1 / 47

WMATA IFB-FQ15233 NEPP Electrical and Data Cabling Installation

Invitation for Bid for electrical and data cabling installation project by Washington Metropolitan Area Transit Authority. Pre-bid conference and bidding information provided.

midgette
Télécharger la présentation

WMATA IFB-FQ15233 NEPP Electrical and Data Cabling Installation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation Pre-Bid Conference IFB FQ15233 NEPP Electrical and Data Cabling Installation Invitation For Bid (IFB)/Contract Number – FQ15233 September 3, 2015 10:00am-12:00pm EST 955 L’Enfant Plaza – Room 5300

  2. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation Opening Remarks • Silence all Cell phones and pagers • No Recording • This presentation and attendee list will be provided on WMATA.com website • Safety Tip: “Safety Harnesses – Tie or Die; Take the right precautions to prevent falls”

  3. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation Introduction of WMATA Personnel • Errol Roper, Contract Administrator, PRMT • Michael Glimp, Contract Administrator, PRMT • Terri Anomnachi, Project Manager, NEPP • Jyotindra Shaw, Project Manager, IRPG • Khizgilov, Vadim, Construction Engineer. IRPG • Elena Almonte, Office Engineer, IRPG • Ernest Hunter, DBE Compliance Specialist, PRMT • Robin Hahn, Quality Assurance, QAAW • Jim Stewart/Carmen Pelham, RISK • Ernest Hunter, DBE Specialist, PRMT • John Cribben, SAFE

  4. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation PURPOSE • To promote a common understanding of: • IFB – NEPP Electrical and Data Cabling Installation • Authority’s requirements • Solicitation Instructions • To provide answers to questions regarding the IFB • Networking opportunity

  5. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation PURPOSE After today’s conference, if you have additional questions, they must be received via electronic mail by the Contracting Officer. Email your questions to: com-inbound-electrical-and-data-cable-installation@procoretech.comby Friday September 11, 2015, NLT 4:00pm.

  6. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation Disclaimer Regarding Changes to the Solicitation The Pre-Bid Conference is for information purposes only. It may answer some Offeror questions. Statements or representations made during the Conference are not legally binding. Changes resulting from this Conference or the site visits are official only if issued through an Amendment to the Invitation For Bid (IFB).

  7. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation All Contractors must register with WMATA at www.wmata.com “New Vendor Registration”. WMATA solicitations are publicized at www.wmata.com

  8. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation BIDDING MATERIAL • Bid Form • Bid Price Schedule • Bid Guarantee • Bid Data Form with Supporting Data • Representations and Certifications • List of DBE Certified Firms • DBE Data • One (1) hard copy AND One (1) electronic copy submitted on USB

  9. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation BIDDING MATERIAL The outside of the envelope shall show: - THE AMENDMENTS RECEIVED (lower left hand corner). Failure to acknowledge all amendments may cause the Bid to be considered not responsive. - HOUR and DATE specified in the IFB for receipt, the IFB number, and the full legal name and address of the Bidder on the face of the envelope

  10. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation BIDDING MATERIAL Proposals may be received prior to, but no later than 2:00 PM, September 16, 2015 BASIS FOR AWARD: The Authority will award a contract to the lowest responsive and responsible bidder whose bid conforms to this Invitation for Bids.

  11. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation AWARD Apparent Low Bidder submits Pre-Award Information within 5 days after Bid Opening WMATA will have 120 calendar days to award the Contract

  12. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation SCHEDULE EVENTDATE IFB ReleaseAugust 17, 2015 Pre-Bid Conference September 3, 2015 Deadline for Proposer Questions September 11, 2015 Bid Opening September 16, 2015 Award Date (estimated) October 15, 2015 Notice to Proceed (NTP) (estimated) November 5, 2015 Dates Subject to Change

  13. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation DBE Compliance, Appendix “B”

  14. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation Disadvantaged Business Enterprises Disadvantaged Business Enterprise (DBE) 20%. $500,000 or more for a construction contract. Submit complete schedule of DBE participation and Letters of Intent. All DBEs must have current WMATA DBE certifications. It is the policy of WMATA, the Federal Transit Administration (FTA) and the U.S. Department of Transportation (US DOT) that Disadvantaged Business Enterprises (DBE’s) shall have an equal opportunity to receive and participate in performing federally -assisted contracts, including contractors and subcontractors at any tier.

  15. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation SUMMARY OF SUBMITTALS With the Bid/Proposal 1. Completed “Schedule of DBE Participation” (Attachment B-1) with current certification letters attached for each listed DBE. 2. Executed “Letters of Intent to Perform as a Subcontractor/Joint Venture” (Attachment B-2). 3. Justification for grant of relief (waiver of DBE goal), if applicable. Include completed “DBE Unavailability Certifications” (Attachment B-3) as appropriate.

