1 / 21

Module 4 Footing & Foundation Inspection I

ARC313 Building Code II. Module 4 Footing & Foundation Inspection I. Review. What does volume 2 of the OBC help you with? specifics as to assemblies for different materials, visual details for some assemblies and more detailed / clarifications of different parts of the code

min
Télécharger la présentation

Module 4 Footing & Foundation Inspection I

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ARC313 Building Code II Module 4Footing & Foundation Inspection I

  2. Review • What does volume 2 of the OBC help you with? • specifics as to assemblies for different materials, visual details for some assemblies and more detailed / clarifications of different parts of the code • help designers with fire separations, assembly information, load calculation information

  3. Review • What is the code requirement for excavation, in regards to freezing and what clause is it? • the bottom of excavations shall be kept from freezing throughout the entire construction period • 9.12.1.3.(1)

  4. Review • Can a foundation be placed on organic material and what clause is it? • NO, the bottom of every excavation shall be free of all organic material • 9.12.1.1.(3) • What is angle of repose? • angle of repose is the steepest angle which the surface of a mass of loose material makes with the ground

  5. Review • If your foundation is below the footing of an adjacent building what must be done and what division and clause gives you that information? • the foundations shall be designed by a professional engineer • Division C – 1.2.1.1.(5)

  6. Review • What are 4 requirements that must be taken in consideration when it comes to excavation for a foundation? • minimum depths of foundations • water on site • soil type • freezing conditions

  7. Module 3 exercise #3M3:1

  8. Module 3 exercise #3M3:2

  9. Module 3 exercise #3M3:3

  10. Module 3 exercise #3M3:4

  11. Module 3 exercise #3M3:5

  12. Footing & Foundation Inspection I Soil Conditions • soil type maps are available to engineers for design calculation purposes • stiff clay ( Windsor area ) has a bearing pressure of 150 kPa or 3130 psf • see 9.15.1.1 for minimum soils bearing capacity

  13. Soil types in Essex County

  14. Soil types in Essex County

  15. Bore hole

  16. Soil Conditions • see 9.4.4.1 table for allowable bearing pressure for soil or rock • when buildings are going to be built on soil condition that do not meet minimum bearing capacity (75 kPa), Division B, Part 4.2.4 Design Requirements applies • if angle of repose for soil becomes a concern, Division C, Part 1.2.1.1(5) applies

  17. Questionable soils 9.4.4.1.(3) (c) • Caution when excavating and the following is observed: • cans, tires, construction materials are exposed • soil discolouration • water that occurs when there has been no rainfall • If the above is observed a geotechnical expert should be retained to: • verify of adequacy of the particular design • report actual bearing capacity of the soil • confirm location of water table at the site

  18. Plain Concrete Footings • Part 9 allows the design of footings to be un-reinforced concrete in such a way that shear reinforcing will not be required which simplifies the process of building footings • Minimum 100mm (4”) by code • CAN/CSA-A23.3-04 200mm (8”) • Division A 1.5.1.2.(1) says that if there is conflict between standards that, the building code prevails

  19. General Qualities of Concrete • The higher the strength does not mean it is good concrete. • A concrete that will last over time and resist wear has to have: • good quality aggregate • optimum amount of Portland cement • minimum amount of water • +/- 6% air entrainment

  20. Concrete mix design should have • acceptable workability • strength • durability • good appearance • economy/cost (see Figure M4:1) • Factors that contribute to good quality concrete • low water to cement ratio (see figure M4:2) • air entrainment • quality materials • adequate curing • good construction practices

  21. Concrete mix design • Concrete with too much water will be: • porous • weak • shrink more • segregate and honeycomb • poor appearance • prone to water leakage • not economical See figure M4:3