundations • Test Pile Program – installed and testing • Milling and fence moving – ongoing GMP 1 – Project 3 Terminal Foundations
New Terminal Construction Update Project 5 – Enabling Parking • Economy lot – site grading and compaction – ongoing • Short-term parking lot re-striping – completed • Substantial completion for short term parking lot (Phase 3B) GMP 1 – Project 5 Enabling Parking