An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Updates on Tevatron and LARP Vladimir Shiltsev FNAL/Accelerator Physics LARP/Accelerator Systems

  2. In short Yesterday, CDF Detector celebrated 2fb-1 of data delivered !  FY07 goals ~1750 / 760 pb-1 Delivered by Nov.1 50 pb-1 FY06 goals 725 / 580 pb-1 Delivered 620 pb-1 APEX Mtg 11/02/2006 - Shiltsev

  3. Pbar production task force initiated Dec-Feb 2006 Best luminosity before shutdown: 171e30 cm-2s-1 25 pb-1/week Shutdown to Upgrade D0 detector Mar-June 2006 Fast start up (<2 weeks) Rush of records: 171182191205228229e30 Current best: store 229.0e30 (avg CDF & D0) week 33pb-1 month ~120pb-1 Average store 27-32 hrs (longest 54hrs), ~120-130 hrs/week 36x36 bunches ~270e9 p/bunch, 60-80(max) pbars/bunch Details APEX Mtg 11/02/2006 - Shiltsev

  4. Reduction of beta* to 28 cm Sep’05 ~8 % Pbar production task force Feb’06 ~10 % Tevatron 150 GeV helix more p June’06 ~10 % Tev collision helix  lifetime July’06 ~15 % New RR WP  emittances, loss Sep’06 ~25 % D0 luminosity counters rescaled Oct’06 15/2=8% Improvements over last ~1yr APEX Mtg 11/02/2006 - Shiltsev

  5. Content APEX Mtg 11/02/2006 - Shiltsev

  6. Pbar production (not cooling!) : still less 20e10/hr Beam-beam effects in Tevatron: Ksi~0.025 for pbars  losses/emittances Ksi ~0.015 for protons  losses/emittances Availablity: component failures no L time 10/30/06 - ??11/08/06?? Tev Cryo vacuum 10/09/06 - 10/23/06 Tevatron Q,D,spool 02/23/06 - Tev magnet failure , early Shtdn start 01/14/06 - 01/27/06 Tev magnet 01/03/06 - 01/06/06 AA magnet 11/22/05 - 12/12/05 Tevatron magnet Plus, power glitches, etc: Jul-Aug’06: 45 stores , 15 aborts/quenches Sep-Oct’06: 36 stores , 17 aborts/quenches Major Limitations APEX Mtg 11/02/2006 - Shiltsev

  7. Content APEX Mtg 11/02/2006 - Shiltsev

  8. Pbar production: AA optics Faster AA to MI to RR transfers (<15 min) Pbar Target optimization New Tevatron WP: To improve luminosity lifetime (less losses, no dEmm) Allow higher Np and Na Next Steps (till ’09?) (yr?) V.Lebedev APEX Mtg 11/02/2006 - Shiltsev

  9. Content APEX Mtg 11/02/2006 - Shiltsev

  10. STATE of LARP …after • Doe Review Jun’06 • LHC Upgrades Workshop in Spain, Oct’06 • LARP Collaboration Meeting at BNL, Oct’06 • Executive Committee Mtg, Oct’06 APEX Mtg 11/02/2006 - Shiltsev

  11. LARP Accel Systems Progress ‘06 • Schottky being baked, will go into LHC tunnel • TCFB: success at SPS • 4 long-term hardware commissioners @CERN • SLAC joins commissioning forces • LHC@FNAL to open in Nov’07, new - LAFS • RC work at full speed, a lot of changes, delay • SPS beam studies: BBQ PLL, Q’ head-tail, bent crystal, etc • Wires built for RHIC tests • # of LARP presentations at Valencia workshop APEX Mtg 11/02/2006 - Shiltsev

  12. 4.8GHz Schottky Detector APEX Mtg 11/02/2006 - Shiltsev

  13. PLL Success on SPS Ramp APEX Mtg 11/02/2006 - Shiltsev

  14. 2007 – First Year of “Deliverables” • “Hard deliverables” are the projects which CERN needs but can not back-up itself in case of failure (thus, special attention and protection needed): • Lumi Monitors for 2 IPs (2007) • Tune Feedback (2007) • Beam Commissioning (2007-2009-beyond) • Phase II rotating collimators prototype (2009) APEX Mtg 11/02/2006 - Shiltsev

  15. Accelerator Systems FY07 Priorities • Lumi-Monitors: construct, install, start commissioning • Tune&Coupling FB: deliver design, participate in installation and commissioning • Schottky: participate in installation and commissioning • Hardware Commissioning: execute current plan – SAFELY! • Beam Commissioning: develop acceptable/detailed execution plan for FY08+ by ~mid-07 (more from BNL!) • Physics experiments: RHIC (BBLR), Tevatron(PLL), ecloud • Other tasks: execute Task Sheet’s Plans APEX Mtg 11/02/2006 - Shiltsev

  16. CARE–HHH: upgrades discussed • IR Upgrade: • both quad first paths NbSn, NbTi • Magnet R&D… Magnet R&D…MagnetR&D • D0 3.5m from IP • <1mrad Crab Crossing not excluded • Low cost, potential high gain: • low-noise feedback • collimator schemes (RC, LEL, Crystals) • beam-beam compensation schemes (W,LEL) • Upgrade of Injector Chain: • new Linac, PS+, PS2 • SPS+ incl. SF-SPS APEX Mtg 11/02/2006 - Shiltsev

  17. wires (2.5m long) with strong-back (-profile)7 support points NEG coated chambersduring assembly RHIC BBLR wires – assembly APEX Mtg 11/02/2006 - Shiltsev

  18. Things not in FY’07 budget Project Reason • Longitudinal Density Monitor budget • Fast Magnet Ramp Measurement System budget • Crab Cavity – hardware part budget • E-lenses budget • Bent Crystal collimation (see below) too early • LER-LHC 1.5TeV (see below) little $$ • Optical Stochastic Cooling too big for LARP APEX Mtg 11/02/2006 - Shiltsev

  19. Summary: • DoE Review was (overall) successful • LTVAC started • Instrumentation tasks are of the highest priority in FY’07 • Constrained by budget, #of tasks dropped • Plans to further improve CERN-LARP communication APEX Mtg 11/02/2006 - Shiltsev