1 / 34

The FMOS Facility for the SUBARU telescope

The FMOS Facility for the SUBARU telescope. Gavin Dalton Oxford/RAL. Overview of F ibre M ulti O bject S pectrograph project for the Subaru telescope. Masayuki Akiyama (Subaru Telescope, NAOJ) on behalf of FMOS team (P.I. Toshinori Maihara). FMOS: instrument overview.

myrrh
Télécharger la présentation

The FMOS Facility for the SUBARU telescope

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The FMOS Facility for the SUBARU telescope Gavin Dalton Oxford/RAL

  2. Overview ofFibreMultiObjectSpectrographproject for the Subaru telescope Masayuki Akiyama (Subaru Telescope, NAOJ) on behalf of FMOS team (P.I. Toshinori Maihara)

  3. FMOS: instrument overview

  4. FMOS: project overview

  5. FMOS: prime-focus corrector • Prime-focus corrector designed and fabricated by AAO • Three BSM51Y design with F/2.0 and 30arcmin diameter FoV. • Image quality optimized between 0.9-1.8micron

  6. FMOS: fibre positioner • If we put 400 magnetic buttons with fibres (like 2dF) on the prime-focus of the Subaru telescope, it would be like,,, • So we need new fibre positioning method for FMOS… 145mm = 30arcmin

  7. FMOS:Echidna: 1998 Birth of Echidna concept • Concept by Peter Gillingham (AAO) shown at SPIE@Kona • Tiling the focal plane with 400 of them = 7mm x 7mm each

  8. FMOS:Echidna:Long-term development effort • 1998 Echidna with “Nano-motor” • 1999 Echidna with “inch-worm” design • 2000 Echidna with “ball-spine” design

  9. FMOS:Echidna: 2001 Final design fixed “Stick-and-slip” motion with sawtooth voltage signal

  10. FMOS:Echidna: Under testing in Hilo • Focal plane with 480 fibres.

  11. FMOS:Echidna: Under testing in Hilo • Focal plane imager.

  12. FMOS:Echidna: Under testing in Hilo • Positioner unit • SEE ECHIDNA THE MOVIE !!

  13. Movies

  14. FMOS:Echidna: test results so far • Focal plane imaging camera tested. Positions of 400 fibres in 154mm FoV can be measured with 2-3micron r.m.s. accuracy. • Configuration accuracy of 10micron (corresponds to 0.12 arcsec. Fibre core is 100micron, i.e. 1.2”) can be achieved for >95% of the 400 fibres with 7 iterations in 11minutes. • Fibre tip is 30micron r.m.s. from the focal plane.

  15. FMOS: prime-focus unit (PIR) • New prime focus unit with • instrument focusing unit (Z-movement) • corrector lens adjustment mechanism (XY-movement) • cable wrapping unit • for FMOS is constructed by Kyoto Univ. and Mitsubishi.

  16. FMOS:PIR+Echidna under testing NOW

  17. FMOS: fibre train with connector • Fibre trains with • 120mm 200 fibres/slit • strain relief boxes • F2/F5 conversion air connector • fibre back illumination system • was designed and fabricated in Durham. • F5-side fibre • F2-side fibre

  18. FMOS: fibre train with connector N.B. some of the tolerances on these lenses turn out to be difficult!

  19. How to map ECHIDNA to spectrographs?

  20. FMOS: fibre train with connector A lot of attention has been paid to cable management!

  21. The FMOS Spectrographs Gavin Dalton Oxford/RAL

  22. Spectrograph outline • 2 bench-mounted spectrographs (total slit length is ~700 arcseconds). • Optics cooled to ~200K, with articulated cryogenic cameras • OH suppression by masking lines at intermediate focus. • Full ZYJH wavelength coverage in 4 shots at suppression resolution • Full coverage in 1 shot through redispersing VPH grating

  23. Why OH Suppression? Because the IR sky is rather nasty… Can work between the lines, but then we start to run out of pixels to do anything useful with this wonderful wide field!

  24. Accomodation Issues • No space for systems of this size in any convenient location • Extra floor added to Subaru enclosure on IR side above the Nasmyth platform • Limited access (spectrogaphs must be assembled in situ) • Cost…

  25. Spectrograph Design

  26. Predicted performance

  27. Installation (two weeks ago)

  28. Installation (two weeks ago)

  29. Installation (two weeks ago)

  30. FMOS Commissioning Schedule • Near future mile-stones(first discussions on this project were 01/97!) • 2007/10 Transfer IR prime-focus unit (PIR) and Echidna fibre positioner to summit • 2007/12 Engineering observations of IR prime-focus unit • Check image quality • Check Auto-Guiding/Shack Hartmann system • 2008/01 Engineering observation of Echidna fibre positioner • Check positioning accuracy (spectrographs available) • 2008/02 Start engineering observation with two spectrographs • 2008/?? Open use observation with shared risk mode/GTO

  31. So what can we do? • 20 nights GTO: Galaxy evolution survey, ~15000 ‘good’ spectra from e.g. UDS (Interesting possibility would be to cover the DEEP2 AEGIS area?). • Opportunity for a large programme (few x 105 redshifts). –See Totani’s talk. • Whatever else comes up?

More Related