1 / 23

Steering Committee Meeting Sunflower Project Statewide Financial Management System Update

Steering Committee Meeting Sunflower Project Statewide Financial Management System Update. September 11, 2009. Today’s Topics. Project status and activities – Kent IV&V Report – Peggy Change control – Peggy Agency Interactions, Timelines & Upcoming Events – Gary

meris
Télécharger la présentation

Steering Committee Meeting Sunflower Project Statewide Financial Management System Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Steering Committee MeetingSunflower ProjectStatewide Financial Management System Update September 11, 2009

  2. Today’s Topics • Project status and activities – Kent • IV&V Report – Peggy • Change control – Peggy • Agency Interactions, Timelines & Upcoming Events – Gary • Agency Reporting Strategy and Approach – Gary • Measuring Progress – Gary • Remaining Issues and Challenges – Gary

  3. Project Timeline Build Phase Test Phase August September October November December January February March Interface Testing Begin System Testing Begin User Acceptance Testing Agency Role Mapping Configure System, Develop Mods Develop Reports, Build and Test Interfaces, Run Data Conversions Business Process Workshops

  4. Project Status & Activities – Finance Team • Completing: • defining and loading configuration values • change requests for remaining software mods • data conversion templates • security role definitions • functional designs for modifications • Continuing: • functional designs for reports • formulating preliminary cutover plan • support for training development and BPWs

  5. Project Status & Activities – Enterprise Readiness Team • Completed demos to facilitate agency decisions on de-commissioning systems (KDOR, SRS, KWP, Aging) • Monitoring progress of agencies and completion of assignments • Five agencies are of concern; meeting with agencies’ leadership to resolve • Conducted 12 of 18 business process workshops with agencies • Developing training materials • Continuing to recruit trainers, facilitators and facilities • Evaluating help desk software and developing support processes

  6. Project Status & Activities – Tech Team • Developing technical designs and coding mods • Developing remaining interfaces (mostly internal) • Developing technical designs and coding reports • Building and maintaining environments • Implementing data warehouse including security based on requirements provided by functional team and agencies • Beginning work on disaster recovery plan – will be working closely with DISC and A&R

  7. Project Status & Activities – Central Systems • A&R/DISC performing modifications to SHARP including data conversion – saving State approximately $200K • Working with IBARS vendor to design modifications to support new chart of accounts • Developing options for SHARP performance testing

  8. Project Status & Activities – Miscellaneous • Monthly forums to address issues and communicate with agencies for interfaces and conversions • Continuing to review project plans to assess agencies’ progress and communicate early identification of problems • Provided three briefings to DoA personnel • Finalizing logistics with Washburn for remedial accounting course for agency personnel • Determining the funding mechanism to support the services provided by the Service Center • State “all hands” meeting held on August 28th

  9. IV&V Review, Findings and Recommendations • 3rd scheduled IV&V project review (Sys Test Labs – Denver) • One week prep, one week on-site, one week to draft report • Interviewed 32 project and non-project personnel • Reviewed 35 documents (deliverables, risk log, issue log, project plan, status reports, requirements matrix, test scripts, etc.) • Overall project health rated as “very good” • Several recommendations provided: • Finalize status of remaining requirements prior to testing (7 out of 3,056 need to be to be approved and 72 out of 3,056 waiting approval) • Need to freeze agency-specific requirements • Improve configuration management plan for code migrations

  10. Change Control Change orders approved since last Steering Committee meeting No change requests over $50K since last meeting Credits of $124K for change orders since last meeting

  11. Change Control – Remaining Balance • Balance of hours for customizations (including all customizations discussed today) • Total Accenture hrs used = 16,407 (15,806 July) • Total available contract hrs = 19,130 • % Used = 86% (83% last month) • % Remaining = 14% (2,723 hours)

