1 / 6

WLCG Remarks

WLCG Remarks. Review of Computing Needs 6 th July 2009. Roadmap 2009/2010. Resource concerns: CNAF – not a big concern ASGC – expect full resources available on schedule NL-T1 – biggest concern – huge amount of resources to commission once new CC available. Current Pledge status.

megara
Télécharger la présentation

WLCG Remarks

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WLCG Remarks Review of Computing Needs 6th July 2009

  2. Roadmap 2009/2010

  3. Resource concerns: • CNAF – not a big concern • ASGC – expect full resources available on schedule • NL-T1 – biggest concern – huge amount of resources to commission once new CC available Current Pledge status

  4. Status • 2009: • In most cases full 2009 pledges for CPU, Disk are already available; tape somewhat less (but OK as short lead-time for media) • Exceptions: NL-T1 significant and serious delays; ASGC delayed by fire but anticipate procurements; CNAF delayed 2009 but will have early 2010 • No point discussing 2009 any further – it is already done • 2010: • In many cases procurements are pending funding agency decisions / pending the outcome of this process today • Procurements are long processes – even if we agree today we must anticipate >>6 months to have resources usable • Some exceptions e.g. US where lead-times are less

  5. Total • Many problems to ramp up resources • Delays in procurements • Faulty equipment • Lack of power & planning ASGC NL-T1 NL-T1 CNAF BNL

  6. Key points • LHCC mini-review (Feb): • “Must ensure that computing is not a limiting factor when data comes” • We must plan the ramp-up of resources carefully – they now have to be commissioned during data taking • Have not had a good experience at this scale in last few years • Many comments made about the less than full utilisation of existing resources: • Remember: we always had the ramp up planned over several years – not feasible any other way • We knew that they would not be fully utilised before the LHC started • We now have significant experience with the computing models (CCRC’08, cosmics, STEP’09, simulation/production work) – today’s models take all that experience into account • Will not be able to estimate future needs any better than today until we have ~6 months real data experience • Effect of further schedule slip: • Minimal on 2010 resources unless many months slip – but we need to act now anyway based on today’s understanding of LHC schedule • Significant slippage could have implications for 2011 • Must conclude today! • Procurement lead times such that will not be able to provide additional resources in time (it’s already very late) • Clear message must be sent to RRB/funding agencies

More Related