1 / 17

REAL TIME DIGITAL SIMULATION

REAL TIME DIGITAL SIMULATION. GOOSE and SV with RTDS. GOOSE and SV with RTDS. Presentation Outline: Introduction to RTDS Network Interface Card GTNET-GSE GTNET-SV IEC 61850 applications in RTDS Question and Answer. RTDS Technologies Inc. Background and History:

Télécharger la présentation

REAL TIME DIGITAL SIMULATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. REAL TIME DIGITAL SIMULATION GOOSE and SV with RTDS

  2. GOOSE and SV with RTDS Presentation Outline: • Introduction to RTDS • Network Interface Card • GTNET-GSE • GTNET-SV • IEC 61850 applications in RTDS • Question and Answer The World Standard for Real Time Digital Power System Simulation

  3. RTDS Technologies Inc. Background and History: • Technical Advisory Board (sponsors) • RTDS Development Project initiated in 1986 • Major Funding from Manitoba Hydro • World’s 1st real time HVDC simulation was achieved in 1989 • Continued development and refinement to produce a commercial product • 1st commercial installation in 1993 • RTDS Technologies created in 1994 The World Standard for Real Time Digital Power System Simulation

  4. RTDS Simulation Hardware RTDS Hardware • Custom parallel processing computer • Modular hardware design • A unit of hardware is called a ‘Rack’ and typicallyincludes: • 2~6 RISC PB5 Processor Cards • 1 Giga Transceiver Workstation InterFace Card (GTWIF) • Main interface with the hardware is through user-friendly software • Ample, convenient input and output allowing connection of physical devices The World Standard for Real Time Digital Power System Simulation

  5. RTDS Simulation Software RSCAD • Includes everything required for simulation studies • No additional add-on modules required for any aspects of simulation • No 3rd party modules • Site license and one maintenance agreement The World Standard for Real Time Digital Power System Simulation

  6. GTNET GTNET Card • Network Interface Card • Used to interface a number of different network protocols with RTDS simulator • Currently supports • GSE – IEC 61850 GOOSE/GSSE • SV – IEC 61850 9-2LE (Sampled Measured Values) • PMU – IEEE C37.118 data stream output • DNP3 – Distributed Network Protocol • IEC 60870-5-104 (104) • PLAYBACK – Playback of large data sets The World Standard for Real Time Digital Power System Simulation

  7. GTNET-SV GTNET Component Library GTNET-SV • Simulates IEC 61850 9-2 LE compliant Merging Unit • Two models with different capabilities available in the library • GTNET_SV9-2_v5.def • GTNET_SV-SE2.def The World Standard for Real Time Digital Power System Simulation

  8. GTNET-SV GTNET Component Library GTNET_SV9-2_v5 • Compliant with IEC 61850 9-2LE • Provides IEC 61850 9-2 Sampled Measured Values communication using GTNET hardware • Can be configured to publish up to 2 data streams • According to 9-2LE, one data stream shall contain 4 currents and 4 voltages • Sample rate at either 80 or 256 samples per cycle • 256 samples per cycle applies to one output data stream only The World Standard for Real Time Digital Power System Simulation

  9. GTNET-SV • GTNET Component Library GTNET_SV9-2_v5 – Non-9.2LE mode • based on IEC 61869-9 and the Chinese National Standard for SV merging units • Able to publish one datastream for up to 24 channels of voltages or currents • The time delay channel can be configured to the first channel as required in a Chinese merging unit SV datastream • Currently supports data rate of 80 samples/cycle • Able to achieve the requirement of 10 usec of jitter between samples The World Standard for Real Time Digital Power System Simulation

  10. GTNET-SV • GTNET Component Library GTNET_SV9-2_v5 – Input Mode • Can be configured to subscribe 1 data stream from 1 MU at 80 or 256 samples per cycle • GTSYNC is needed for use of the GTNET_SV9-2_v5 component The World Standard for Real Time Digital Power System Simulation

  11. GTNET-SV • GTNET Component Library GTNET_SV-SE2 • Developed to have customized functions for Alstom Grid (UK) • Only supports 1 SV output data stream at 80 samples per cycle • Change chronological order of Samples (packets) • Packet delay • Packet loss • Jitter algorithm • Provides more flexibility for testing MUs The World Standard for Real Time Digital Power System Simulation

  12. GTNET-GSE • GTNET Component Library GTNET_GSE • GTNET_GSE_v5.def • Provides IEC 61850 GOOSE communications • Supports up to 4 TX/RX modules, which can be arranged to simulate 1-4 IEDs (i.e. 1 IED with 4 modules, 4 IEDs each with 1 module…) • Each module can publish up to 64 points (stVal) (Boolean, or INT32, or FLOAT32, or Dbpos), or 32 points with Quality • Each module can subscribe up to 32 points (16 Booleans) with Quality • Can subscribe GOOSE message from up to 16 unique external IEDs The World Standard for Real Time Digital Power System Simulation

  13. GTNET-GSE • GTNET_GSE SCD Editor • A software tool to generate the required configuration file • The configuration file defines the capabilities of the interconnected devices • Provides a mechanism for the user to create and edit a Substation Configuration Description (SCD) file • Includes an interface for mapping the external references to the GTNET inputs • Loads existing SCD files to import ICD/CID files • Exports GTNET ICD file The World Standard for Real Time Digital Power System Simulation

  14. GTNET-GSE GTNET_GSE SCD Editor The World Standard for Real Time Digital Power System Simulation

  15. GTNET IEC 61850 Test GTNET Card Testing • IEC 61850 Closed-loop relay testing • The interested power system is simulated in RTDS • Bus voltages and breaker currents at certain location are sent to the external physical IEDs (IEC 61850 9-2LE or 61869-9 compatible) through SV messages • Breaker status and tripping/reclosing signals are exchanged through GOOSE messages The World Standard for Real Time Digital Power System Simulation

  16. GTNET IEC 61850 Test Testing IEC 61850 Closed-Loop Relay Testing Demonstration The World Standard for Real Time Digital Power System Simulation

  17. Question & Answer The World Standard for Real Time Digital Power System Simulation ?

More Related