  12. Change Control – Remaining CRs • CRReq’dEstimated Cost • Interfund Process – creating groups for notifications Yes < $30K • Travel and Expense – payment method Yes $10K • Travel and Expense - decentralizing • Travel and Expense set up for traveler and approval Yes $40K • Data Warehouse • SHARP HR/Payroll data Yes TBD • Financial data Yes TBD • Note: May need additional CRs to address new or previously unidentified requirements that don’t surface until testing

  13. Agency Interactions • Meetings held with agencies: • Health Policy Authority • Department of Revenue • State Treasurer • KU and KUMC (separately) • Regents (collectively) • SRS & State Hospitals • Wildlife and Parks • Corrections • KPERS • and many others

  14. Conversion and Interface Timelines 2009 Agency Interface/System Modifications Connectivity Testing Interface Testing Cycles Conversion Build and Unit Test Extract Conversion Data Conversion Assembly Test Mock 1 Conversion Test Conversion Data Cleansing

  15. Upcoming Events September Monthly Conversion Technical Meeting Business Process Workshops Change Agent Network Meeting #5 – 09/30 Data Warehouse Advisory Group – 09/26 October Monthly Interface Technical Meeting

  16. Agency Reporting Strategy & Approach • Objective: Identify and resolve critical agency reporting gaps • Background • Over 150 reports will be available for agency use at go-live • However, some agencies may have reports or data feeds that will not be fully replaced by the new reports • Developed an approach to address and resolve go-live agency reporting gaps • Piloting this approach with several large agencies (SRS, KDOR, DOL) prior to rolling out Statewide

  17. Agency Reporting Strategy & Approach • Step 1 – Agencies list reports that are critical to perform the agency’s Day 1, go-live business processes • Step 2 – Agencies compare reports identified in Step 1 with list of reports available in SMART and identify reporting gaps • Step 3 – Sunflower Project Team reviews agencies’ high priority reporting gaps to determine if: • A delivered report meets the reporting need • If a report can be built by the agency in the data warehouse • If a report is not available in the data warehouse and will need to be developed by the Project Team • Team will document their determination for each reporting gap and return the information to the agency • Note: Medium and low priority reporting gaps will be addressed after go-live using a process to be determined

  18. Agency Reporting Strategy & Approach • If a report can be built by the agency in the data warehouse: • Agency identifies at least one agency person to build and test these reports prior to go-live • Agency report developer attends mandatory training on the data warehouse and the reporting tool • Agency report developer will have access to a report development lab to create and test their reports • Agency must have sufficient data in the system to develop their reports (interface testing, conversion, on-line entry) • Agency develops lower priority reports after go-live

  19. Measuring Progress Tech Team (Accenture and State) are working OT No impact on key milestones or the “go-live” date

  20. Remaining Issues and Challenges • Technical resources barely adequate to complete remaining development work in scheduled timeframe • Accenture brining on additional technical resources • State re-assigning team member from coordinator role to developer role • Making minor changes to testing schedule to accommodate late mods • Finance Team continues to be stretched and will remain very busy for next 6-8 months • In general, most agencies continue to be good partners – complete assignments, provide feedback and attend meetings and workshops • Small number of agencies consume inordinate amount of time • Review status reports each month and follow-up on issues • Large interfacing agencies (KDOT, SRS, KDOR and KHPA) are making good progress on system modifications and interface development • Approximately 50% of agencies are behind schedule in asset conversions • Continue to retain 2 months of schedule contingency for disaster recovery testing and operational readiness testing

  21. Recently Resolved Issues and Challenges • Data warehouse team lacked project management, technical resources and functional support • Corrective actions taken over past two months: • Replaced key consultant • Brought in a senior manager and developed detailed project plan • Reviewed resource requirements • Adding additional data modeler and Business Intelligence consultant • State coordinating scope definition and security requirements

  22. Questions and Answers For additional information on the project, please see the project website: http://da.ks.gov/smart ?

  23. Authority for Change Requests

More Related