This document outlines the summary of operations from November 25 to December 2, 2013, detailing the performance and intensity metrics of various beam operations including NuMI, BNB, NMuon, and MTest. During this period, NuMI delivered 4.84E18 protons, while BNB and NMuon provided 5.63E18 and 1.99E15 protons respectively. The report also highlights various technical issues, such as a vacuum instability and ongoing maintenance work, along with plans for continued improvements and system upgrades.
E N D
All Experimenters’ Meeting December 2, 2013 Photo by Martin Murphy
Accelerator Operation Summary From : November 25, 2013 (0000 hours) To: December 02, 2013 (0000 hours) Calendar Week # 48 NuMI Weekly Integrated Intensity 4.84 E18protons * Beam Hours To NuMI 156.6hours * 2 days of low intensity operation BNB Weekly Integrated Intensity 5.63 E18protons Beam Hours To BNB 156.5hours NMuonWeekly Integrated Intensity 1.99 E15protons Beam Hours To NMuon138.8 hours MTest Weekly Integrated Intensity 3.73 E13 protons Beam Hours To MTest72.3 hours
Status /Work Completed/Plans • Proton Source • RIL: • Source A instability due to LEBT vacuum • Changed sources this morning • Booster: • Vacuum burst in over weekend • Leak check scheduled for this week • Install BRF8 cavity on Wednesday • Main Injector • 2 day access Wednesday & Thursday • Q229 replacement • Recycler • 2 day access Wednesday & Thursday • Lambertson work • 901 BV replacement • BNB • Monitored temperature probe for 50 meter absorber area • NuMI • ~ 2 days of 2e12 p/p • MTest • Experiment T-979 & T-1015 online • NMuon • G2SEM foil calibration this week
Status /Work Completed/Plans • 2 day access • Wednesday & Thursday • Beam off ~ 0400 • Bstr : BRF8 install • MI: Replace Q229 • RR: Lambertson, 901 BV
Schedules and Links: • Schedule can be accessed from the Operations Home Page • - Schedules -> Operations Schedule • Direct link to schedule • - http://www-ad.fnal.gov/ops/schedule.html