  16. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation SUMMARY OF SUBMITTALS Bid and Proposal Requirements (Apparent Successful Bidder/Proposer) 1. All DBEs must submit a copy of their current WMATA or DC DOT certification letters or a certification letter issued by the MWUCP. 2. DBE Manufacturer’s Affidavit, if applicable, must be submitted in order to receive 100 percent of the allowable credit for expenditures to DBE manufacturers/suppliers (Attachment B-4). 3. Schedule B Information for Determining Joint Venture Eligibility, if applicable (Attachment B-5, pgs. 1, 2, 3, 4). 4. Copy of Joint Venture Agreement, if applicable. 5. Certification letter of the DBE regular dealer/supplier, if applicable.

  17. Washington Metropolitan Area Transit Authority IFB-FQ15233 NEPP Electrical and Data Cabling Installation SUMMARY OF SUBMITTALS After Contract Award 1. “Prompt Payment Report-Prime Contractor’s Report” Attachment B-6) – submitted monthly. 2. “Prompt Payment Report-Subcontractor’s Report” (Attachment B-7) – submitted monthly. 3. Request to substitute DBE contractor (see paragraph 8.C.) – submitted as required. 4. Copies of subcontracts-submitted at the time of their execution.

  18. Washington Metropolitan Area Transit AuthorityIFB-FQ15233NEPP Electrical and Data Cabling Installation TECHNICAL SPECIFICATIONS & PROJECT OVERVIEW

  19. Agenda • Background • High Level Scope • Technical • Project Management • Scheduling / Coordination • Special Conditions • Summary of Work Matrix • Existing Mezzanine Inspection Report (MIR) • Site Visits

  20. Background (1) • New power circuits to Kiosk • New Ethernet cable to faregate array • Addressing cable infrastructure • Completed inspection tasks • video scoping • pull-string installation • poor duct and new raceway identification

  21. Background (2) • Work Locations- 34 Metrorail Red Line Stations

  22. High Level Scope • Installation of Under-Floor Duct • Installation of Exposed Conduit • Installation of Faregate Array Under-Floor Duct • CAT6 Installation and Termination • Installation and Termination of Electrical Circuit • Installation of Fire Alarm System Cable

  23. Installation of Under-Floor Duct • Typical Mezzanine Duct Layout

  24. Exposed Conduit Installation (1) • In public and secure areas • One inch GRS conduit

  25. Exposed Conduit Installation (2) • Existing to new conduit transition

  26. Installation of Faregate Array Under-Floor Duct

  27. Temporary Trench Cover of U/F Duct

  28. CAT6 Installation and Termination (I)

  29. CAT6 Installation and Termination (II)

  30. Installation and Termination of Electrical Circuit

  31. Kiosk- Previous Design

  32. Kiosk- Present Design

  33. Installation of Fire Alarm Cable • Will be installed from the mezzanine Kiosk to the end-of-array faregate cabinet • At the Kiosk-end the cable will land in the secured AFC cabinet • Leave ample cable slack as lengths indicate in the pricing sheets • Cable compliant with NEC 760

  34. Project Management • Project Specific Quality Management Plan (PSQMP) • Design Control Plan and Quality Plan shall be submitted for approval • Site Specific Safety Plan (SSWP) • Master schedule • 4 week schedule (weekly) • Weekly Quality Reports • Daily reports • Weekly meetings

  35. SITE ACCESS & POWER OUTAGE SUBMITTAL PROCESS Target Work Week SSWP Request (60 Days) Escort Request (Monday, Prior Target Week) GOTRS/SO Request (21 Days) Escort Approved (Thursday, Prior Target Week) SO Request Confirmation (Monday, Prior Target Week) SO Approved (Friday, Prior to Target Week)

  36. Site Access & Power Outage Submittal Process • Sample of Weekly Switch Order Request

  37. Special Condition- High Ceiling

  38. Special Condition- Confined Space • Under platform at track level is the typical location • Only a handful of locations require this level of safety • Tenleytown • Takoma • Judiciary Square West

  39. Special Condition- Battery & ELES Rooms

  40. Summary of Work Matrix

  41. MIR- Cleveland Park (1)

  42. MIR- Cleveland Park (2)

  43. MIR- Cleveland Park (3)

  44. MIR- Cleveland Park (4)

  45. MIR- Cleveland Park (5)

  46. Site Visit • Gallery Place – Verizon Center • Faregate U/F duct work • CAT6 cable terminations at both ends • Remote mezzanine (F/A cable) • Cleveland Park • Conduit installation • CAT6 cable installation • Battery room • Below floor cable trench (pull-through area)

  47. Washington Metropolitan Area Transit AuthorityIFB-FQ15233NEPP Electrical and Data Cabling Installation QUESTIONS?

More Related