PERKIRAAN BIAYA PROYEK

PERKIRAAN BIAYA PROYEK. FUNGSI: Penyelengara : u/ mengetahui besar biaya investasi, merencanakan sumberdaya dan waktu, mengendalikan sumberdaya & waktu. Pemilik (owner): patokan …………………..perkiraan biaya. Kontraktor : keuntungan finansial

minnie
Télécharger la présentation

PERKIRAAN BIAYA PROYEK

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PERKIRAAN BIAYA PROYEK FUNGSI: • Penyelengara : u/ mengetahui besar biaya investasi, merencanakan sumberdaya dan waktu, mengendalikan sumberdaya & waktu. • Pemilik (owner): patokan …………………..perkiraan biaya. • Kontraktor : keuntungan finansial perkiraan biaya tinggi ……………...kalah, perkiraan terlalu rendah………kesulitan. • Konsultan : kredibilitas….ketepatan harga estimet, usulan harga terbaik.

  2. PERKIRAAN BIAYA : The art of approximating kemungkinan jumlah biaya yang diperlukan untuk suatu kegiatan didasarkan atas informasi terkini. • ANGGARAN BIAYA : Perencanaan rinci perkiraan biaya dari kegiatan yang dikaitkan dengan waktu.

  3. TOTAL BIAYA PROYEK: BIAYA INVESTASI = FIXED CAPITAL + WORKING CAPITAL • FIXED CAPITAL = MODAL TETAP BAGIAN BIAYA PROYEK MEMBANGUN INSTALASI/PRODUK PROYEK, MULAI DARI SURVEY, DESIGN ENG, PENGADAAN FABRIKASI, KONSTRUKSI SAMPAI PROYEK BERFUNGSI PENUH terdiri dari : • DIRECT COST (BIAYA LANGSUNG) • INDIRECT COST (BIAYA TAK LANGSUNG) • WORKING CAPITAL = MODAL KERJA UNTUK MENUTUPI KEBUTUHAN PADA TAHAP AWAL OPERASI.

  4. KOMPONEN BIAYA PROYEK TOTAL BIAYA PROYEK MODAL KERJA MODAL TETAP BIAYA LANGSUNG BIAYA TAK LANGSUNG

  5. METODA PERKIRAAN BIAYA • METODA PARAMETRIK • DAFTAR INDEKS & INFO TERDAHULU • METODA ANALISIS UNSUR UNSUR • METODA FAKTOR • QUANTITY TAKE OFF & HARGA SATUAN • UNIT PRICE • DATA & INFO PROYEK

  6. METODA PARAMETRIK KURVA LINER Y = biaya (variabel cost) x = variabal fisik a = parameter yg menerangkan hub. Y dgn x q = komponen tetap px= komponen variabel y y q Y = ax x y Y=ax x Y = px + q y Y=px + q q x

  7. b) KURVA PANGKAT Y2 = Y1 [X2 / X1]n Y biaya y Y2 =Y1[X2/X1]n Y1 = biaya pembangunan instalasi A Y2 = biaya pembangunan instalasi B X1 = kapasitas instalasi A X2 = kapasitas instalasi B n = indeks harga (= 0,60) Kapasitas produksi

  8. MEMAKAI INDEKS HARGA (COST INDEX) I = 0,37 Im + 0,081 Ie + 0,10 Ic + 0,19 Is + o,26 Io HARGA TH A = HARGA TH B [INDEK HARGA TH A / INDEK HARGA TH B] dimana I = total (komposit) indeks Im = indeks engineering mekanik Ie = indeks engineering listrik Ic = indeks engineering sipil Is = indeks engineering site (lapangan) Io = indeks overhoul

  9. Tabel : Daftar indeks harga (dari penerbit)

  10. METODE FAKTOR PCE = HARGA PENGADAAN PERALATAN UTAMA (sampai di lokasi) SISTEMATIKA : 1 2 3 4 5 PERALATAN TERPASANG PPC = PCE (1+I1+I2+……+ In) Diperhitungkan faktor pemakaian material dan jam-orang Sampai peralatan berfungsi MODAL TETAP FCC = PPC (1 + fe + fc + ff) Diperhitungkan faktorbiaya engineering, Kontingensi, dan fee MODAL KERJA = 5 % s.d 10 % ( MODAL TETAP FCC) TOTAL BIAYA PROYEK = MODAL TETAP + MODAL KERJA

  11. RUMUS LANG RUMUS LANG MENYEDERHANAKAN PENDEKATAN DIATAS DENGAN MENGGUNAKAN FAKTOR LANG YAITU: MODAL TETAP = FL x PCE dimana : PCE = harga pembelian peralatan utama FL = Faktor Lang FL = 3,1 untuk instalasi jenis proses material padat FL = 4,7 untuk instalasi jenis proses material fluida / cair FL = 3,6 untuk instalasi jenis proses campuran padat – cair

  12. RUMUS HIRSCH & GLAZIER I = E [ A (1 + Fl + Fp + Fm) + B + C] dimana : I = total investasi A = total biaya pembelian-fob B = total biaya terpasang C = biaya material alloy anti korosi E = biaya tidak langsung (indeks = 1,4) Fl = faktor biaya tenaga kerja Fp= faktor biaya insrumen, isolasi, dll. Fm=faktor biaya untuk pipa

  13. selesai terima kasih