El Chaguite : Water Storage Tank

El Chaguite : Water Storage Tank. Date of EWB Honduras Meeting: January 26 th , 2010 By Ryan Mahoney. El Chaguite Population: 333 people. West Tank. Existing Tank. Transmission Main. Source. Proposed Tank Site. Existing Tank Site. Project: El Chaguite Water System. 3. Project Schedule.

minh
Télécharger la présentation

El Chaguite : Water Storage Tank

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. El Chaguite: Water Storage Tank Date of EWB Honduras Meeting: January 26th, 2010 By Ryan Mahoney Project: El Chaguite Water System

  2. El ChaguitePopulation: 333 people West Tank Existing Tank Project: El Chaguite Water System

  3. Transmission Main Source Proposed Tank Site Existing Tank Site Project: El Chaguite Water System 3

  4. Project Schedule Project: El Chaguite Water System

  5. El Chaguite: Phase I Project: El Chaguite Water System

  6. Design Process • Excel water flow model • WaterGEMS flow model • Multi-phase implementation • Phase 1 (COMPLETE) • Construct Transmission Main • Instruct villagers on construction of distribution system • Build break pressure tank (float-valve tank) • Phase 2 • Water storage tank • Inspect village-constructed distribution system Project: El Chaguite Water System

  7. First Step:How much water they need… Project: El Chaguite Water System

  8. Demand Schedule: • Water Source : 15.52 gpm (22,348 gallons/day) • 25 year projected demand: 12,755 gpd +4,350 gpd (Irrigation use) 17,105 gpd • Diurnal Demand Cycle Project: El Chaguite Water System

  9. Sizing - Spreadsheet Project: El Chaguite Water System

  10. Sizing - Graph Project: El Chaguite Water System

  11. Sources Project: El Chaguite Water System

  12. Assumptions Project: El Chaguite Water System

  13. Tank Design Under guidance of Professor Sasani

  14. Tank Wall

  15. Walls: Horizontal Rebar Project: El Chaguite Water System

  16. Walls: Vertical Rebar Project: El Chaguite Water System

  17. Tank Foundation

  18. Foundation Design

  19. Foundation – Wall Interface

  20. Tank Roof

  21. Tank Inlet and Outlet

  22. Preguntas? Project: El Chaguite Water System