An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WBS 7.2 & 7.3:Data Acquisition D. Casper (UC Irvine)

  2. Outline • WBS 7 Components • Design Specifications • Design Issues and Concerns • Progress to Date and Near Term Plans • Cost and Schedule Overview • Cost and Schedule Issues and Concerns • Conclusions Electronics and DAQ

  3. WBS 7.2 & 7.3: DAQ • CROCs and DAQ (7.2, 7.3) • One CROC per 48 MAPMTs • Each CROC controls 4 LVDS chains of 12 MAPMTs • Three VME crates + computer • Two crates for CROCs • One crates for auxiliary electronics • Front-end/computer interface • Distribute trigger and synchronization from NuMI • Monitor and control MAPMT high-voltages • Configure front-end electronics Electronics and DAQ

  4. Specifications • Synchronization • Measure global time (between front-end boards) to a few nanoseconds • Trigger • Tap into NuMI timing signals through MINOS • Readout • Handle rates up to 1 kHz (for PMT testing and calibration) • Control • MAPMT HV control and monitoring • Configuration of front-end board firmware Electronics and DAQ

  5. Design Issues and Concerns • CROC Design • Not technically challenging, but requires EE time • Triggering and Synchronization • Need to flesh-out interface with NuMI and MINOS • Understand what auxiliary electronics are required • Investigate possibility of self-triggering • Firmware issue? • Readout • Requirements for PMT testing unspecified • Requirements for Veto Wall unspecified Electronics and DAQ

  6. Progress to Date/Near-Term Plans • Progress • LVDS chaining tested successfully (between front-end boards only) • Protocol and Frame for LVDS communications successfully tested (Christian Gingu) • Designed to be forward compatible with full required functionality • Near Term Plans • Begin design of CROC prototype as soon as possible • Procure VME system for testing and writing low-level readout software Electronics and DAQ

  7. Cost and Schedule Overview (I) Electronics and DAQ

  8. Cost and Schedule Overview (II) • Current schedule is out of date • e.g. CROC design did not begin on 6/1/05 and will not be completed on 9/20/05 • Projected Schedule • CROCs: • Should begin design as soon as possible • Finish production and testing of prototype by July ’06 • VME Readout System • Procurement of VME test system scheduled for October 2005 • Need to complete paperwork for UC Irvine MoU, etc. Electronics and DAQ

  9. Cost and ScheduleIssues and Concerns • PMT Testing (WBS 6) Drives Our Schedule • Need to understand required components and coordinate schedules • M&S costs for CROC prototypes (7.2.3) underestimated (need more than two) • Auxiliary Electronics • MINOS timing module for NuMI synchronization not explicitly included in WBS • Veto Wall DAQ Requirements (if any) Unspecified • Electronics Design • Paul is unavailable until roughly 1/06 • Design of CROC prototype should start as soon as possible • Should request EDIA time from another EE Electronics and DAQ

  10. Conclusions • Base Cost: $349,464 (total, no contingency) • M&S: $210,310 • Labor: $139,154 • Need to update after confirming the number of prototypes needed • Highest Contingency Items: • CROC production: 50%  $48,000 = $24,000 • Need a concrete design • Other M&S contingencies are nominally 20% • Based on old quotes, need to update • Unspecified auxiliary electronics • No big-ticket items, but potentially a number of smaller ones • Schedule Risks: • CROC design should begin as soon as possible, in parallel with front-end work • Not a significant technical risk • Only serious constraint is PMT testing • Understand the WBS 6 schedule and requirements Electronics and DAQ