QUIMICA. CEPSA QUIMICA PALOS DE LA FRONTERA IPPC DEVELOPMENT. Palos de la Frontera Jul 12 th , 2012. IPPC DEVELOPMENT: KEY DATES. Quality, Safety and Environment Certifications. QUALITY. ISO 9001. 1992. ISO 14001. ENVIRONMENT. 1999. 2010. ENVIRONMENT. EMAS. OHSAS 18001. 2004.

meris
Télécharger la présentation

QUIMICA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. QUIMICA CEPSA QUIMICA PALOS DE LA FRONTERA IPPC DEVELOPMENT Palos de la Frontera Jul 12th, 2012

  2. IPPC DEVELOPMENT: KEY DATES

  3. Quality, Safety and Environment Certifications QUALITY ISO 9001 1992 ISO 14001 ENVIRONMENT 1999 2010 ENVIRONMENT EMAS OHSAS 18001 2004 RISKS PREVENTION 1993 RESPONSIBLE CARE SUSTAINABILITY SUSTAINABILITY DOÑANA 21 2007 At start of IPPC legislation CEPSA Química had established operational procedures to control and minimize pollution

  4. IPPC DEVELOPMENT • What’s needed to obtain IPPC permit?: • BREF Documents relevant to petrochemical industry: • “Large Volume Organic Chemical Industry”, 2003/02. • “Cooling Systems”, 2001/12. • “Common Waste Water and Waste Gas Treatment and Management Systems in the Chemical Sector”, 2003/02. • “Emission from storage of bulk or dangerous materials”, 2003/07. • “Monitoring Systems”, 2003/07. • “Large Combustion Plants”, 2003/03 • Did not exist specific BREF of phenol production (today: first draft in study). • Methylamine: BREF LVOC summary of system established in CEPSA Química: BAT. • PHENOL/ACETONE: Process via cumene oxidation formed by alkylation: BAT QUIMICA

  5. IPPC DEVELOPMENT: requirements • Control of Air Pollution Emissions Fuel: Priority utilization of natural gas. Minimization of Fuel-oil (Voluntary objective) QUIMICA 2004: Only one furnace used FO and NG simultaneously: B-401. New plant that started at 2007: furnace designed only for natural gas. 2008: stopped use of FO. 2009: New furnace B-401N to substitute old B-401. New furnaces: Low NOx burners. B-401 NOx emissions below limits. High reductionin SOx and Noxemissios

  6. IPPC DEVELOPMENT: requirements

  7. IPPC DEVELOPMENT: requirements • Control of Air Pollution Emissions • Continuous emissions Monitoring system for furnaces > 50 Mw: • (B-401/ B-401N) and cogeneration plant. • Adaptation of platform and ladder in furnace B-401’s stack for air emission measurements. • Design of stacks to optimize dispersion of pollutant. QUIMICA

  8. IPPC DEVELOPMENT: requirements • Control of Air Pollution Emissions • Minimization of Volatile Organic Compound emissions (VOC’s) (Voluntary objective) QUIMICA Optimization of activated charcoal chambers system to reduce VOC in air from oxidation reactors. New vents absorber of Methylamine plant. Reduction of atmospheric vents from trucks and drums loading. Change of open samplings systems to closed-loops. Pump Seals: Substitution of water systems to gas closed circuits. Establishment of a Leak Detection and repair (LDAR) program.

  9. IPPC DEVELOPMENT: requirements Control of Air Pollution Emissions CEPSA Químicahas a Cogeneration plant that has an independent IPPC Permit. Reduction of limit to NOx: 500 to 75 mg/Nm3. Change to a gas generator with Dry Low Emissions technology . Investment 8 MM €. QUIMICA

  10. IPPC DEVELOPMENT: requirements • Control of Waste Water Emissions Process water waste is sent to a primary treatment and then goes to the treatment plant where the contaminants are eliminated through a biological cleaning process: Emission point #1 IPPC permit established authorized waste water limits and how they must be controlled. CQ have made Investments to optimize effluent plant in order to improve the quality of the waste water even better than limits: Design and implementation of new system of waste water treatment from new plant that started operation at 2007. Optimization of control elements to lower contamination of waste water. New filtersystemforsludgeexcess QUIMICA

  11. IPPC DEVELOPMENT: requirements • Control of Waste Water Emissions The rainfall water has an independent circuit: Emission point #2 IPPC permit established that water could only be sent at this emission point when it's raining and must be free of contaminants. CEPSA Química had made Investments to take residual water out of rainfall circuit. Implementation of Continuous Flow equipment that allows us to control that rainfall circuit only operates when it’s raining. QUIMICA

  12. IPPC DEVELOPMENT: requirements • Control of Wastes IPPC permit established authorized Hazardous waste and regulations about its management. CQ has established techniques and operational controls to minimize wastes. New temporary warehouses has been built to gather the residues. Selective gathering of residues has been improved. QUIMICA

  13. IPPC DEVELOPMENT: requirements • Control of soil and groundwater CQ has established techniques and operational controls to avoid this contamination. Special attention to storage: leak proofing of storage tanks, built over pedestal with leaks detectors, bunds,…. . Protection of land of Operational areas by use of waterproof concrete. QUIMICA

  14. IPPC DEVELOPMENT: requirements • Other requirements stipulated in the permit Internal and external measurements, control and report of air emissions, waste water, wastes…(many of these are indicated on environmental legislation). Audits of compliance of requirements from IPPC permit by administration (each 2 years, measurements including). Establish obligation of Communication: environmental incidents/accidents, changes in process, productive stops…. Realization of annual report of “European Regulation on Pollutant Release and Transfer Registers (E-PRTR)”. QUIMICA

  15. Environment-related operational costs and investments (MM €) Not including technical changes operational and security that have relation with environment. Not including Cogeneration Plant.

  16. Consumption of water, calorific energy, electricity

  17. IPPC DEVELOPMENT: requirements • And now? Validity period of permit is 8 years (will expire in 2013): The documentation for renewal was presented in May, 2012 Requirements of new BREF and new legislation will be included (for example Industrial Emissions Directive) Will establish new BAT and emission levels associated (BAT-AELs): new investments. Will include references to raw materials and energy consumption. QUIMICA