1 / 29

The Replanting of Lochaber Hydro Power Station

The Replanting of Lochaber Hydro Power Station. by Andrew Thick. E V E N T S P O N S O R S. Topics to be covered today. Scheme modelling; Operating capability of Lochaber; Turbine Selection; Penstock works. Schematic of the Lochaber Scheme. Gravity Inflows. Surge Chamber.

milton
Télécharger la présentation

The Replanting of Lochaber Hydro Power Station

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Replanting of Lochaber Hydro Power Station by Andrew Thick

  2. E V E N T S P O N S O R S

  3. Topics to be covered today • Scheme modelling; • Operating capability of Lochaber; • Turbine Selection; • Penstock works.

  4. Schematic of the Lochaber Scheme Gravity Inflows Surge Chamber Gravity Inflows Spill Spill Spill tunnel tunnel Power-house tunnel Tailrace Penstocks Loch Laggan & reservoir Spey reservoir Loch Treig Loch Linnhe

  5. Schematic of the Lochaber Scheme Gravity Inflows Surge Chamber Gravity Inflows Spill Spill Spill tunnel tunnel Power-house tunnel Tailrace Penstocks Loch Laggan & reservoir Spey reservoir Loch Treig Loch Linnhe

  6. Schematic of the Lochaber Scheme Gravity Inflows Surge Chamber Gravity Inflows Spill Spill Spill tunnel tunnel Power-house tunnel Tailrace Penstocks Loch Laggan & reservoir Spey reservoir Loch Treig Loch Linnhe

  7. Schematic of the Lochaber Scheme Gravity Inflows Surge Chamber Gravity Inflows Spill Spill Spill tunnel tunnel Power-house tunnel Tailrace Penstocks Loch Laggan & reservoir Spey reservoir Loch Treig Loch Linnhe

  8. Schematic of the Lochaber Scheme Gravity Inflows Surge Chamber Gravity Inflows Spill Spill Spill tunnel tunnel Power-house tunnel Tailrace Penstocks Loch Laggan & reservoir Spey reservoir Loch Treig Loch Linnhe

  9. Schematic of the Lochaber Scheme Gravity Inflows Surge Chamber Gravity Inflows Spill Spill Spill tunnel tunnel Power-house tunnel Tailrace Penstocks Loch Laggan & reservoir Spey reservoir Loch Treig Loch Linnhe

  10. Schematic of the Lochaber Scheme Gravity Inflows Surge Chamber Gravity Inflows Spill Spill Spill tunnel tunnel Power-house tunnel Tailrace Penstocks Loch Laggan & reservoir Spey reservoir Loch Treig Loch Linnhe

  11. Schematic of the Lochaber Scheme Gravity Inflows Surge Chamber Gravity Inflows Spill Spill Spill tunnel tunnel Power-house tunnel Tailrace Penstocks Loch Laggan & reservoir Spey reservoir Loch Treig Loch Linnhe

  12. Schematic of the Lochaber Scheme Gravity Inflows Surge Chamber Gravity Inflows Spill Spill Spill tunnel tunnel Power-house tunnel Tailrace Penstocks Loch Laggan & reservoir Spey reservoir Loch Treig Loch Linnhe

  13. Schematic of the Lochaber Scheme Gravity Inflows Surge Chamber Gravity Inflows Spill Spill Spill tunnel tunnel Power-house tunnel Tailrace Penstocks Loch Laggan & reservoir Spey reservoir Loch Treig Loch Linnhe

  14. Simplified Lochaber Scheme Model Qintakes Qintakes QLin QLspill QTin QTspill QLin QTunnel QLin QP/H QTin Treig Laggan

  15. Energy Modelling Results

  16. Scheme Operating Capability Diagram Average Operation 9.3 % Q 90.7 % Q No Gravity Inflows 0 % Q 100 % Q Max. Gravity Inflows 100 % Q 0 % Q

  17. Turbine Selection The steps towards to turbine selection were: • Analysis of historical data of scheme operation • The number of generating units was selected – 5 • Analysis of operating data from scheme model • Performance data from tendering suppliers was fed into the scheme model

  18. Penstock works Key aspects of the penstock works were: • Need to undertake the works minimising shutdown of generation. • Existing penstock system was very complex. • In order to maintain double isolation, the penstocks needed to be dewatered sequentially. • The works were complex with poor access. • Decision with RTA to laser scan the penstock system and create a 3-D model.

  19. Penstock works Key aspects of the penstock works were: • Need to undertake the works minimising shutdown of generation. • Existing penstock system was very complex. • In order to maintain double isolation for the penstocks needed to be dewatered sequentially. • The works were complex with poor access. • Decision with RTA to laser scan the penstock system and create a 3-D model.

  20. Project Summary • The generating plant has been replaced to give 25+ years life extension. • The water to wire efficiency has been improved from 75% to 90+%. • Energy production increased from 460 GWh/yr to 600+ GWh/yr. • The scheme’s capability is better understood and limitations identified. • The scheme was completed ahead of schedule and is operating successfully with minimal disruption to Smelter operations during construction

  21. Thank you for your kind attention Contact Details Andrew Thick BEng CEng MIMechE URS Infrastructure and Environment UK Limited International House, Dover Place Ashford Kent TN23 1HU United Kingdom Tel: +44 (0) 1233 658200 hydropower@urs.com

More Related