140 likes | 445 Vues
PMI North Area PMP Exam Study Group . Risk Presentation Prepared by Denise Robertson 15 March 2003. Risk Management Processes. Process I/O and Tools/Techniques emphasized on exam, so memorize them Memorize process in order: Risk Management Planning Risk Identification
E N D
PMI North Area PMP Exam Study Group Risk Presentation Prepared by Denise Robertson 15 March 2003 Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Risk Management Processes • Process I/O and Tools/Techniques emphasized on exam, so memorize them • Memorize process in order: • Risk Management Planning • Risk Identification • Qualitative Analysis • Quantitative Analysis • Risk Response Planning • Risk Monitoring and Control Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Risk Concepts • Risk tolerance • Risk adverse • Risk factors • Probability • Impact • Range of possible outcomes • Expected timing in project life cycle Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Unknowns • Risks are also called “Unknowns” • “Known Unknowns” are identified during Risk Management and are documented in the project plan • Can be planned for with Risk Response • “Unknown Unknowns” are unanticipated risks • Cannot be planned for in advance Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Policy Level • Organization’s Risk Management Policy on how to approach risk is now part of PMBOK • Policy describes: • Level of tolerance • Level of acceptable risk Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Project Status • 3 possible statuses: • In Jeopardy • Committed to • Approved Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Risk Probability/Impact Matrix • 2-D rating system that rates: • Likelihood (probability) of a risk occurring between 0.0 and 1.0 or 100% certainty • Impact of risk should it occur • Impact scale can be • Ordinal (ordered) • Cardinal (assigned numeric values) • Risk Score = Probability * Impact Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Evaluating Project Data for Use in Assessing Risk • Assumption Testing Criteria: • Stability of assumption • Impact to project if assumption proves false • Data Precision Ranking Accuracy Dependencies: • Extent risk is understood • Data available about risk • Quality of data • Reliability and integrity of data Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Monte Carlo Simulation • Used in Quantitative Risk Analysis and Cost Analysis • Evaluates the project, not the tasks, however: • Provides probability of completing project on any specific day or for any specific task • Provides probability of any task actually being on the critical path • Provides percent probability that each task will be on critical path • Takes into account path convergence • Translates uncertainties into impacts to total project • Can be used to assess cost and schedule impacts • Results in probability distribution Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Decision Tree Analysis • Quantitative Analysis Tool • Diagram describes decision and probabilities associated with choices • Determines aggressive or conservative route to highest Expected Monetary Value (EMV) • Total of Probabilities * Consequences for a Choice Event = EMV Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Cost Reserve • PMI recommends at least 10% OR • Based on EMV: • Total of Probability * Risk Cost for all risks • Remember risk can be negative or positive Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Risk Response Techniques Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials
Residual and Secondary Risks • Outputs from Risk Response Planning • Residual Risks are those that remain after Avoidance, Transference, and Mitigation have been taken. • Secondary Risks arise as a direct result of implementing a risk response • Secondary risks should be identified and responses planned Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials